MSHA DATABASEMSHA records · 17 contributing sources · snapshot Oct 13, 2026

MINE DETAILS

Maxine-Pratt Mine

Abandoned and SealedUndergroundCoal (Bituminous)
MSHA MINE ID0103419
LOCATIONJefferson, AL
PUBLIC RECORD6,964 linked rows

LOCATION

Mine location

1 of 1 mine with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-13Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

92

17 significant & substantial (S&S)

  1. 2025 Q115
  2. 2025 Q221
  3. 2025 Q339
  4. 2025 Q416
  5. 2026 Q11
  6. 2026 Q20
  7. 2026 Q30
  8. 2026 Q4 *0

Accident records

3

0 records classified as fatality

  1. 2025 Q11
  2. 2025 Q22
  3. 2025 Q30
  4. 2025 Q40
  5. 2026 Q10
  6. 2026 Q20
  7. 2026 Q30
  8. 2026 Q4 *0

Proposed penalties · USD

27,619.00

91 of 92 violations with amounts

  1. 2025 Q15,900
  2. 2025 Q25,039
  3. 2025 Q39,096
  4. 2025 Q47,433
  5. 2026 Q1151
  6. 2026 Q2—
  7. 2026 Q3—
  8. 2026 Q4 *—

On-site inspection hours

543.50

11 inspections · 11 with hours

  1. 2025 Q1133.00
  2. 2025 Q2150.50
  3. 2025 Q3142.25
  4. 2025 Q499.75
  5. 2026 Q118.00
  6. 2026 Q2—
  7. 2026 Q3—
  8. 2026 Q4 *—
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q11555,900.00104133.0
2025-Q22165,039.00203150.5
2025-Q33939,096.00002142.3
2025-Q41637,433.0000199.8
2026-Q110151.0000118.0
2026-Q200—000—
2026-Q300—000—
2026-Q4 *00—000—

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. violation5063549

    70.209(a) · $151.00 proposed

  2. inspectionF02775C

    Regular Safety and Health Inspection · 18.0 on-site hours

  3. violation5069616

    75.400 · $151.00 proposed

  4. violation5069615

    75.1403 · $151.00 proposed

  5. violation5069073

    75.1403 · $151.00 proposed

  6. violation5063526

    75.1103-8(a) · $959.00 proposed

  7. violation5063525

    75.1103-1 · $1,679.00 proposed

  8. violation5069823

    75.1101-10 · S&S · $432.00 proposed

  9. violation5069822

    75.363(a) · S&S · $2,133.00 proposed

  10. violation5069821

    75.601-1 · $151.00 proposed

  11. violation5069820

    75.601 · $151.00 proposed

  12. violation5069819

    75.1101-10 · S&S · $432.00 proposed

  13. violation5069818

    77.208(d) · $151.00 proposed

  14. violation5190447

    75.1505(b) · $151.00 proposed

  15. violation5190446

    75.1600-3(a)(2) · $288.00 proposed

  16. violation5190445

    75.380(d)(7)(iv) · $151.00 proposed

  17. violation5069610

    77.205(b) · $151.00 proposed

  18. violation5069609

    75.364(h) · $151.00 proposed

  19. inspection6920737

    Regular Safety and Health Inspection · 99.8 on-site hours

  20. violation5061874

    70.211(c) · $151.00 proposed

  21. violation9709155

    75.1107-16(b) · $151.00 proposed

  22. violation9709154

    75.512 · $642.00 proposed

  23. violation5069216

    75.503 · $151.00 proposed

  24. violation5069215

    75.512-2 · $151.00 proposed

  25. violation5069214

    75.800-3(a) · $151.00 proposed

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-13.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-07Source checked 2026-10-13 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS—0 rows · 0 receiving plants
HEAT CONTENT · BTU/LB—Weighted by reported tons
SULFUR / ASH · % BY WEIGHT— / —Separate averages over measured receipts
DELIVERED COST · USD/TON—No price coverage

No receipts matched this mine in the selected period. EIA-923 does not cover all mine sales, exports or metallurgical coal shipments.

Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_07_2026_21SEP2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

Latest priced year: 2024Source checked 2026-10-13. Prices apply only to their calendar year.

