  1. Regular Safety and Health Inspection

    inspectionRecord F0145BB

    0.0 on-site hours reported

  2. Spot Inspection

    inspectionRecord F00CDD9

    7.0 on-site hours reported

  3. Mine ventilation plan; submission and approval.

    violationRecord 5132066

    30 CFR 75.370(a)(1) · $151.00 proposed penalty

  4. Ventilation controls.

    violationRecord 5132065

    30 CFR 75.333(c)(2) · $151.00 proposed penalty

  5. Other safeguards.

    violationRecord 5132064

    30 CFR 75.1403

  6. Accumulation of combustible materials.

    violationRecord 5132063

    30 CFR 75.400 · $151.00 proposed penalty

  7. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5132062

    30 CFR 75.1731(a) · $151.00 proposed penalty

  8. Automatic fire sensor and warning device systems; examination and test requirements.

    violationRecord 5132061

    30 CFR 75.1103-8(c) · $151.00 proposed penalty

  9. Accumulation of combustible materials.

    violationRecord 5132060

    30 CFR 75.400 · $151.00 proposed penalty

  10. Power wires; support.

    violationRecord 5132059

    30 CFR 75.516 · $151.00 proposed penalty

  11. Mine ventilation plan; submission and approval.

    violationRecord 5132058

    30 CFR 75.370(a)(1) · Significant and substantial (S&S) · $245.00 proposed penalty

  12. Permanent splicing of trailing cables.

    violationRecord 5132057

    30 CFR 75.604(b) · $151.00 proposed penalty

  13. Methane monitors.

    violationRecord 5132056

    30 CFR 75.342(a)(4) · $151.00 proposed penalty

  14. Permanent splicing of trailing cables.

    violationRecord 5132055

    30 CFR 75.604(b) · Significant and substantial (S&S) · $504.00 proposed penalty

  15. Accumulation of combustible materials.

    violationRecord 5132054

    30 CFR 75.400 · $151.00 proposed penalty

  16. Permissible electric face equipment; maintenance.

    violationRecord 5132053

    30 CFR 75.503 · $151.00 proposed penalty

  17. High-voltage underground equipment; grounding.

    violationRecord 5132052

    30 CFR 75.811 · $151.00 proposed penalty

  18. Violation — cited standard not reported

    violationRecord 5132051

    $168.00 proposed penalty

  19. Map locations of self-contained self-rescuers (SCSR).

    violationRecord 5132050

    30 CFR 75.1714-5 · $151.00 proposed penalty

  20. Roof control plan.

    violationRecord 5132049

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  21. Regular Safety and Health Inspection

    inspectionRecord 7047949

    67.3 on-site hours reported

  22. Installation of main mine fans.

    violationRecord 5132023

    30 CFR 75.310(a)(3) · $151.00 proposed penalty

  23. Accumulation of combustible materials.

    violationRecord 5132022

    30 CFR 75.400 · $151.00 proposed penalty

  24. Power wires; support.

    violationRecord 5132021

    30 CFR 75.516 · $151.00 proposed penalty

  25. Condition and examination of firefighting equipment.

    violationRecord 5132020

    30 CFR 75.1100-3 · $151.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.