Travelways at surface installations.
Coal Clean Prep Plant · 460857130 CFR 77.205(a) · $151.00 proposed penalty
Travelways at surface installations.
Coal Clean Prep Plant · 460857130 CFR 77.205(a) · Significant and substantial (S&S) · $504.00 proposed penalty
Mine ventilation plan; submission and approval.
Maple Eagle No. 1 Mine · 460423630 CFR 75.370(a)(1) · $504.00 proposed penalty
Short circuit protection; ratings and settings of circuit breakers.
Speed Mine · 460543730 CFR 75.601-1 · $366.00 proposed penalty
Power wires; support.
Winchester 2 · 460961530 CFR 75.516 · $151.00 proposed penalty
Storage of liquefied and nonliquefied compressed gas cylinders; requirements.
Winchester 2 · 460961530 CFR 75.1106-3(a)(2) · $209.00 proposed penalty
Preshift examination at fixed intervals.
Winchester 2 · 460961530 CFR 75.360(g) · $151.00 proposed penalty
Accumulation of combustible materials.
Maple Eagle No. 1 Mine · 460423630 CFR 75.400 · $465.00 proposed penalty
Accumulation of combustible materials.
Maple Eagle No. 1 Mine · 460423630 CFR 75.400 · $465.00 proposed penalty
Automatic fire sensor and warning device systems; examination and test requirements.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1103-8(c) · $165.00 proposed penalty
Accumulation of combustible materials.
Maple Eagle No. 1 Mine · 460423630 CFR 75.400 · $465.00 proposed penalty
Short circuit protection; ratings and settings of circuit breakers.
Maple Eagle No. 1 Mine · 460423630 CFR 75.601-1 · $165.00 proposed penalty
Protection of trailing cables.
Maple Eagle No. 1 Mine · 460423630 CFR 75.606 · $549.00 proposed penalty
Mine ventilation plan; submission and approval.
Maple Eagle No. 1 Mine · 460423630 CFR 75.370(a)(1) · $1,968.00 proposed penalty
Automatic fire sensor and warning device systems; examination and test requirements.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1103-8(c) · $245.00 proposed penalty
Identification of circuit breakers and disconnecting switches.
Maple Eagle No. 1 Mine · 460423630 CFR 75.809 · $1,219.00 proposed penalty
Spot Inspections
Speed Mine · 4605437103(i) · 6.0 on-site hours reported
Emergency tethers.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1714-6 · $549.00 proposed penalty
Electric equipment and circuits; overload and short circuit protection; minimum requirements.
Maple Eagle No. 1 Mine · 460423630 CFR 75.518-1 · $1,219.00 proposed penalty
Mine ventilation plan; submission and approval.
Maple Eagle No. 1 Mine · 460423630 CFR 75.370(a)(1) · $1,818.00 proposed penalty
Installation of high-voltage transmission cables.
Maple Eagle No. 1 Mine · 460423630 CFR 75.807 · $1,219.00 proposed penalty
Accumulation of combustible materials.
Speed Mine · 460543730 CFR 75.400 · Significant and substantial (S&S) · $7,676.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
Speed Mine · 460543730 CFR 75.1731(a) · $1,126.00 proposed penalty
Mechanical equipment guards.
Speed Mine · 460543730 CFR 75.1722(c) · Significant and substantial (S&S) · $6,540.00 proposed penalty
Loading and haulage equipment; installations.
Coal Clean Prep Plant · 460857130 CFR 77.1605(k) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.