  1. Permanent splicing of trailing cables.

    violationRecord 5096931

    30 CFR 75.604(b) · Significant and substantial (S&S) · $8,315.00 proposed penalty

  2. Power wires and cables; insulation and protection.

    violationRecord 5096930

    30 CFR 75.517 · Significant and substantial (S&S) · $8,315.00 proposed penalty

  3. Mechanical equipment guards.

    violationRecord 5096929

    30 CFR 75.1722(a) · $177.00 proposed penalty

  4. Criteria—Belt conveyors.

    violationRecord 5096928

    30 CFR 75.1403-5(g) · Significant and substantial (S&S) · $1,968.00 proposed penalty

  5. Power wires and cables; insulation and protection.

    violationRecord 5096927

    30 CFR 75.517 · $755.00 proposed penalty

  6. Mine ventilation plan; submission and approval.

    violationRecord 5096926

    30 CFR 75.370(a)(1) · $818.00 proposed penalty

  7. Accumulation of combustible materials.

    violationRecord 5096925

    30 CFR 75.400 · $432.00 proposed penalty

  8. Escapeways; bituminous and lignite mines.

    violationRecord 5096924

    30 CFR 75.380(f)(3)(iii) · $267.00 proposed penalty

  9. Cable fittings; suitability.

    violationRecord 5096923

    30 CFR 75.515 · $883.00 proposed penalty

  10. Mine ventilation plan; submission and approval.

    violationRecord 5096922

    30 CFR 75.370(a)(1) · $366.00 proposed penalty

  11. Automatic fire sensor and warning device systems; installation; minimum requirements.

    violationRecord 5096921

    30 CFR 75.1103-4(b) · $151.00 proposed penalty

  12. Permissible electric face equipment; maintenance.

    violationRecord 5096920

    30 CFR 75.503 · $165.00 proposed penalty

  13. Electric equipment; examination, testing and maintenance.

    violationRecord 5096919

    30 CFR 75.512 · $398.00 proposed penalty

  14. Protection from falls of roof, face and ribs.

    violationRecord 5096918

    30 CFR 75.202(a) · Significant and substantial (S&S) · $6,037.00 proposed penalty

  15. Regular Safety and Health Inspection

    inspectionRecord F0107ED

    294.8 on-site hours reported

  16. Roof control plan.

    violationRecord 5096917

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $8,315.00 proposed penalty

  17. Mine ventilation plan; submission and approval.

    violationRecord 5096916

    30 CFR 75.370(a)(1) · $366.00 proposed penalty

  18. Protection from falls of roof, face and ribs.

    violationRecord 5096915

    30 CFR 75.202(a) · Significant and substantial (S&S) · $1,818.00 proposed penalty

  19. Spot Inspection

    inspectionRecord F0106E5

    5.0 on-site hours reported

  20. Spot Inspection

    inspectionRecord F01D4D3

    4.5 on-site hours reported

  21. Power wires and cables; insulation and protection.

    violationRecord 5095003

    30 CFR 75.517 · $592.00 proposed penalty

  22. Accumulation of combustible materials.

    violationRecord 5091293

    30 CFR 75.400 · $165.00 proposed penalty

  23. Roof control plan.

    violationRecord 5095002

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $883.00 proposed penalty

  24. Roof control plan.

    violationRecord 5095001

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $1,968.00 proposed penalty

  25. Permanent splicing of trailing cables.

    violationRecord 5095000

    30 CFR 75.604(b) · Significant and substantial (S&S) · $3,184.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.