ACTIVE / OPERATOR PORTFOLIO

Morton Salt Inc

Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.

MSHA OPERATOR ID0114165

MINE PORTFOLIO

3 of 3 mines and facilities

2025-01-01 – 2026-10-18. Active records; production reporting is not required.

MineLocation / typeCoal · short tonsHours workedViolationsAccident recordsOn-site inspection hours
GRAND SALINE OPERATIONS4101776 · Active6/8 quarters reportedVan Zandt, TXUnderground · MSHA: Salt0633,0701983604.3
Morton Salt Fairport Mine3301993 · Active6/8 quarters reportedLake, OHUnderground · MSHA: Salt0359,0794828609.3
Weeks Island Mine and Mill1600970 · Active6/8 quarters reportedIberia, LAUnderground · MSHA: Salt0508,172187101,244.8

LOCATION

Portfolio map

3 of 3 mines with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-18Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

433

53 significant & substantial (S&S)

  1. 2025 Q138
  2. 2025 Q244
  3. 2025 Q343
  4. 2025 Q476
  5. 2026 Q166
  6. 2026 Q270
  7. 2026 Q394
  8. 2026 Q4 *2

Accident records

41

0 records classified as fatality

  1. 2025 Q16
  2. 2025 Q27
  3. 2025 Q34
  4. 2025 Q45
  5. 2026 Q18
  6. 2026 Q25
  7. 2026 Q36
  8. 2026 Q4 *0

Proposed penalties · USD

306,618.00

426 of 433 violations with amounts

  1. 2025 Q127,552
  2. 2025 Q217,277
  3. 2025 Q335,541
  4. 2025 Q476,522
  5. 2026 Q154,450
  6. 2026 Q243,010
  7. 2026 Q352,266
  8. 2026 Q4 *—

On-site inspection hours

2,458.25

102 inspections · 102 with hours

  1. 2025 Q1372.25
  2. 2025 Q2280.75
  3. 2025 Q3247.25
  4. 2025 Q4446.50
  5. 2026 Q1375.75
  6. 2026 Q2277.75
  7. 2026 Q3458.00
  8. 2026 Q4 *—
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q138427,552.006017372.3
2025-Q244717,277.007010280.8
2025-Q3431035,541.004014247.3
2025-Q4761576,522.005015446.5
2026-Q166754,450.008016375.8
2026-Q270743,010.005011277.8
2026-Q394352,266.006019458.0
2026-Q4 *20—000—

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. accident220261100010
    Morton Salt Fairport Mine · 3301993

    HOISTING · ACCIDENT ONLY

    Accident narrative

    While performing rope NDT, rope met retirement criteria.

  2. inspectionF01B777
    Weeks Island Mine and Mill · 1600970

    103(i) Spot Inspections · 5.0 on-site hours

  3. violation5076002
    Morton Salt Fairport Mine · 3301993

    57.4260(a) · $151.00 proposed

  4. inspectionF02FBBC
    Morton Salt Fairport Mine · 3301993

    Regular Safety and Health Inspection · 49.3 on-site hours

  5. violation5076001
    Morton Salt Fairport Mine · 3301993

    57.3200 · $151.00 proposed

  6. violation5070600
    Morton Salt Fairport Mine · 3301993

    47.44(b) · $151.00 proposed

  7. violation5070599
    Morton Salt Fairport Mine · 3301993

    57.12032 · $151.00 proposed

  8. inspectionF024841
    Weeks Island Mine and Mill · 1600970

    Spot Inspection · 11.3 on-site hours

  9. inspectionF03166B
    GRAND SALINE OPERATIONS · 4101776

    Spot Inspection · 12.8 on-site hours

  10. inspectionF02483E
    Weeks Island Mine and Mill · 1600970

    103(i) Spot Inspections · 3.0 on-site hours

  11. inspectionF02483F
    Weeks Island Mine and Mill · 1600970

    103 (g) Written Notification Hazard Complaint Inspectio · 4.0 on-site hours

  12. violation5005965
    Weeks Island Mine and Mill · 1600970

    57.14209(b) · S&S · $2,936.00 proposed

  13. accident220260890069
    Morton Salt Fairport Mine · 3301993

    HOISTING · ACCIDENT ONLY

    Accident narrative

    The final stop switch on the Koepe faulted. Evacuation was canceled.

  14. inspectionF02DD9D
    Weeks Island Mine and Mill · 1600970

    103(i) Spot Inspections · 4.0 on-site hours

  15. inspectionF002D32
    Weeks Island Mine and Mill · 1600970

    103(i) Spot Inspections · 6.0 on-site hours

  16. accident220260610012
    Morton Salt Fairport Mine · 3301993

    HOISTING · ACCIDENT ONLY

    Accident narrative

    Hoist dynamic brakes faulted causing the production hoist to be unavailable. Cancelled before evacuation was completed. Also, cancelled before the phone call to report ended.

  17. accident220260610011
    Morton Salt Fairport Mine · 3301993

    HOISTING · ACCIDENT ONLY

    Accident narrative

    Lug to electrical contactor failed causing the production hoist to be unavailable.

  18. violation5005480
    Weeks Island Mine and Mill · 1600970

    57.18002(b) · $209.00 proposed

  19. inspectionF03165E
    GRAND SALINE OPERATIONS · 4101776

    Compliance Follow-up Inspection · 0.0 on-site hours

  20. accident220260580006
    Morton Salt Fairport Mine · 3301993

    HOISTING · ACCIDENT ONLY

    Accident narrative

    Utility power outage caused the production hoist to be unavailable.

  21. violation5009323
    Weeks Island Mine and Mill · 1600970

    57.22304(a) · $1,219.00 proposed

  22. violation5009322
    Weeks Island Mine and Mill · 1600970

    57.20011 · $697.00 proposed

  23. violation5009321
    Weeks Island Mine and Mill · 1600970

    57.14100(b) · $366.00 proposed

  24. violation5005358
    Weeks Island Mine and Mill · 1600970

    57.14100(c) · $209.00 proposed

  25. violation5005357
    Weeks Island Mine and Mill · 1600970

    57.16003 · $151.00 proposed

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-18.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

SELECTED PORTFOLIO

1 linked controller.

Relationships reflect the selected mine status and current MSHA controller/operator fields.