ACTIVE / OPERATOR PORTFOLIO

Peabody Midwest Mining, LLC

Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.

MSHA OPERATOR IDP23854

MINE PORTFOLIO

4 of 4 mines and facilities

2025-01-01 – 2026-10-13. Active records; production reporting is not required.

MineLocation / typeCoal · short tonsHours workedViolationsAccident recordsOn-site inspection hours
Columbia Maintenance Services1202076 · Active6/8 quarters reportedGibson, INFacility · MSHA: Coal (Bituminous)063,8163061.8
Francisco Mine1202147 · Active6/8 quarters reportedGibson, INFacility · MSHA: Coal (Bituminous)076,85980146.5
Francisco Underground Pit1202295 · Active6/8 quarters reportedGibson, INUnderground · MSHA: Coal (Bituminous)2,277,074641,64059345,081.3
Preparation Plant1102546 · Active6/8 quarters reportedRandolph, ILFacility · MSHA: Coal (Bituminous)082,97550142.5

LOCATION

Portfolio map

4 of 4 mines with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-13Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

609

115 significant & substantial (S&S)

  1. 2025 Q1123
  2. 2025 Q275
  3. 2025 Q371
  4. 2025 Q496
  5. 2026 Q188
  6. 2026 Q256
  7. 2026 Q389
  8. 2026 Q4 *11

Accident records

4

0 records classified as fatality

  1. 2025 Q10
  2. 2025 Q20
  3. 2025 Q31
  4. 2025 Q40
  5. 2026 Q11
  6. 2026 Q21
  7. 2026 Q31
  8. 2026 Q4 *0

Proposed penalties · USD

377,094.00

564 of 609 violations with amounts

  1. 2025 Q185,999
  2. 2025 Q241,932
  3. 2025 Q357,790
  4. 2025 Q455,416
  5. 2026 Q174,646
  6. 2026 Q230,104
  7. 2026 Q331,207
  8. 2026 Q4 *—

On-site inspection hours

5,432.00

179 inspections · 179 with hours

  1. 2025 Q1815.50
  2. 2025 Q2768.75
  3. 2025 Q3753.75
  4. 2025 Q4881.00
  5. 2026 Q1785.00
  6. 2026 Q2730.50
  7. 2026 Q3686.00
  8. 2026 Q4 *11.50
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q11232585,999.000025815.5
2025-Q2751141,932.000027768.8
2025-Q3712257,790.001027753.8
2025-Q4961355,416.000023881.0
2026-Q1881974,646.001024785.0
2026-Q256630,104.001024730.5
2026-Q3891731,207.001026686.0
2026-Q4 *112—00311.5

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. violation9785635
    Francisco Underground Pit · 1202295

    75.333(b)(2)

  2. violation9785634
    Francisco Underground Pit · 1202295

    75.370(a)(1) · S&S

  3. violation5014612
    Francisco Underground Pit · 1202295

    75.220(a)(1)

  4. violation5014611
    Francisco Underground Pit · 1202295

    75.1731(a)

  5. inspection7005304
    Francisco Underground Pit · 1202295

    103(i) Spot Inspections · 0.0 on-site hours

  6. violation9785633
    Francisco Underground Pit · 1202295

    75.1202

  7. violation9785632
    Francisco Underground Pit · 1202295

    75.342(a)(4)

  8. violation9785631
    Francisco Underground Pit · 1202295

    75.370(a)(1)

  9. inspectionF01B952
    Francisco Underground Pit · 1202295

    103(i) Spot Inspections · 0.0 on-site hours

  10. violation9785630
    Francisco Underground Pit · 1202295

    75.342(a)(4) · S&S

  11. violation9785629
    Francisco Underground Pit · 1202295

    75.503

  12. violation9780751
    Francisco Underground Pit · 1202295

    75.370(a)(1)

  13. inspectionF046F02
    Francisco Underground Pit · 1202295

    Regular Safety and Health Inspection · 11.5 on-site hours

  14. violation9780750
    Francisco Underground Pit · 1202295

    75.370(a)(1)

  15. inspectionF0243EE
    Columbia Maintenance Services · 1202076

    Spot Inspection · 5.0 on-site hours

  16. inspectionF0232BC
    Francisco Underground Pit · 1202295

    103(i) Spot Inspections · 6.5 on-site hours

  17. violation9785882
    Francisco Underground Pit · 1202295

    75.370(a)(1)

  18. violation5014335
    Francisco Underground Pit · 1202295

    75.370(a)(1)

  19. violation5014334
    Francisco Underground Pit · 1202295

    75.333(h)

  20. violation5014333
    Francisco Underground Pit · 1202295

    75.1714-2(c)

