MSHA DATABASEMSHA records · 17 contributing sources · snapshot Oct 13, 2026

MINE DETAILS

Mayflower Preparation Plant

ActiveFacilityCoal (Bituminous)
MSHA MINE ID4405605
LOCATIONLee, VA
PUBLIC RECORD4,193 linked rows

LOCATION

Mine location

1 of 1 mine with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-13Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

43

10 significant & substantial (S&S)

  1. 2025 Q10
  2. 2025 Q26
  3. 2025 Q30
  4. 2025 Q44
  5. 2026 Q18
  6. 2026 Q218
  7. 2026 Q30
  8. 2026 Q4 *7

Accident records

0

0 records classified as fatality

  1. 2025 Q10
  2. 2025 Q20
  3. 2025 Q30
  4. 2025 Q40
  5. 2026 Q10
  6. 2026 Q20
  7. 2026 Q30
  8. 2026 Q4 *0

Proposed penalties · USD

7,781.00

36 of 43 violations with amounts

  1. 2025 Q1—
  2. 2025 Q2986
  3. 2025 Q3—
  4. 2025 Q4630
  5. 2026 Q12,628
  6. 2026 Q23,537
  7. 2026 Q3—
  8. 2026 Q4 *—

On-site inspection hours

254.00

13 inspections · 13 with hours

  1. 2025 Q16.00
  2. 2025 Q241.25
  3. 2025 Q36.00
  4. 2025 Q453.75
  5. 2026 Q132.75
  6. 2026 Q276.75
  7. 2026 Q35.00
  8. 2026 Q4 *32.50
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q100—0026.0
2025-Q264986.0000141.3
2025-Q300—0026.0
2025-Q440630.0000153.8
2026-Q1832,628.0000432.8
2026-Q21833,537.0000176.8
2026-Q300—0015.0
2026-Q4 *70—00132.5

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. violation9272241

    77.1605(d)

  2. violation9272240

    77.1605(b)

  3. violation9272239

    77.1605(d)

  4. violation9272238

    77.1605(d)

  5. violation9272237

    77.1605(d)

  6. violation9272236

    77.1109(c)(1)

  7. violation9272235

    77.1606(c)

