ACTIVE / OPERATOR PORTFOLIO

WARRIOR COAL LLC

Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.

MSHA OPERATOR IDP24534

MINE PORTFOLIO

2 of 2 mines and facilities

2025-01-01 – 2026-10-18. Active records; production reporting is not required.

MineLocation / typeCoal · short tonsHours workedViolationsAccident recordsOn-site inspection hours
CARDINAL1517216 · Active6/8 quarters reportedHopkins, KYUnderground · MSHA: Coal (Bituminous)6,732,3141,639,1251,0937610,522.3
Warrior Preparation Plant1514335 · Active6/8 quarters reportedHopkins, KYFacility · MSHA: Coal (Bituminous)0124,119100354.5

LOCATION

Portfolio map

2 of 2 mines with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-18Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

1,103

271 significant & substantial (S&S)

  1. 2025 Q1109
  2. 2025 Q2204
  3. 2025 Q3166
  4. 2025 Q4148
  5. 2026 Q1156
  6. 2026 Q2159
  7. 2026 Q3134
  8. 2026 Q4 *27

Accident records

76

0 records classified as fatality

  1. 2025 Q114
  2. 2025 Q27
  3. 2025 Q39
  4. 2025 Q49
  5. 2026 Q112
  6. 2026 Q213
  7. 2026 Q312
  8. 2026 Q4 *0

Proposed penalties · USD

590,232.00

1,023 of 1,103 violations with amounts

  1. 2025 Q163,502
  2. 2025 Q299,854
  3. 2025 Q387,077
  4. 2025 Q4120,698
  5. 2026 Q198,144
  6. 2026 Q271,468
  7. 2026 Q349,489
  8. 2026 Q4 *—

On-site inspection hours

10,876.75

197 inspections · 197 with hours

  1. 2025 Q11,267.50
  2. 2025 Q21,581.50
  3. 2025 Q31,634.50
  4. 2025 Q41,675.00
  5. 2026 Q11,641.50
  6. 2026 Q21,529.25
  7. 2026 Q31,398.25
  8. 2026 Q4 *149.25
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q11093363,502.00140301,267.5
2025-Q22044499,854.0070221,581.5
2025-Q31663387,077.0090291,634.5
2025-Q414845120,698.0090291,675.0
2026-Q11564098,144.00120251,641.5
2026-Q21593471,468.00130301,529.3
2026-Q31343549,489.00120281,398.3
2026-Q4 *277—004149.3

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. violation5045269
    CARDINAL · 1517216

    75.517 · S&S

  2. violation5045268
    CARDINAL · 1517216

    75.370(a)(1)

  3. violation5221272
    CARDINAL · 1517216

    75.325(f)(3) · S&S

  4. violation5221001
    CARDINAL · 1517216

    75.380(d)(7)(vi)

  5. inspectionF00AE9C
    CARDINAL · 1517216

    103(i) Spot Inspections · 6.3 on-site hours

  6. violation5045267
    CARDINAL · 1517216

    75.342(a)(4)

  7. violation5221271
    CARDINAL · 1517216

    75.604(b) · S&S

  8. violation5221270
    CARDINAL · 1517216

    75.517 · S&S

  9. violation5221215
    CARDINAL · 1517216

    75.370(a)(1)

  10. violation5221214
    CARDINAL · 1517216

    75.333(c)(3)

  11. violation5221213
    CARDINAL · 1517216

    75.1731(a)

  12. violation5221212
    CARDINAL · 1517216

    75.370(a)(1)

  13. violation5221269
    CARDINAL · 1517216

    75.1714-8(a)(2)

  14. violation5221268
    CARDINAL · 1517216

    75.517 · S&S

  15. violation5221267
    CARDINAL · 1517216

    75.512

  16. violation5221211
    CARDINAL · 1517216

    75.370(a)(1)

  17. violation5221266
    CARDINAL · 1517216

    Description not reported

  18. violation5221210
    CARDINAL · 1517216

    75.517 · S&S

  19. violation5221209
    CARDINAL · 1517216

    75.220(a)(1)