  21. violation5014332
    Francisco Underground Pit · 1202295

    75.220(a)(1) · S&S

  22. inspectionF0308A3
    Francisco Underground Pit · 1202295

    103(i) Spot Inspections · 8.5 on-site hours

  23. violation5014472
    Francisco Underground Pit · 1202295

    75.321(a)(1) · S&S

  24. violation5014471
    Francisco Underground Pit · 1202295

    75.604(b) · S&S

  25. violation5014470
    Francisco Underground Pit · 1202295

    75.370(a)(1) · S&S

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-13.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-07Source checked 2026-10-13 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS1,424,96314 rows · 2 receiving plants
HEAT CONTENT · BTU/LB11,645Weighted by reported tons
SULFUR / ASH · % BY WEIGHT3.28 / 9.94Separate averages over measured receipts
DELIVERED COST · USD/TON68.0998.4% of reported tons have usable costs
Quarterly receipts and quality
QuarterShort tonsHeat · Btu/lbSulfur %Ash %Delivered USD/ton
2025-Q3 *163,71611,8433.529.4963.16
2025-Q4405,98111,5843.3810.0863.80
2026-Q1378,04011,6483.2910.3271.15
2026-Q2359,75411,5903.019.4570.72
2026-Q3 *117,47211,7323.3610.3071.75
Month / sourceMineReceiving plant / supplierShort tonsDelivered USD/tonHeat · Btu/lbSulfur %Ash %PurchaseTransport
2026-07EIA row 12120 · preliminaryFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES117,47271.7511,7323.3610.30ContractBITRail
2026-06EIA row 10211 · preliminaryFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES105,70472.6811,8833.369.60ContractBITRail
2026-05EIA row 8358 · preliminaryFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES124,48267.4110,9792.339.70ContractBITRail
2026-04EIA row 6551 · preliminaryFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES129,56872.3011,9393.379.10ContractBITRail
2026-03EIA row 4724 · preliminaryFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES140,73571.1611,7473.359.40ContractBITRail
2026-02EIA row 2794 · preliminaryFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES114,56070.9311,5443.2011.50ContractBITRail
2026-01EIA row 813 · preliminaryFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES111,21971.3611,6453.2710.30ContractBITRail
2026-01EIA row 1330 · preliminaryFRANCISCO MINE - UNDERGROUND P1202295Archer Daniels Midland Decatur10865 · IL · PEABODY COAL SALES11,526—Not published11,5003.6010.00SpotBITRail
2025-12EIA row 34849 · finalFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES93,10466.6411,2753.429.90ContractBITRail
2025-12EIA row 35648 · finalFRANCISCO MINE - UNDERGROUND P1202295Archer Daniels Midland Decatur10865 · IL · PEABODY COAL SALES11,608—Not published11,5003.6010.00SpotBITRail
2025-11EIA row 31858 · finalFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES104,99263.5311,6143.2810.40ContractBITRail
2025-10EIA row 28912 · finalFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES196,27762.6111,7203.4110.00ContractBITRail
2025-09EIA row 25845 · finalFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES46,66263.5911,9303.539.20ContractBITRail
2025-08EIA row 22716 · finalFRANCISCO MINE1202147Gibson6113 · IN · PEABODY COAL SALES117,05462.9811,8083.519.60ContractBITRail
Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_07_2026_21SEP2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

Latest priced year: 2024Source checked 2026-10-13. Prices apply only to their calendar year.

FOB PRICE BENCHMARK · USD/TON—Weighted by estimated sales of covered mines
ESTIMATED SALES · SHORT TONS—Allocated from published county sales
ESTIMATED COAL REVENUE · USD—Covered mines only · not reported revenue
ANNUAL PRODUCTION COVERED0.0%0 of 1 producing annual mine records
Mine / countyAnnual production · tonsCounty FOB · USD/tonEst. sales · tonsEst. coal revenue · USDBasis / availability
Preparation Plant1102546 · Randolph, Illinois0———Preparation plant1 eligible mines / 1 sales respondents
Columbia Maintenance Services1202076 · Location unavailable————No matching annual production record
Francisco Mine1202147 · Gibson, Indiana0———Preparation plant2 eligible mines / 2 sales respondents
Francisco Underground Pit1202295 · Gibson, Indiana1,715,164———County sales or price not published2 eligible mines / 2 sales respondents
Method, assumptions and source records
  1. This is an annual county-sales allocation, not reported mine or company revenue. Currency is nominal USD in the source year; quantities are short tons.
  2. Mine share = same-year annual mine production / eligible same-county production. Estimated sales = published county sales × share. Estimated coal revenue = estimated sales × published county average FOB price.
  3. The model assumes eligible mines share county sales in proportion to production and receive the county-average price. Matching mine counts is a check, not proof of identical respondents. Mine quality, contracts and sales timing can differ substantially. No statistical confidence interval is implied.
  4. FOB excludes transport and insurance. EIA-923 delivered costs do not enter this model. No grade premium, state/national fallback, quarterly apportionment or carry-forward to a later year is applied.
  5. Eligibility follows the source's production threshold and excludes preparation-only and refuse operations. Withheld values, inconsistent county counts and missing/ambiguous locations produce no estimate.
  6. County sales are published in thousands of tons and prices to cents. Calculations retain precision, but the inputs are rounded and the allocation is approximate.
  7. Portfolio attribution uses current MSHA ownership, not ownership during the sales year. Covered-mine sums exclude unavailable estimates and must not be read as whole-company revenue. Coverage denominators use the annual EIA mine-production release.

Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.

EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index

Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.

SELECTED PORTFOLIO