  8. inspectionF044347

    Regular Safety and Health Inspection · 32.5 on-site hours

  9. inspectionF0134F5

    Impoundment Spot Inspection · 5.0 on-site hours

  10. violation9271759

    77.205(a) · $151.00 proposed

  11. violation9214967

    77.1606(c) · $151.00 proposed

  12. violation9214966

    77.1606(c) · $151.00 proposed

  13. violation9214965

    77.1109(c)(1) · $151.00 proposed

  14. violation9214964

    77.410(c) · $151.00 proposed

  15. violation9214963

    77.410(c) · $151.00 proposed

  16. violation9214962

    77.1109(c)(1) · $151.00 proposed

  17. violation9271758

    77.1104 · $151.00 proposed

  18. violation9271757

    77.400(a) · S&S · $398.00 proposed

  19. violation9271756

    77.516 · $177.00 proposed

  20. violation9271755

    77.502 · $151.00 proposed

  21. violation9271754

    77.516 · $177.00 proposed

  22. violation9271753

    77.516 · $151.00 proposed

  23. violation9271752

    77.505 · $177.00 proposed

  24. violation9271751

    77.904 · S&S · $398.00 proposed

  25. violation9271750

    77.502 · $151.00 proposed

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-13.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-07Source checked 2026-10-13 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS163,60516 rows · 2 receiving plants
HEAT CONTENT · BTU/LB12,850Weighted by reported tons
SULFUR / ASH · % BY WEIGHT0.64 / 5.97Separate averages over measured receipts
DELIVERED COST · USD/TON—0.0% of reported tons have usable costs
Quarterly receipts and quality
QuarterShort tonsHeat · Btu/lbSulfur %Ash %Delivered USD/ton
2025-Q3 *20,93712,7450.626.40—
2025-Q438,05012,7410.695.75—
2026-Q151,65212,8410.675.96—
2026-Q227,30012,9370.615.83—
2026-Q3 *25,66613,0250.586.10—
Month / sourceReceiving plant / supplierShort tonsDelivered USD/tonHeat · Btu/lbSulfur %Ash %PurchaseTransport
2026-07EIA row 12647 · preliminaryTennessee Eastman Operations50481 · TN · NALLY & HAMILTON25,666—Not published13,0250.586.10SpotBITRail / Truck
2026-06EIA row 10704 · preliminaryTennessee Eastman Operations50481 · TN · NALLY & HAMILTON10,500—Not published12,7950.595.80SpotBITRail / Truck
2026-05EIA row 8828 · preliminaryTennessee Eastman Operations50481 · TN · NALLY & HAMILTON8,400—Not published12,7800.646.40SpotBITRail / Truck
2026-04EIA row 7040 · preliminaryTennessee Eastman Operations50481 · TN · NALLY & HAMILTON8,400—Not published13,2700.605.30SpotBITRail / Truck
2026-03EIA row 5209 · preliminaryTennessee Eastman Operations50481 · TN · NALLY & HAMILTON5,252—Not published13,0900.556.00SpotBITRail / Truck
2026-03EIA row 5221 · preliminaryFlorence Mill50806 · SC · CARBON PARTNERS, INC .7,400—Not published12,4000.534.30ContractBITRail
2026-02EIA row 3315 · preliminaryTennessee Eastman Operations50481 · TN · NALLY & HAMILTON15,750—Not published12,8350.686.90SpotBITRail / Truck
2026-01EIA row 1347 · preliminaryTennessee Eastman Operations50481 · TN · NALLY & HAMILTON15,750—Not published13,1800.716.20SpotBITRail / Truck
2026-01EIA row 1363 · preliminaryFlorence Mill50806 · SC · CARBON PARTNERS, INC .7,500—Not published12,4000.775.10ContractBITRail
2025-12EIA row 35670 · finalTennessee Eastman Operations50481 · TN · NALLY & HAMILTON14,610—Not published12,7500.716.20SpotBITRail / Truck
2025-12EIA row 35708 · finalFlorence Mill50806 · SC · CARBON PARTNERS, INC .7,500—Not published12,4000.775.10ContractBITRail / Truck
2025-11EIA row 32656 · finalTennessee Eastman Operations50481 · TN · NALLY & HAMILTON7,350—Not published12,8500.645.60SpotBITRail / Truck
2025-10EIA row 29714 · finalTennessee Eastman Operations50481 · TN · NALLY & HAMILTON8,400—Not published12,9400.625.70SpotBITRail / Truck
2025-10EIA row 29753 · finalFlorence Mill50806 · SC · CARBON PARTNERS, INC .190—Not published12,4000.614.90ContractBITRail / Truck
2025-09EIA row 26657 · finalTennessee Eastman Operations50481 · TN · NALLY & HAMILTON10,437—Not published12,8750.686.20SpotBITRail / Truck
2025-08EIA row 23567 · finalTennessee Eastman Operations50481 · TN · NALLY & HAMILTON10,500—Not published12,6150.576.60SpotBITRail / Truck
Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_07_2026_21SEP2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

Latest priced year: 2024Source checked 2026-10-13. Prices apply only to their calendar year.

FOB PRICE BENCHMARK · USD/TON—Published county average
ESTIMATED SALES · SHORT TONS—Allocated from published county sales
ESTIMATED COAL REVENUE · USD—Covered mines only · not reported revenue
ANNUAL PRODUCTION COVERED—0 of 0 producing annual mine records
Mine / countyAnnual production · tonsCounty FOB · USD/tonEst. sales · tonsEst. coal revenue · USDBasis / availability
Mayflower Preparation Plant4405605 · Lee, Virginia0———Preparation plant
Method, assumptions and source records
  1. This is an annual county-sales allocation, not reported mine or company revenue. Currency is nominal USD in the source year; quantities are short tons.
  2. Mine share = same-year annual mine production / eligible same-county production. Estimated sales = published county sales × share. Estimated coal revenue = estimated sales × published county average FOB price.
  3. The model assumes eligible mines share county sales in proportion to production and receive the county-average price. Matching mine counts is a check, not proof of identical respondents. Mine quality, contracts and sales timing can differ substantially. No statistical confidence interval is implied.
  4. FOB excludes transport and insurance. EIA-923 delivered costs do not enter this model. No grade premium, state/national fallback, quarterly apportionment or carry-forward to a later year is applied.
  5. Eligibility follows the source's production threshold and excludes preparation-only and refuse operations. Withheld values, inconsistent county counts and missing/ambiguous locations produce no estimate.
  6. County sales are published in thousands of tons and prices to cents. Calculations retain precision, but the inputs are rounded and the allocation is approximate.
  7. Portfolio attribution uses current MSHA ownership, not ownership during the sales year. Covered-mine sums exclude unavailable estimates and must not be read as whole-company revenue. Coverage denominators use the annual EIA mine-production release.

Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.

EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index

Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.

OWNERSHIP

Operator and controller history

Current ownership comes from MSHA Mines. Historical start and end dates come from MSHA Controller and Operator History.

CURRENT HIERARCHYThomas R Hamilton → Nally & Hamilton Enterprises Inc. → Mayflower Preparation Plant
HISTORY RECORDS821 relationships
INTERVAL CHECKPASScontroller/operator overlap
—

Thomas R Hamilton et alcontrolsNally & Hamilton Enterprises Inc.operatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
—

Jeffery A HoopscontrolsPowell Mountain Energy LLCoperatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
—

Arch Resources InccontrolsPowell Mountain Energy LLCoperatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
—

International Coal Group Inc (ICG)controlsPowell Mountain Energy LLCoperatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
—

Karat Acquisition LLCcontrolsPowell Mountain Energy LLCoperatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
—

Progress Energy InccontrolsPowell Mountain Coal Co. IncoperatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
—

Florida Progress CorporationcontrolsPowell Mountain Coal Company IncoperatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
—

Amvest CorporationcontrolsPowell Mountain Coal Company IncoperatesMayflower Preparation Plant

msha-controller-operator-history · controller/operator co-tenure derived on mine 4405605
Other historical summaries · source-specific periods

RECORD SUMMARY

Production, safety and enforcement

These summaries use the periods stated on each card, independently of the reporting period above.

