  1. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 9216608
    Berwind Deep Mine · 4609533

    30 CFR 75.1731(a) · $165.00 proposed penalty

  2. Travelways at surface installations.

    violationRecord 5130784
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 77.205(b) · $398.00 proposed penalty

  3. Automatic emergency-parking brakes.

    violationRecord 5130783
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.523-3(b)(5) · $177.00 proposed penalty

  4. Cable fittings; suitability.

    violationRecord 9216607
    Berwind Deep Mine · 4609533

    30 CFR 75.515 · $366.00 proposed penalty

  5. Permissible electric face equipment; maintenance.

    violationRecord 9216606
    Berwind Deep Mine · 4609533

    30 CFR 75.503 · $1,126.00 proposed penalty

  6. Permissible electric face equipment; maintenance.

    violationRecord 9216605
    Berwind Deep Mine · 4609533

    30 CFR 75.503 · $1,126.00 proposed penalty

  7. Protection from falls of roof, face and ribs.

    violationRecord 9216604
    Berwind Deep Mine · 4609533

    30 CFR 75.202(a) · Significant and substantial (S&S) · $4,047.00 proposed penalty

  8. Roof control plan.

    violationRecord 9216603
    Berwind Deep Mine · 4609533

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $3,736.00 proposed penalty

  9. Roof control plan.

    violationRecord 5092522
    NO. 2 GAS · 4609541

    30 CFR 75.220(a)(1) · $1,126.00 proposed penalty

  10. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5130782
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.1731(b) · $288.00 proposed penalty

  11. Escapeways; bituminous and lignite mines.

    violationRecord 9878936
    Laurel Fork Mine · 4609084

    30 CFR 75.380(d)(7)(iv) · $1,968.00 proposed penalty

  12. Accumulation of combustible materials.

    violationRecord 9216602
    Berwind Deep Mine · 4609533

    30 CFR 75.400 · $818.00 proposed penalty

  13. Grounding metallic frames, casings, and other enclosures of electric equipment.

    violationRecord 5092521
    NO. 2 GAS · 4609541

    30 CFR 75.701 · $818.00 proposed penalty

  14. Roof control plan.

    violationRecord 5092520
    NO. 2 GAS · 4609541

    30 CFR 75.220(a)(1) · $1,126.00 proposed penalty

  15. Spot Inspections

    inspectionRecord F02224B
    Berwind Deep Mine · 4609533

    103(i) · 6.5 on-site hours reported

  16. Accumulation of combustible materials.

    violationRecord 5130781
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.400 · $366.00 proposed penalty

  17. Roof testing and scaling.

    violationRecord 5092519
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.211(d) · $151.00 proposed penalty

  18. On-shift examination.

    violationRecord 5098337
    Crucible Deep Mine · 4609614

    30 CFR 75.362(a)(2) · $151.00 proposed penalty

  19. Accumulation of combustible materials.

    violationRecord 5130780
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.400 · $959.00 proposed penalty

  20. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5130779
    Stonecoal Branch Mine No. 2 · 4608663

    30 CFR 75.1731(a) · $267.00 proposed penalty

  21. Identification of circuit breakers.

    violationRecord 9216601
    Berwind Deep Mine · 4609533

    30 CFR 75.904 · $1,219.00 proposed penalty

  22. Mine ventilation plan; submission and approval.

    violationRecord 9212400
    Berwind Deep Mine · 4609533

    30 CFR 75.370(a)(1) · $1,037.00 proposed penalty

  23. Mine ventilation plan; submission and approval.

    violationRecord 8284600
    Berwind Deep Mine · 4609533

    30 CFR 75.370(a)(1) · $1,037.00 proposed penalty

  24. Accumulation of combustible materials.

    violationRecord 8284599
    Berwind Deep Mine · 4609533

    30 CFR 75.400 · $818.00 proposed penalty

  25. Mine ventilation plan; submission and approval.

    violationRecord 8284598
    Berwind Deep Mine · 4609533

    30 CFR 75.370(a)(1) · $1,550.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.