FOB PRICE BENCHMARK · USD/TON205.24Published county average
ESTIMATED SALES · SHORT TONS107,592Allocated from published county sales
ESTIMATED COAL REVENUE · USD22,082,147Covered mines only · not reported revenue
ANNUAL PRODUCTION COVERED100.0%1 of 1 producing annual mine records
Mine / countyAnnual production · tonsCounty FOB · USD/tonEst. sales · tonsEst. coal revenue · USDBasis / availability
Maxine-Pratt Mine0103419 · Jefferson, Alabama102,539205.24107,59222,082,147County allocation estimate1.22% of eligible county production4 eligible mines / 4 sales respondents
Method, assumptions and source records
  1. This is an annual county-sales allocation, not reported mine or company revenue. Currency is nominal USD in the source year; quantities are short tons.
  2. Mine share = same-year annual mine production / eligible same-county production. Estimated sales = published county sales × share. Estimated coal revenue = estimated sales × published county average FOB price.
  3. The model assumes eligible mines share county sales in proportion to production and receive the county-average price. Matching mine counts is a check, not proof of identical respondents. Mine quality, contracts and sales timing can differ substantially. No statistical confidence interval is implied.
  4. FOB excludes transport and insurance. EIA-923 delivered costs do not enter this model. No grade premium, state/national fallback, quarterly apportionment or carry-forward to a later year is applied.
  5. Eligibility follows the source's production threshold and excludes preparation-only and refuse operations. Withheld values, inconsistent county counts and missing/ambiguous locations produce no estimate.
  6. County sales are published in thousands of tons and prices to cents. Calculations retain precision, but the inputs are rounded and the allocation is approximate.
  7. Portfolio attribution uses current MSHA ownership, not ownership during the sales year. Covered-mine sums exclude unavailable estimates and must not be read as whole-company revenue. Coverage denominators use the annual EIA mine-production release.

Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.

EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index

Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.

OWNERSHIP

Operator and controller history

Current ownership comes from MSHA Mines. Historical start and end dates come from MSHA Controller and Operator History.

CURRENT HIERARCHYSandton Credit Solutions Master Fund IV, LP → Prospect Mining & Development Company LLC → Maxine-Pratt Mine
HISTORY RECORDS39 relationships
INTERVAL CHECKPASScontroller/operator overlap
—

Sandton Credit Solutions Master Fund IV, LPcontrolsProspect Mining & Development Company LLCoperatesMaxine-Pratt Mine

msha-controller-operator-history · controller/operator co-tenure derived on mine 0103419
—

David E Parton SrcontrolsAlaco L.L.C.operatesMaxine-Pratt Mine

msha-controller-operator-history · controller/operator co-tenure derived on mine 0103419
—

Ronald S Bryant et alcontrolsWarrior Investments Company IncoperatesMaxine-Pratt Mine

msha-controller-operator-history · controller/operator co-tenure derived on mine 0103419
Other historical summaries · source-specific periods

RECORD SUMMARY

Production, safety and enforcement

These summaries use the periods stated on each card, independently of the reporting period above.

01 / SAFETYwatch

Accidents and injuries

31 historical accident/injury rows; 0 coded fatalities and 742 lost days across the published record.

ACCIDENT + INJURY RECORD12 since 2021
accidentsmine-production-quarterly
02 / COMPLIANCEwatch

Violations and penalties

920 violation rows across the full record; 216 carry an S&S flag and $250,858 appears in current assessed amounts.

ENFORCEMENT ACTIVITY389 since 2021
inspectionsviolationsassessed-violationsorders-107a
03 / HEALTHwatch

Occupational health samples

3,893 coal dust; 100 coal quartz; 212 noise. 0 personal-sample rows have a published C/E ratio above 1; 32 noise rows have an action-level or PEL dose above 100%. These are separate measures, not a silica exceedance count. Silica results and sample status are shown separately.

OCCUPATIONAL EXPOSURE4K samples
coal-dust-samplesquartz-samplesnoise-samples
04 / PRODUCTIONcontext

Quarterly production and employment

7K employee hours and 16 summed average employees across reported subunits in the latest published quarter.

2026-Q13K tons
mine-production-quarterlymine-production-yearly
05 / LEGALwatch

Contests, conferences and decisions

266 contested-violation rows, 266 civil-penalty docket/decision rows, and 11 conference records linked by issuance number.

POST-ISSUANCE LIFECYCLE543 linked rows
conferencescontested-violationscivil-penalty-dockets-decisions
06 / CONTRACTORScontext

Contractors

Contractors are linked through this mine’s violation or accident records. Their production and hours cover all their operations, so they are not included in this mine’s totals.

ENTITY-LEVEL CONTEXT3 linked entities
contractor-production-quarterlycontractor-production-yearlyaccidentsviolations
07 / INSPECTIONScontext

Inspections

181 inspection events and 12K published inspection hours across the historical record.

