  1. Cable fittings; suitability.

    violationRecord 5097647
    Laurel Fork Mine · 4609084

    30 CFR 75.515 · $366.00 proposed penalty

  2. Permanent splicing of trailing cables.

    violationRecord 5097646
    Laurel Fork Mine · 4609084

    30 CFR 75.604(b) · $366.00 proposed penalty

  3. Short circuit protection of trailing cables.

    violationRecord 5097645
    Laurel Fork Mine · 4609084

    30 CFR 75.601 · $366.00 proposed penalty

  4. Roof control plan.

    violationRecord 5132969
    Crucible Deep Mine · 4609614

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $1,126.00 proposed penalty

  5. Air quality detectors and measurement devices.

    violationRecord 5132615
    Crucible Deep Mine · 4609614

    30 CFR 75.320(a) · $313.00 proposed penalty

  6. Mine ventilation plan; submission and approval.

    violationRecord 5132614
    Crucible Deep Mine · 4609614

    30 CFR 75.370(a)(1) · $288.00 proposed penalty

  7. Roof control plan.

    violationRecord 5131406
    Crucible Deep Mine · 4609614

    30 CFR 75.220(a)(1) · $504.00 proposed penalty

  8. Mechanical equipment guards.

    violationRecord 5134002
    Elk Creek Plant · 4602444

    30 CFR 77.400(d) · $151.00 proposed penalty

  9. Protection from falls of roof, face and ribs.

    violationRecord 5132968
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.202(a) · Significant and substantial (S&S) · $3,448.00 proposed penalty

  10. Roof control plan.

    violationRecord 5132967
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $3,184.00 proposed penalty

  11. Accumulation of combustible materials.

    violationRecord 5132966
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.400 · $209.00 proposed penalty

  12. Accumulation of combustible materials.

    violationRecord 5132965
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.400 · $209.00 proposed penalty

  13. Installation of high-voltage transmission cables.

    violationRecord 5097644
    Laurel Fork Mine · 4609084

    30 CFR 75.807 · $2,712.00 proposed penalty

  14. Protection from falls of roof, face and ribs.

    violationRecord 5097643
    Laurel Fork Mine · 4609084

    30 CFR 75.202(a) · Significant and substantial (S&S) · $549.00 proposed penalty

  15. Roof control plan.

    violationRecord 5097642
    Laurel Fork Mine · 4609084

    30 CFR 75.220(a)(1) · $165.00 proposed penalty

  16. Mine ventilation plan; submission and approval.

    violationRecord 5097641
    Laurel Fork Mine · 4609084

    30 CFR 75.370(a)(1) · $288.00 proposed penalty

  17. Roof control plan.

    violationRecord 5094846
    Crucible Deep Mine · 4609614

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $1,126.00 proposed penalty

  18. Mine ventilation plan; submission and approval.

    violationRecord 5094845
    Crucible Deep Mine · 4609614

    30 CFR 75.370(a)(1) · $209.00 proposed penalty

  19. Spot Inspections

    inspectionRecord F017E8C
    Berwind Deep Mine · 4609533

    103(i) · 6.5 on-site hours reported

  20. Machinery and equipment; operation and maintenance.

    violationRecord 5133495
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.1725(a) · Significant and substantial (S&S) · $1,320.00 proposed penalty

  21. Automatic fire sensors and manual actuators; installation; minimum requirements.

    violationRecord 5133494
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.1107-4(c) · $151.00 proposed penalty

  22. Proximity detection systems.

    violationRecord 5133493
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.1732(b)(1) · Significant and substantial (S&S) · $1,818.00 proposed penalty

  23. Ventilation controls.

    violationRecord 5097640
    Laurel Fork Mine · 4609084

    30 CFR 75.333(d)(3) · $432.00 proposed penalty

  24. Permanent splicing of trailing cables.

    violationRecord 8252266
    Berwind Deep Mine · 4609533

    30 CFR 75.604(b) · Significant and substantial (S&S) · $3,448.00 proposed penalty

  25. Permanent splicing of trailing cables.

    violationRecord 5095584
    Crucible Deep Mine · 4609614

    30 CFR 75.604(b) · $151.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.