Panther Creek Mining LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Identification of circuit breakers.
Maple Eagle No. 1 Mine · 460423630 CFR 75.904 · $592.00 proposed penalty
Mine ventilation plan; submission and approval.
Maple Eagle No. 1 Mine · 460423630 CFR 75.370(a)(1) · $504.00 proposed penalty
Protection of trailing cables.
Maple Eagle No. 1 Mine · 460423630 CFR 75.606 · $549.00 proposed penalty
Roof control plan.
Speed Mine · 460543730 CFR 75.220(a)(1) · Significant and substantial (S&S) · $4,383.00 proposed penalty
Power wires and cables; insulation and protection.
Speed Mine · 460543730 CFR 75.517 · Significant and substantial (S&S) · $4,047.00 proposed penalty
Dry chemical devices; capacity; minimum requirements.
Speed Mine · 460543730 CFR 75.1107-9(a)(1) · $336.00 proposed penalty
Protection from falls of roof, face and ribs.
Speed Mine · 460543730 CFR 75.202(a) · Significant and substantial (S&S) · $2,936.00 proposed penalty
Mechanical equipment guards.
Speed Mine · 460543730 CFR 75.1722(b) · Significant and substantial (S&S) · $2,503.00 proposed penalty
Methane monitors.
Maple Eagle No. 1 Mine · 460423630 CFR 75.342(a)(4) · $1,431.00 proposed penalty
Machinery and equipment; operation and maintenance.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1725(a) · Significant and substantial (S&S) · $2,936.00 proposed penalty
Mine ventilation plan; submission and approval.
Maple Eagle No. 1 Mine · 460423630 CFR 75.370(a)(1) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Other safeguards.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1403 · $883.00 proposed penalty
Air quality detectors and measurement devices.
Maple Eagle No. 1 Mine · 460423630 CFR 75.320(b) · $177.00 proposed penalty
Map of electrical system.
Maple Eagle No. 1 Mine · 460423630 CFR 75.508 · $151.00 proposed penalty
Escapeways; bituminous and lignite mines.
Maple Eagle No. 1 Mine · 460423630 CFR 75.380(b)(1) · Significant and substantial (S&S) · $6,037.00 proposed penalty
Escapeways; bituminous and lignite mines.
Maple Eagle No. 1 Mine · 460423630 CFR 75.380(d)(7)(vii)(A) · $549.00 proposed penalty
Additional self-contained self-rescuers (SCSRs).
Maple Eagle No. 1 Mine · 460423630 CFR 75.1714-4(f) · $549.00 proposed penalty
Refuge alternatives.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1506(a) · $549.00 proposed penalty
Roof control plan.
Maple Eagle No. 1 Mine · 460423630 CFR 75.220(a)(1) · $2,133.00 proposed penalty
Roof control plan.
Maple Eagle No. 1 Mine · 460423630 CFR 75.220(a)(1) · $288.00 proposed penalty
Roof bolting.
Maple Eagle No. 1 Mine · 460423630 CFR 75.204(c)(1) · $165.00 proposed penalty
Other safeguards.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1403 · $1,550.00 proposed penalty
Escapeways; bituminous and lignite mines.
Maple Eagle No. 1 Mine · 460423630 CFR 75.380(d)(1) · $504.00 proposed penalty
Other safeguards.
Maple Eagle No. 1 Mine · 460423630 CFR 75.1403 · $1,550.00 proposed penalty
First-aid equipment; location; minimum requirements.
Speed Mine · 460543730 CFR 75.1713-7(c) · $336.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.