Violation — cited standard not reported
Bailey Mine · 3607230Other safeguards.
Bailey Mine · 360723030 CFR 75.1403 · $165.00 proposed penalty
Fire suppression devices; approved components; installation requirements.
Bailey Mine · 360723030 CFR 75.1107-3(d) · $151.00 proposed penalty
Cable fittings; suitability.
Bailey Mine · 360723030 CFR 75.515 · $151.00 proposed penalty
Maintenance of incombustible content of rock dust.
Bailey Mine · 360723030 CFR 75.403 · $151.00 proposed penalty
Accumulation of combustible materials.
Bailey Mine · 360723030 CFR 75.400 · $177.00 proposed penalty
Permissible electric face equipment; maintenance.
Bailey Mine · 360723030 CFR 75.503 · $151.00 proposed penalty
Dry chemical devices; capacity; minimum requirements.
Bailey Mine · 360723030 CFR 75.1107-9(a)(1) · $151.00 proposed penalty
Mine ventilation plan; submission and approval.
ENLOW FORK MINE · 360741630 CFR 75.370(a)(1) · $209.00 proposed penalty
Permanent splicing of trailing cables.
ENLOW FORK MINE · 360741630 CFR 75.604(b) · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
HARVEY MINE · 361004530 CFR 75.1731(a) · $151.00 proposed penalty
Spot Inspections
Bailey Mine · 3607230103(i) · 4.0 on-site hours reported
Spot Inspections
ENLOW FORK MINE · 3607416103(i) · 5.8 on-site hours reported
Electric equipment; examination, testing and maintenance.
Bailey Mine · 360723030 CFR 75.512 · $313.00 proposed penalty
Escapeways; bituminous and lignite mines.
Bailey Mine · 360723030 CFR 75.380(d)(7)(iv) · $151.00 proposed penalty
Mine ventilation plan; submission and approval.
Bailey Mine · 360723030 CFR 75.370(a)(1) · $151.00 proposed penalty
Maintenance of incombustible content of rock dust.
Bailey Mine · 360723030 CFR 75.403 · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
Bailey Mine · 360723030 CFR 75.1731(a) · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
Bailey Mine · 360723030 CFR 75.1731(b) · $151.00 proposed penalty
Accumulation of combustible materials.
ENLOW FORK MINE · 360741630 CFR 75.400 · $366.00 proposed penalty
Other safeguards.
HARVEY MINE · 361004530 CFR 75.1403 · $177.00 proposed penalty
Ventilation controls.
HARVEY MINE · 361004530 CFR 75.333(e)(1)(ii) · $165.00 proposed penalty
Slip or fall of person
Bailey Mine · 3607230Days away from work only
Accident narrative
At #6 EE was parked beside the refuse shop. EE exited EE's pickup truck to take supplies to a truck driver that was in line at the bin. When walking back to EE's truck EE slipped on the ice and fell backward onto back. When EE fell EE's hardhat came off and ended up under EE's top of back/neck area. Employee did not miss work until 2/23/2025.
Handling of materials
HARVEY MINE · 3610045Days away from work only
Accident narrative
Employee was dragging / pulling a wash down hose in 1N TG when the hose snagged something on the mine floor. EE felt discomfort in EE's left bicep. Diagnosed with Torn Bicep. LTA on 2/10/25.
Spot Inspections
HARVEY MINE · 3610045103(i) · 8.3 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.