  20. violation5221208
    CARDINAL · 1517216

    75.604(b) · S&S

  21. violation5045266
    CARDINAL · 1517216

    75.362(g)(3)

  22. inspectionF00AE9B
    CARDINAL · 1517216

    103(i) Spot Inspections · 6.8 on-site hours

  23. violation5045265
    CARDINAL · 1517216

    75.342(a)(4)

  24. violation5221207
    CARDINAL · 1517216

    75.370(a)(1)

  25. inspectionF035D57
    CARDINAL · 1517216

    103(i) Spot Inspections · 7.3 on-site hours

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-18.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-07Source checked 2026-10-18 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS4,430,90851 rows · 5 receiving plants
HEAT CONTENT · BTU/LB12,379Weighted by reported tons
SULFUR / ASH · % BY WEIGHT3.05 / 8.94Separate averages over measured receipts
DELIVERED COST · USD/TON71.51100.0% of reported tons have usable costs
Quarterly receipts and quality
QuarterShort tonsHeat · Btu/lbSulfur %Ash %Delivered USD/ton
2025-Q3 *736,29812,3903.088.9872.29
2025-Q41,123,89712,3673.078.9071.44
2026-Q11,083,85912,3393.019.1271.20
2026-Q21,150,47012,4123.068.7971.72
2026-Q3 *336,38412,4063.058.9270.32
Month / sourceMineReceiving plant / supplierShort tonsDelivered USD/tonHeat · Btu/lbSulfur %Ash %PurchaseTransport
2026-01EIA row 251 · preliminaryCARDINAL1517216Mill Creek (KY)1364 · KY · ALLIANCE COAL130,63672.5612,4123.008.60ContractBITRail
2026-01EIA row 579 · preliminaryCARDINAL1517216Kingston3407 · TN · ALLIANCE COAL11,44889.3012,3103.009.20ContractBITRail
2026-01EIA row 1240 · preliminaryCARDINAL1517216Calvert City8837 · KY · ALLIANCE COAL88,93466.1512,2863.029.50ContractBITRail
2026-01EIA row 1241 · preliminaryCARDINAL1517216Calvert City8837 · KY · ALLIANCE COAL38,36475.7812,2542.979.30ContractBITRail
2025-12EIA row 33833 · finalCARDINAL1517216Seminole (FL)136 · FL · ALLIANCE COAL22,94972.2612,2403.089.40ContractBITRail
2025-12EIA row 34073 · finalCARDINAL1517216Mill Creek (KY)1364 · KY · ALLIANCE COAL173,83571.8712,4043.068.60ContractBITRail
2025-12EIA row 34509 · finalCARDINAL1517216Kingston3407 · TN · ALLIANCE COAL64,79297.9512,3153.089.20ContractBITRail
2025-12EIA row 35544 · finalCARDINAL1517216Calvert City8837 · KY · ALLIANCE COAL129,17764.0512,3083.069.20ContractBITRail
2025-11EIA row 30851 · finalCARDINAL1517216Seminole (FL)136 · FL · ALLIANCE COAL35,53172.1012,3203.169.10ContractBITRail
2025-11EIA row 31087 · finalCARDINAL1517216Mill Creek (KY)1364 · KY · ALLIANCE COAL164,06371.7212,4263.058.60ContractBITRail
2025-11EIA row 32529 · finalCARDINAL1517216Calvert City8837 · KY · ALLIANCE COAL129,50263.2612,3453.059.00ContractBITRail
2025-11EIA row 32570 · finalCARDINAL1517216Four Rivers Terminal8899 · KY · ALLIANCE COAL26,14483.3712,2683.069.40ContractBITRail
2025-10EIA row 27877 · finalCARDINAL1517216Seminole (FL)136 · FL · ALLIANCE COAL12,37672.0012,3253.149.20ContractBITRail
2025-10EIA row 28119 · finalCARDINAL1517216Mill Creek (KY)1364 · KY · ALLIANCE COAL176,56371.1112,4283.098.60ContractBITRail
2025-10EIA row 28572 · finalCARDINAL1517216Kingston3407 · TN · ALLIANCE COAL34,85397.0412,3343.059.00ContractBITRail
2025-10EIA row 29597 · finalCARDINAL1517216Calvert City8837 · KY · ALLIANCE COAL101,80663.1812,3403.069.20ContractBITRail
2025-10EIA row 29630 · finalCARDINAL1517216Four Rivers Terminal8899 · KY · ALLIANCE COAL39,20862.5212,3463.059.10ContractBITRail
2025-10EIA row 29631 · finalCARDINAL1517216Four Rivers Terminal8899 · KY · ALLIANCE COAL13,09884.2212,3423.079.10ContractBITRail
2025-09EIA row 24789 · finalCARDINAL1517216Seminole (FL)136 · FL · ALLIANCE COAL27,37272.5212,3203.169.40ContractBITRail
2025-09EIA row 25049 · finalCARDINAL1517216Mill Creek (KY)1364 · KY · ALLIANCE COAL148,44870.6012,4433.078.70ContractBITRail
2025-09EIA row 25501 · finalCARDINAL1517216Kingston3407 · TN · ALLIANCE COAL58,01997.0912,3843.099.20ContractBITRail
2025-09EIA row 26539 · finalCARDINAL1517216Calvert City8837 · KY · ALLIANCE COAL130,53163.3012,3443.069.30ContractBITRail
2025-08EIA row 21631 · finalCARDINAL1517216Seminole (FL)136 · FL · ALLIANCE COAL13,68772.4912,3153.119.30ContractBITRail
2025-08EIA row 21889 · finalCARDINAL1517216Mill Creek (KY)1364 · KY · ALLIANCE COAL147,26370.4112,4103.118.70ContractBITRail
2025-08EIA row 22347 · finalCARDINAL1517216Kingston3407 · TN · ALLIANCE COAL69,26097.0112,3873.109.10ContractBITRail
Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_07_2026_21SEP2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

