ACTIVE / OPERATOR PORTFOLIO

Egypt Valley Stone

Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.

MSHA OPERATOR ID0084805

MINE PORTFOLIO

1 of 1 mines and facilities

2025-01-01 – 2026-10-13. Active records; production reporting is not required.

MineLocation / typeCoal · short tonsHours workedViolationsAccident recordsOn-site inspection hours
Egypt Valley Stone3304588 · Active6/8 quarters reportedBelmont, OHSurface · MSHA: Crushed, Broken Limestone NEC0113,06911079.3

LOCATION

Mine location

1 of 1 mine with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-13Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

11

3 significant & substantial (S&S)

  1. 2025 Q18
  2. 2025 Q21
  3. 2025 Q30
  4. 2025 Q40
  5. 2026 Q11
  6. 2026 Q20
  7. 2026 Q31
  8. 2026 Q4 *0

Accident records

0

0 records classified as fatality

  1. 2025 Q10
  2. 2025 Q20
  3. 2025 Q30
  4. 2025 Q40
  5. 2026 Q10
  6. 2026 Q20
  7. 2026 Q30
  8. 2026 Q4 *0

Proposed penalties · USD

1,935.00

11 of 11 violations with amounts

  1. 2025 Q11,482
  2. 2025 Q2151
  3. 2025 Q3—
  4. 2025 Q4—
  5. 2026 Q1151
  6. 2026 Q2—
  7. 2026 Q3151
  8. 2026 Q4 *—

On-site inspection hours

79.25

8 inspections · 8 with hours

  1. 2025 Q129.00
  2. 2025 Q226.75
  3. 2025 Q30.75
  4. 2025 Q4—
  5. 2026 Q111.25
  6. 2026 Q2—
  7. 2026 Q311.50
  8. 2026 Q4 *—
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q1831,482.0000229.0
2025-Q210151.0000326.8
2025-Q300—0010.8
2025-Q400—000—
2026-Q110151.0000111.3
2026-Q200—000—
2026-Q310151.0000111.5
2026-Q4 *00—000—

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. inspectionF02F248
    Egypt Valley Stone · 3304588

