← Sewell Mine B

Sewell Mine B safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5131380

    30 CFR 75.1731(a) · $366.00 proposed penalty

  2. Mechanical equipment guards.

    violationRecord 5131379

    30 CFR 75.1722(a) · $267.00 proposed penalty

  3. Roof control plan.

    violationRecord 5131378

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  4. Cable fittings; suitability.

    violationRecord 5131377

    30 CFR 75.515 · $2,936.00 proposed penalty

  5. Escapeways; bituminous and lignite mines.

    violationRecord 5131376

    30 CFR 75.380(d)(7)(vi) · $151.00 proposed penalty

  6. Permanent splicing of trailing cables.

    violationRecord 5131375

    30 CFR 75.604(b) · Significant and substantial (S&S) · $2,936.00 proposed penalty

  7. Permanent splicing of trailing cables.

    violationRecord 5131374

    30 CFR 75.604(b) · $2,936.00 proposed penalty

  8. Mine ventilation plan; submission and approval.

    violationRecord 5131373

    30 CFR 75.370(a)(1) · Significant and substantial (S&S) · $549.00 proposed penalty

  9. Cable fittings; suitability.

    violationRecord 5131372

    30 CFR 77.505 · $2,936.00 proposed penalty

  10. Escapeway maps.

    violationRecord 5131371

    30 CFR 75.1505(a) · $151.00 proposed penalty

  11. Accumulations of combustible materials.

    violationRecord 5131370

    30 CFR 77.1104 · $177.00 proposed penalty

  12. Requirement for container labels.

    violationRecord 5131369

    30 CFR 47.41(a)(1) · $151.00 proposed penalty

  13. Accumulation of combustible materials.

    violationRecord 5131368

    30 CFR 75.400 · $432.00 proposed penalty

  14. Accumulation of combustible materials.

    violationRecord 5131367

    30 CFR 75.400 · $432.00 proposed penalty

  15. Escapeway maps.

    violationRecord 5131366

    30 CFR 75.1505(a) · $151.00 proposed penalty

  16. Permanent splicing of trailing cables.

    violationRecord 5131365

    30 CFR 75.604(b) · Significant and substantial (S&S) · $2,936.00 proposed penalty

  17. Mine ventilation plan; submission and approval.

    violationRecord 5131364

    30 CFR 75.370(a)(1) · $549.00 proposed penalty

  18. Minimum requirements; fire suppression materials and location; maintenance of entries and crosscuts; access doors; communications; fire crews; high-expansion foam devices.

    violationRecord 5131363

    30 CFR 75.1103-9(a)(1) · $209.00 proposed penalty

  19. Roof control plan.

    violationRecord 5131362

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $2,936.00 proposed penalty

  20. Mechanical equipment guards.

    violationRecord 5131361

    30 CFR 75.1722(a) · Significant and substantial (S&S) · $5,144.00 proposed penalty

  21. Accumulation of combustible materials.

    violationRecord 5131360

    30 CFR 75.400 · $226.00 proposed penalty

  22. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5131359

    30 CFR 75.1731(b) · $151.00 proposed penalty

  23. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5131358

    30 CFR 75.1731(b) · $209.00 proposed penalty

  24. Regular Safety and Health Inspection

    inspectionRecord F02EDF9

    146.8 on-site hours reported

  25. Mechanical equipment guards.

    violationRecord 5131357

    30 CFR 75.1722(a) · Significant and substantial (S&S) · $11,450.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.