Latest priced year: 2024Source checked 2026-10-18. Prices apply only to their calendar year.

FOB PRICE BENCHMARK · USD/TON—Weighted by estimated sales of covered mines
ESTIMATED SALES · SHORT TONS—Allocated from published county sales
ESTIMATED COAL REVENUE · USD—Covered mines only · not reported revenue
ANNUAL PRODUCTION COVERED0.0%0 of 1 producing annual mine records
Mine / countyAnnual production · tonsCounty FOB · USD/tonEst. sales · tonsEst. coal revenue · USDBasis / availability
Warrior Preparation Plant1514335 · Hopkins, Kentucky0———Preparation plant1 eligible mines / 1 sales respondents
Cardinal1517216 · Hopkins, Kentucky4,406,080———County sales or price not published1 eligible mines / 1 sales respondents
Method, assumptions and source records
  1. This is an annual county-sales allocation, not reported mine or company revenue. Currency is nominal USD in the source year; quantities are short tons.
  2. Mine share = same-year annual mine production / eligible same-county production. Estimated sales = published county sales × share. Estimated coal revenue = estimated sales × published county average FOB price.
  3. The model assumes eligible mines share county sales in proportion to production and receive the county-average price. Matching mine counts is a check, not proof of identical respondents. Mine quality, contracts and sales timing can differ substantially. No statistical confidence interval is implied.
  4. FOB excludes transport and insurance. EIA-923 delivered costs do not enter this model. No grade premium, state/national fallback, quarterly apportionment or carry-forward to a later year is applied.
  5. Eligibility follows the source's production threshold and excludes preparation-only and refuse operations. Withheld values, inconsistent county counts and missing/ambiguous locations produce no estimate.
  6. County sales are published in thousands of tons and prices to cents. Calculations retain precision, but the inputs are rounded and the allocation is approximate.
  7. Portfolio attribution uses current MSHA ownership, not ownership during the sales year. Covered-mine sums exclude unavailable estimates and must not be read as whole-company revenue. Coverage denominators use the annual EIA mine-production release.

Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.

EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index

Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.