Winchester 2 safety activity
MSHA violations, accident reports and inspections.
Safety activity
Roof bolting.
30 CFR 75.204(c)(1) · $151.00 proposed penalty
Multi-gas detectors.
30 CFR 75.1714-7(a) · $151.00 proposed penalty
Self-rescue devices; inspection, testing, maintenance, repair, and recordkeeping.
30 CFR 75.1714-3(d) · $151.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $151.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(b) · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $313.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $313.00 proposed penalty
Water sprinkler systems; general.
30 CFR 75.1101-6 · $151.00 proposed penalty
Electric equipment and circuits; overload and short circuit protection; minimum requirements.
30 CFR 75.518-1 · $151.00 proposed penalty
Roof testing and scaling.
30 CFR 75.211(d) · $151.00 proposed penalty
Regular Safety and Health Inspection
186.3 on-site hours reported
Spot Inspection
5.5 on-site hours reported
Accumulation of combustible materials.
30 CFR 75.400 · $151.00 proposed penalty
Permanent splicing of trailing cables.
30 CFR 75.604(b) · Significant and substantial (S&S) · $1,968.00 proposed penalty
Maintenance of incombustible content of rock dust.
30 CFR 75.403 · $288.00 proposed penalty
Escapeway maps.
30 CFR 75.1505(b) · $151.00 proposed penalty
Other safeguards.
30 CFR 75.1403
Ventilation controls.
30 CFR 75.333(d)(3) · $151.00 proposed penalty
Power wires; support.
30 CFR 75.516 · $151.00 proposed penalty
Storage of liquefied and nonliquefied compressed gas cylinders; requirements.
30 CFR 75.1106-3(a)(2) · $209.00 proposed penalty
Preshift examination at fixed intervals.
30 CFR 75.360(g) · $151.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $2,312.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $1,037.00 proposed penalty
Permanent splicing of trailing cables.
30 CFR 75.604(b) · Significant and substantial (S&S) · $2,312.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.