    Regular Safety and Health Inspection · 11.5 on-site hours

  2. violation9589616
    Egypt Valley Stone · 3304588

    56.14100(b) · $151.00 proposed

  3. violation9255914
    Egypt Valley Stone · 3304588

    56.14132 · $151.00 proposed

  4. inspectionF0141C6
    Egypt Valley Stone · 3304588

    Regular Safety and Health Inspection · 11.3 on-site hours

  5. inspectionF00AADA
    Egypt Valley Stone · 3304588

    Special Emphasis Programs · 0.8 on-site hours

  6. inspectionF011DB6
    Egypt Valley Stone · 3304588

    Regular Safety and Health Inspection · 18.3 on-site hours

  7. violation9936089
    Egypt Valley Stone · 3304588

    56.4500 · $151.00 proposed

  8. inspectionF0114C2
    Egypt Valley Stone · 3304588

    Spot Inspection · 1.5 on-site hours

  9. inspectionF00B067
    Egypt Valley Stone · 3304588

    Health Technical Investigation · 7.0 on-site hours

  10. violation9583178
    Egypt Valley Stone · 3304588

    56.14100(b) · S&S · $151.00 proposed

  11. violation9583177
    Egypt Valley Stone · 3304588

    56.14107(a) · $151.00 proposed

  12. violation9583176
    Egypt Valley Stone · 3304588

    56.14100(a) · S&S · $288.00 proposed

  13. violation9583175
    Egypt Valley Stone · 3304588

    56.14100(b) · S&S · $288.00 proposed

  14. violation9583174
    Egypt Valley Stone · 3304588

    56.4104(a) · $151.00 proposed

  15. violation9583173
    Egypt Valley Stone · 3304588

    56.14107(a) · $151.00 proposed

  16. inspectionF00B066
    Egypt Valley Stone · 3304588

    103 (g) Written Notification Hazard Complaint Inspectio · 16.0 on-site hours

  17. violation9933373
    Egypt Valley Stone · 3304588

    56.4201(b) · $151.00 proposed

  18. violation9933372
    Egypt Valley Stone · 3304588

    56.14107(a) · $151.00 proposed

  19. inspectionF00AACE
    Egypt Valley Stone · 3304588

    Regular Safety and Health Inspection · 13.0 on-site hours

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-13.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-07Source checked 2026-10-13 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS25,66812 rows · 2 receiving plants
HEAT CONTENT · BTU/LB11,991Weighted by reported tons
SULFUR / ASH · % BY WEIGHT3.45 / 10.73Separate averages over measured receipts
DELIVERED COST · USD/TON60.6880.6% of reported tons have usable costs
Quarterly receipts and quality
QuarterShort tonsHeat · Btu/lbSulfur %Ash %Delivered USD/ton
2025-Q3 *6,90112,5383.7310.7859.88
2025-Q47,80712,4403.8310.4059.44
2026-Q15,67711,2552.7611.6157.84
2026-Q3 *5,28311,4053.2810.2065.62
Month / sourceMineReceiving plant / supplierShort tonsDelivered USD/tonHeat · Btu/lbSulfur %Ash %PurchaseTransport
2026-07EIA row 12035 · preliminaryEgypt Valley Stone, L.L.C.3304588H L Spurlock6041 · KY · CCU COAL & CONSTRUCTION, LLC5,28365.6211,4053.2810.20SpotBITRiver
2026-03EIA row 4665 · preliminaryEgypt Valley Stone, L.L.C.3304588H L Spurlock6041 · KY · RAW MATERIALS RECYCLING, INC.3,84857.3311,2902.4011.90SpotBITRiver
2026-02EIA row 2706 · preliminaryEgypt Valley Stone, L.L.C.3304588H L Spurlock6041 · KY · RAW MATERIALS RECYCLING, INC.1,82958.9011,1803.5111.00SpotBITRiver
2025-12EIA row 35726 · finalEgypt Valley Stone, L.L.C.3304588Scrubgrass Reclamation CO. LP.50974 · PA · NEISWONGER CONSTRUCTION, INC.1,096—Not published12,1253.6113.00SpotBITTruck
2025-11EIA row 31776 · finalEgypt Valley Stone, L.L.C.3304588H L Spurlock6041 · KY · RAW MATERIALS RECYCLING, INC.1,59557.1011,9903.578.70SpotBITRiver
2025-11EIA row 32714 · finalEgypt Valley Stone, L.L.C.3304588Scrubgrass Reclamation CO. LP.50974 · PA · NEISWONGER CONSTRUCTION, INC.1,108—Not published12,1253.6113.00SpotBITTruck
2025-10EIA row 28829 · finalEgypt Valley Stone, L.L.C.3304588H L Spurlock6041 · KY · RAW MATERIALS RECYCLING, INC.3,20760.6012,9604.168.80SpotBITRiver
2025-10EIA row 29772 · finalEgypt Valley Stone, L.L.C.3304588Scrubgrass Reclamation CO. LP.50974 · PA · NEISWONGER CONSTRUCTION, INC.801—Not published12,1253.6113.00SpotBITTruck
2025-09EIA row 25761 · finalEgypt Valley Stone, L.L.C.3304588H L Spurlock6041 · KY · RAW MATERIALS RECYCLING, INC.3,32659.6812,5753.529.60SpotBITRiver
2025-09EIA row 26710 · finalEgypt Valley Stone, L.L.C.3304588Scrubgrass Reclamation CO. LP.50974 · PA · NEISWONGER CONSTRUCTION, INC.833—Not published12,1253.6113.00SpotBITTruck
2025-08EIA row 22619 · finalEgypt Valley Stone, L.L.C.3304588H L Spurlock6041 · KY · RAW MATERIALS RECYCLING, INC.1,61060.2912,9654.3210.50SpotBITRiver
2025-08EIA row 23624 · finalEgypt Valley Stone, L.L.C.3304588Scrubgrass Reclamation CO. LP.50974 · PA · NEISWONGER CONSTRUCTION, INC.1,132—Not published12,1253.6113.00SpotBITTruck
Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_07_2026_21SEP2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

SELECTED PORTFOLIO

1 linked controller.

Relationships reflect the selected mine status and current MSHA controller/operator fields.