Panther Creek Mining LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Accumulation of combustible materials.
Maple Eagle No. 1 Mine · 460423630 CFR 75.400
Permissible electric face equipment; maintenance.
Maple Eagle No. 1 Mine · 460423630 CFR 75.503
Roof control plan.
Winchester 2 · 460961530 CFR 75.220(a)(1)
Mine ventilation plan; submission and approval.
Winchester 2 · 460961530 CFR 75.370(a)(1)
Temporary notations, revisions, and supplements.
Speed Mine · 460543730 CFR 75.1202-1(a)
Quantity and location of firefighting equipment.
Speed Mine · 460543730 CFR 75.1100-2(e)
Preshift examination at fixed intervals.
Speed Mine · 460543730 CFR 75.360(f)
Permissible electric face equipment; maintenance.
Speed Mine · 460543730 CFR 75.503
Condition and examination of firefighting equipment.
Speed Mine · 460543730 CFR 75.1100-3
Roof testing and scaling.
Maple Eagle East Deep Mine · 460941630 CFR 75.211(d)
Accumulation of combustible materials.
Maple Eagle East Deep Mine · 460941630 CFR 75.400
Accumulation of combustible materials.
Maple Eagle East Deep Mine · 460941630 CFR 75.400
Regular Safety and Health Inspection
Maple Eagle No. 1 Mine · 460423664.3 on-site hours reported
Regular Safety and Health Inspection
Speed Mine · 4605437106.0 on-site hours reported
Regular Safety and Health Inspection
Samples Surface Mine · 460717871.5 on-site hours reported
Regular Safety and Health Inspection
Maple Eagle East Deep Mine · 460941656.0 on-site hours reported
Regular Safety and Health Inspection
Winchester 2 · 460961544.3 on-site hours reported
Power wires and cables; insulation and protection.
Maple Eagle No. 1 Mine · 460423630 CFR 75.517 · Significant and substantial (S&S)
Escapeway maps.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1505(b)
Communications facilities; refuge alternatives.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1600-3(a)(1)
Escapeways; bituminous and lignite mines.
Maple Eagle No. 1 Mine · 460423630 CFR 75.380(d)(1)
Mine ventilation plan; submission and approval.
Maple Eagle East Deep Mine · 460941630 CFR 75.370(a)(1)
Mine ventilation plan; submission and approval.
Maple Eagle East Deep Mine · 460941630 CFR 75.370(a)(1)
High-voltage underground equipment; grounding.
Maple Eagle East Deep Mine · 460941630 CFR 75.811
Handling of materials
Maple Eagle No. 1 Mine · 4604236No dys awy frm wrk,no rstr act
Accident narrative
Employee was struck by a joint of water line causing a laceration that required 4 stitches in their right leg.
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.