ALL STATUSES / OPERATOR PORTFOLIO

ROSATI MATERIAL INC.

Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.

MSHA OPERATOR ID0193753

MINE PORTFOLIO

1 of 1 mines and facilities

2025-01-01 – 2026-10-13. All statuses records; production reporting is not required.

MineLocation / typeCoal · short tonsHours workedViolationsAccident recordsOn-site inspection hours
ROSATI MATERIAL PIT 11901288 · Intermittent6/8 quarters reportedHampden, MASurface · MSHA: Construction Sand and Gravel03,4238119.0

LOCATION

Mine location

1 of 1 mine with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-13Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

8

0 significant & substantial (S&S)

  1. 2025 Q10
  2. 2025 Q20
  3. 2025 Q35
  4. 2025 Q40
  5. 2026 Q10
  6. 2026 Q23
  7. 2026 Q30
  8. 2026 Q4 *0

Accident records

1

0 records classified as fatality

  1. 2025 Q10
  2. 2025 Q20
  3. 2025 Q31
  4. 2025 Q40
  5. 2026 Q10
  6. 2026 Q20
  7. 2026 Q30
  8. 2026 Q4 *0

Proposed penalties · USD

1,208.00

8 of 8 violations with amounts

  1. 2025 Q1—
  2. 2025 Q2—
  3. 2025 Q3755
  4. 2025 Q4—
  5. 2026 Q1—
  6. 2026 Q2453
  7. 2026 Q3—
  8. 2026 Q4 *—

On-site inspection hours

19.00

2 inspections · 2 with hours

  1. 2025 Q1—
  2. 2025 Q2—
  3. 2025 Q38.00
  4. 2025 Q4—
  5. 2026 Q1—
  6. 2026 Q211.00
  7. 2026 Q3—
  8. 2026 Q4 *—
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q100—000—
2025-Q200—000—
2025-Q350755.001018.0
2025-Q400—000—
2026-Q100—000—
2026-Q230453.0000111.0
2026-Q300—000—
2026-Q4 *00—000—

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. violation5099368
    ROSATI MATERIAL PIT 1 · 1901288

    56.14100(c) · $151.00 proposed

  2. inspectionF020DA8
    ROSATI MATERIAL PIT 1 · 1901288

    Regular Safety and Health Inspection · 11.0 on-site hours

  3. violation5099366
    ROSATI MATERIAL PIT 1 · 1901288

    47.51(b) · $151.00 proposed

  4. violation5099365
    ROSATI MATERIAL PIT 1 · 1901288

    56.12004 · $151.00 proposed

  5. inspectionF017025
    ROSATI MATERIAL PIT 1 · 1901288

    Regular Safety and Health Inspection · 8.0 on-site hours

  6. violation5045336
    ROSATI MATERIAL PIT 1 · 1901288

    50.30(a) · $151.00 proposed

  7. violation5045335
    ROSATI MATERIAL PIT 1 · 1901288

    56.20003(a) · $151.00 proposed

  8. violation5045334
    ROSATI MATERIAL PIT 1 · 1901288

    56.4201(a)(2) · $151.00 proposed

  9. violation5045333
    ROSATI MATERIAL PIT 1 · 1901288

    56.14100(b) · $151.00 proposed

  10. violation5045332
    ROSATI MATERIAL PIT 1 · 1901288

    56.14100(b) · $151.00 proposed

  11. accident220252300022
    ROSATI MATERIAL PIT 1 · 1901288

    SLIP OR FALL OF PERSON · DAYS AWAY FROM WORK ONLY

    Accident narrative

    Weather: rain. Operator was exiting wheel loader. Operator missed last step on loader ladder causing them to fall backwards. Operator sustained laceration to head requiring two staples, laceration to right elbow requiring two stitches, laceration to left elbow requiring one stitch. Operator was seen at emergency room, not admitted to hospital.

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-13.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

SELECTED PORTFOLIO

1 linked controller.

Relationships reflect the selected mine status and current MSHA controller/operator fields.