RIVER VIEW MINE safety activity
MSHA violations, accident reports and inspections.
Safety activity
Inspection of fire suppression devices.
30 CFR 75.1107-16-b · $151.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $642.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 75.1725(c) · Significant and substantial (S&S) · $10,569.00 proposed penalty
Immediate notification.
30 CFR 50.10(d) · $151.00 proposed penalty
Non-Injury Accident Investigation
18.0 on-site hours reported
Violation — cited standard not reported
Roof control plan.
30 CFR 75.220(a)(1) · $151.00 proposed penalty
Hazardous conditions and violations of mandatory health or safety standards; posting, correcting, and recording.
30 CFR 75.363(b) · $177.00 proposed penalty
Fall of roof or back
Accident only
Accident narrative
A roof fall has occurred on the #1 unit of the 1I panel in #4 entry. From spad 20+20 to 20+85. The fall measured 25ft x 6ft x 19ft. The fall will not be loaded out and the area has had additional support added.
Methane monitors.
30 CFR 75.342(a)(4) · $151.00 proposed penalty
Spot Inspections
103(i) · 7.8 on-site hours reported
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $697.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · $151.00 proposed penalty
Nonpermissible diesel-powered equipment; electrical system design and performance requirements.
30 CFR 75.1910(j) · $336.00 proposed penalty
Escapeway maps.
30 CFR 75.1505(b) · $151.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $151.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $151.00 proposed penalty
Preshift examination at fixed intervals.
30 CFR 75.360(b) · Significant and substantial (S&S) · $3,448.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $209.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $267.00 proposed penalty
Preshift examination at fixed intervals.
30 CFR 75.360(f) · $209.00 proposed penalty
Ventilation controls.
30 CFR 75.333(h) · $151.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $697.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $697.00 proposed penalty
Handling of materials
Days away from work only
Accident narrative
Employee was pulling a 3/4" waterline over a feeder. The hose got hung up on the backside and as they pulled on the hose, they felt a burning pain in their left shoulder and bicep. Employee worked until 09/23/2026 to have surgery to repair a torn rotator cuff and bicep.
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.