  1. Atmospheric monitoring systems.

    violationRecord 5131353

    30 CFR 75.351(d)(2) · $165.00 proposed penalty

  2. Electric equipment; examination, testing and maintenance.

    violationRecord 5131352

    30 CFR 75.512 · $151.00 proposed penalty

  3. Accumulation of combustible materials.

    violationRecord 5131351

    30 CFR 75.400 · $151.00 proposed penalty

  4. Air quality detectors and measurement devices.

    violationRecord 5131350

    30 CFR 75.320(a) · $151.00 proposed penalty

  5. Roof control plan.

    violationRecord 5131349

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $818.00 proposed penalty

  6. Permanent splicing of trailing cables.

    violationRecord 5131348

    30 CFR 75.604(b) · Significant and substantial (S&S) · $1,818.00 proposed penalty

  7. Drill dust control at underground areas of underground mines.

    violationRecord 5131347

    30 CFR 72.630(b) · $177.00 proposed penalty

  8. Mechanical equipment guards.

    violationRecord 5131346

    30 CFR 77.400(a) · Significant and substantial (S&S) · $959.00 proposed penalty

  9. Electric equipment; examination, testing, and maintenance.

    violationRecord 5131345

    30 CFR 77.502 · Significant and substantial (S&S) · $2,133.00 proposed penalty

  10. Travelways at surface installations.

    violationRecord 5131344

    30 CFR 77.205(b) · $151.00 proposed penalty

  11. Mechanical equipment guards.

    violationRecord 5131343

    30 CFR 77.400(d) · $193.00 proposed penalty

  12. Storage of materials.

    violationRecord 5131342

    30 CFR 77.208(d) · $193.00 proposed penalty

  13. Escapeways; bituminous and lignite mines.

    violationRecord 5131341

    30 CFR 75.380(d)(7)(i) · Significant and substantial (S&S) · $10,569.00 proposed penalty

  14. Communication facilities; working sections; installation and maintenance requirements; audible or visual alarms.

    violationRecord 5131340

    30 CFR 75.1600-2(e) · $151.00 proposed penalty

  15. Escapeway maps.

    violationRecord 5131339

    30 CFR 75.1505(b) · $151.00 proposed penalty

  16. Power centers.

    violationRecord 5131338

    30 CFR 75.825(c) · $432.00 proposed penalty

  17. Power centers.

    violationRecord 5131337

    30 CFR 75.825(c) · $432.00 proposed penalty

  18. Regular Safety and Health Inspection

    inspectionRecord F02EDF6

    57.8 on-site hours reported

  19. Health Technical Investigation

    inspectionRecord F02EDF5

    7.0 on-site hours reported

  20. Mine ventilation plan; submission and approval.

    violationRecord 5131331

    30 CFR 75.370(a)(1) · $193.00 proposed penalty

  21. Electrical Technical Investigation

    inspectionRecord F010DD6

    7.0 on-site hours reported

  22. Escapeway maps.

    violationRecord 5095428

    30 CFR 75.1505(b) · $151.00 proposed penalty

  23. Ventilation controls.

    violationRecord 5131329

    30 CFR 75.333(a) · $151.00 proposed penalty

  24. Spot Inspection

    inspectionRecord F020A48

    8.0 on-site hours reported

  25. Roof control plan.

    violationRecord 5099217

    30 CFR 75.220(a)(1) · $549.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.