Ramaco Resources, LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Mine ventilation plan; submission and approval.
Crucible Deep Mine · 460961430 CFR 75.370(a)(1) · $165.00 proposed penalty
Mine ventilation plan; submission and approval.
Crucible Deep Mine · 460961430 CFR 75.370(a)(1) · $165.00 proposed penalty
Mine ventilation plan; submission and approval.
Crucible Deep Mine · 460961430 CFR 75.370(a)(1) · $165.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
Laurel Fork Mine · 460908430 CFR 75.1731(a) · $151.00 proposed penalty
Accumulation of combustible materials.
Laurel Fork Mine · 460908430 CFR 75.400 · $245.00 proposed penalty
Protection from falls of roof, face and ribs.
Crucible Deep Mine · 460961430 CFR 75.202(a) · $151.00 proposed penalty
Mechanical equipment guards.
Crucible Deep Mine · 460961430 CFR 75.1722(a) · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
Crucible Deep Mine · 460961430 CFR 75.1731(a) · $151.00 proposed penalty
Verbal Hazard Complaint Inspections
Elk Creek Plant · 46024443.5 on-site hours reported
Mine ventilation plan; submission and approval.
Laurel Fork Mine · 460908430 CFR 75.370(a)(1) · $288.00 proposed penalty
Protection from falls of roof, face and ribs.
Crucible Deep Mine · 460961430 CFR 75.202(a) · Significant and substantial (S&S) · $642.00 proposed penalty
Spot Inspections
Berwind Deep Mine · 4609533103(i) · 6.5 on-site hours reported
Accumulation of combustible materials.
Laurel Fork Mine · 460908430 CFR 75.400 · $2,312.00 proposed penalty
Machinery and equipment; operation and maintenance.
Laurel Fork Mine · 460908430 CFR 75.1725(a) · Significant and substantial (S&S) · $2,712.00 proposed penalty
Other safeguards.
Laurel Fork Mine · 460908430 CFR 75.1403
Other safeguards.
Laurel Fork Mine · 460908430 CFR 75.1403
Other safeguards.
Laurel Fork Mine · 460908430 CFR 75.1403 · Significant and substantial (S&S) · $2,503.00 proposed penalty
Sanitary toilet facilities; maintenance.
Laurel Fork Mine · 460908430 CFR 71.501 · $1,037.00 proposed penalty
Communications facilities; refuge alternatives.
Berwind Deep Mine · 460953330 CFR 75.1600-3(a)(1) · $398.00 proposed penalty
Electric equipment; examination, testing and maintenance.
Berwind Deep Mine · 460953330 CFR 75.512 · Significant and substantial (S&S) · $1,679.00 proposed penalty
Permissible electric face equipment; maintenance.
Berwind Deep Mine · 460953330 CFR 75.503 · Significant and substantial (S&S) · $3,184.00 proposed penalty
Maintenance of incombustible content of rock dust.
Berwind Deep Mine · 460953330 CFR 75.403 · $1,037.00 proposed penalty
Drill dust control at underground areas of underground mines.
Crucible Deep Mine · 460961430 CFR 72.630(b) · Significant and substantial (S&S) · $642.00 proposed penalty
Impoundment Spot Inspection
Elk Creek Plant · 46024447.0 on-site hours reported
Spot Inspection
Elk Creek Plant · 46024443.5 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.