OVERSIGHT COVERAGE43 since 2021
inspectionsviolations

HEALTH SAMPLING

Silica and quartz

Matching records00 coal · 0 personal · 0 area
Sample status0 not voided0 voided · 0 status not reported
Mean coal quartz concentration— µg/m³0 eligible measurements · 0 missing concentration
2026 · No reported dates in this selection
Date / sampleDataset / analyteOccupation / areaMeasurementSample statusPublished action
No silica records match these filters. Missing samples do not establish safe conditions.
Sources and interpretation
  • Coal means use numeric concentrations from samples marked not voided, excluding control/invalid sample types and dates after the snapshot. Missing values remain null; reported zeroes remain zero.
  • Quarterly means describe available samples, not mine-wide or worker-average exposure. Quarters with no eligible measurements remain empty; the current quarter is partial.
  • Personal C/E is MSHA's published concentration-to-limit ratio. A value above 1 is not by itself a citation or a determination under the 2024 silica rule. Personal and area files do not publish a void-status field.
  • Area records include bulk-dust analyses and are kept separate from personal exposure results. Their concentration units are not specified in the source dictionary.
  • Missing samples do not establish safe conditions. Coal quartz percentage and concentration are separate measures. No compliance threshold is inferred for coal samples.

Coal quartz field definitions ↗Metal/nonmetal personal field definitions ↗Metal/nonmetal area field definitions ↗

EIA + TITLE 30

EIA production and cited regulations

EIA annual figures are reported separately from MSHA. Regulation links use the current eCFR snapshot.

RECENT PUBLIC RECORDS

Recent violations and samples

Latest records retained for inspection; aggregates above use the full source history.

VIOLATIONS12 latest shown
506354970.209(a)Citation
506961675.400Citation
506961575.1403Citation
506907375.1403Citation
506352675.1103-8(a)Citation
506352575.1103-1Citation
506982375.1101-10S&S
506982275.363(a)S&S
OTHER HEALTH SAMPLES8 latest shown

Coal dust, noise and other contaminants. Silica records above ↑

Coal dustCONTINUOUS MINER OPERATOR
.054 mg/m³Voided
Coal dustCONTINUOUS MINER OPERATOR
.094 mg/m³Voided
Coal dustCONTINUOUS MINER OPERATOR
.042 mg/m³Voided
Coal dustCONTINUOUS MINER OPERATOR
.075 mg/m³Voided · UNREPRESENTATIVE SAMPLE
Coal dustCONTINUOUS MINER OPERATOR
.182 mg/m³Voided
Coal dustCONTINUOUS MINER OPERATOR
.125 mg/m³Not voided
Coal dustCONTINUOUS MINER OPERATOR
.172 mg/m³Voided
Coal dustCONTINUOUS MINER OPERATOR
.032 mg/m³Not voided

SOURCE COVERAGE

Reporting dates and coverage

17 datasets contain linked records. Missing datasets are listed below.

DATASETROWSWINDOWSTATUS
Accident, Injuries, and Illnessessafety · contractors31Apr 26, 2011—May 17, 2025mine-keyed
Addresses of Recordidentity · logistics1Mar 24, 2026—Mar 24, 2026mine-keyed
Assessed Violationscompliance · legal905Dec 13, 2010—Jan 13, 2026mine-keyed
Civil Penalty Dockets and Decisionscompliance · legal266May 22, 2013—Apr 20, 2026mine-keyed
Coal Dust Sampleshealth · safety3,893Dec 13, 2010—Jan 15, 2026mine-keyed
Conferencescompliance · legal11Dec 26, 2012—Feb 16, 2024mine-keyed
Contested Violationscompliance · legal266Oct 24, 2011—Dec 2, 2025mine-keyed
Contractor Employment and Production — Quarterlycontractors · production · safety6Not published—Not publishedentity-linked
Contractor Employment and Production — Yearlycontractors · production · safety4Not published—Not publishedentity-linked
Controller and Operator Historyidentity · compliance3Oct 15, 2009—Oct 25, 2021mine-keyed
Mine Employment and Production — Quarterlyproduction · safety · compliance130Not published—Not publishedmine-keyed
Mine Employment and Production — Yearlyproduction · safety · compliance34Not published—Not publishedmine-keyed
Inspectionssafety · compliance181Jul 7, 2010—Jan 12, 2026mine-keyed
Minesidentity · production · logistics1Not published—Not publishedmine-keyed
Metal and Nonmetal Area Sampleshealth · safety—No published rowsabsent / not applicable
Metal and Nonmetal Personal Health Sampleshealth · safety—No published rowsabsent / not applicable
Noise Sampleshealth · safety · equipment212Aug 10, 2011—Dec 16, 2025mine-keyed
Quartz Samples — Coalhealth · safety100Dec 15, 2010—Dec 16, 2025mine-keyed
Violationscompliance · safety · legal920Dec 13, 2010—Jan 13, 2026mine-keyed
107(a) Orders Issuedsafety · compliance—No published rowsabsent / not applicable

NOTES

Limitations

  • Contractor production is entity-level and is never represented as mine-attributable.
  • Missing rows can mean no event, publication delay, identity mismatch, or inapplicability.