Ventilation controls.
Berwind Deep Mine · 460953330 CFR 75.333(h) · $177.00 proposed penalty
Violation — cited standard not reported
NO. 2 GAS · 4609541$4,871.00 proposed penalty
Violation — cited standard not reported
NO. 2 GAS · 4609541$17,521.00 proposed penalty
Drill dust control at underground areas of underground mines.
Crucible Deep Mine · 460961430 CFR 72.630(b) · Significant and substantial (S&S) · $1,679.00 proposed penalty
Protection from falls of roof, face and ribs.
Crucible Deep Mine · 460961430 CFR 75.202(a) · Significant and substantial (S&S) · $2,936.00 proposed penalty
Roof control plan.
Crucible Deep Mine · 460961430 CFR 75.220(a)(1) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Spot Inspections
Laurel Fork Mine · 4609084103(i) · 3.8 on-site hours reported
Verbal Hazard Complaint Inspections
Berwind Deep Mine · 46095337.0 on-site hours reported
Loading and haulage equipment; installations.
Highwall Miner No.1 · 460921930 CFR 77.1605(d) · $313.00 proposed penalty
Storage of materials.
Highwall Miner No.1 · 460921930 CFR 77.208(e) · $313.00 proposed penalty
Examination and maintenance of firefighting equipment.
Highwall Miner No.1 · 460921930 CFR 77.1110 · $313.00 proposed penalty
Roof control plan.
Berwind Deep Mine · 460953330 CFR 75.220(a)(1) · $959.00 proposed penalty
Verbal Hazard Complaint Inspections
Berwind Deep Mine · 46095333.0 on-site hours reported
Verbal Hazard Complaint Inspections
NO. 2 GAS · 460954110.5 on-site hours reported
Communication facilities; working sections; installation and maintenance requirements; audible or visual alarms.
Stonecoal Branch Mine No. 2 · 460866330 CFR 75.1600-2(b) · $151.00 proposed penalty
Accumulations of combustible materials.
Highwall Miner No.1 · 460921930 CFR 77.1104 · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
Berwind Deep Mine · 460953330 CFR 75.202(a) · Significant and substantial (S&S) · $10,569.00 proposed penalty
Protection from falls of roof, face and ribs.
Berwind Deep Mine · 460953330 CFR 75.202(a) · Significant and substantial (S&S) · $4,749.00 proposed penalty
Weekly examination.
Crucible Deep Mine · 460961430 CFR 75.364(b)(4) · $226.00 proposed penalty
Loading and haulage equipment; installations.
Crucible Deep Mine · 460961430 CFR 77.1605(d) · $226.00 proposed penalty
Mobile equipment; automatic warning devices.
Crucible Deep Mine · 460961430 CFR 77.410(a)(1) · $226.00 proposed penalty
Accumulations of combustible materials.
Crucible Deep Mine · 460961430 CFR 77.1104 · $226.00 proposed penalty
Loading and haulage equipment; installations.
Crucible Deep Mine · 460961430 CFR 77.1605(d) · $193.00 proposed penalty
Verbal Hazard Complaint Inspections
Berwind Deep Mine · 460953313.5 on-site hours reported
Mine ventilation plan; submission and approval.
Berwind Deep Mine · 460953330 CFR 75.370(a)(1) · $504.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.