01 / SAFETYneutral

Accidents and injuries

22 historical accident/injury rows; 0 coded fatalities and 502 lost days across the published record.

ACCIDENT + INJURY RECORD0 since 2021
accidentsmine-production-quarterly
02 / COMPLIANCEwatch

Violations and penalties

785 violation rows across the full record; 321 carry an S&S flag and $242,738 appears in current assessed amounts.

ENFORCEMENT ACTIVITY95 since 2021
inspectionsviolationsassessed-violationsorders-107a
03 / HEALTHwatch

Occupational health samples

189 coal dust; 3 coal quartz; 90 noise. 0 personal-sample rows have a published C/E ratio above 1; 16 noise rows have an action-level or PEL dose above 100%. These are separate measures, not a silica exceedance count. Silica results and sample status are shown separately.

OCCUPATIONAL EXPOSURE282 samples
coal-dust-samplesquartz-samplesnoise-samples
04 / PRODUCTIONcontext

Quarterly production and employment

2K employee hours and 3 summed average employees across reported subunits in the latest published quarter.

2026-Q20 tons
mine-production-quarterlymine-production-yearly
05 / LEGALwatch

Contests, conferences and decisions

24 contested-violation rows, 27 civil-penalty docket/decision rows, and 72 conference records linked by issuance number.

POST-ISSUANCE LIFECYCLE123 linked rows
conferencescontested-violationscivil-penalty-dockets-decisions
06 / CONTRACTORScontext

Contractors

Contractors are linked through this mine’s violation or accident records. Their production and hours cover all their operations, so they are not included in this mine’s totals.

ENTITY-LEVEL CONTEXT34 linked entities
contractor-production-quarterlycontractor-production-yearlyaccidentsviolations
07 / INSPECTIONScontext

Inspections

178 inspection events and 5K published inspection hours across the historical record.

OVERSIGHT COVERAGE26 since 2021
inspectionsviolations

HEALTH SAMPLING

Silica and quartz

Matching records00 coal · 0 personal · 0 area
Sample status0 not voided0 voided · 0 status not reported
Mean coal quartz concentration— µg/m³0 eligible measurements · 0 missing concentration
2026 · No reported dates in this selection
Date / sampleDataset / analyteOccupation / areaMeasurementSample statusPublished action
No silica records match these filters. Missing samples do not establish safe conditions.
Sources and interpretation
  • Coal means use numeric concentrations from samples marked not voided, excluding control/invalid sample types and dates after the snapshot. Missing values remain null; reported zeroes remain zero.
  • Quarterly means describe available samples, not mine-wide or worker-average exposure. Quarters with no eligible measurements remain empty; the current quarter is partial.
  • Personal C/E is MSHA's published concentration-to-limit ratio. A value above 1 is not by itself a citation or a determination under the 2024 silica rule. Personal and area files do not publish a void-status field.
  • Area records include bulk-dust analyses and are kept separate from personal exposure results. Their concentration units are not specified in the source dictionary.
  • Missing samples do not establish safe conditions. Coal quartz percentage and concentration are separate measures. No compliance threshold is inferred for coal samples.

Coal quartz field definitions ↗Metal/nonmetal personal field definitions ↗Metal/nonmetal area field definitions ↗

EIA + TITLE 30

EIA production and cited regulations

EIA annual figures are reported separately from MSHA. Regulation links use the current eCFR snapshot.

EIA MINE CONTEXT2024 record
ANNUAL COAL PRODUCTION0short tons
LABOR HOURS
13,957
AVG EMPLOYEES
5
SUPPLY REGION
Appalachia Central
UNION
No union code published
OPERATION
Preparation Plant
COMPANY TYPE
Independent Producer Operator

1 published EIA row aggregated under this MSHA ID. Components remain available in JSON.

RECENT PUBLIC RECORDS

Recent violations and samples

Latest records retained for inspection; aggregates above use the full source history.

VIOLATIONS12 latest shown
927224177.1605(d)Citation
927224077.1605(b)Citation
927223977.1605(d)Citation
927223877.1605(d)Citation
927223777.1605(d)Citation
927223677.1109(c)(1)Citation
927223577.1606(c)Citation
927175977.205(a)Citation
OTHER HEALTH SAMPLES8 latest shown

Coal dust, noise and other contaminants. Silica records above ↑

NoiseBULLDOZER OPERATOR
PEL dose: 40%Action-level dose: 31%
NoiseMECHANIC
PEL dose: 40%Action-level dose: 23%
NoiseMINE FOREMAN/MINE MANAGER
PEL dose: 12%Action-level dose: 8%
Coal dustBULLDOZER OPERATOR
.009 mg/m³Not voided
Coal dustBULLDOZER OPERATOR
0 mg/m³Voided · DISCARDED SAMPLE (TOO OLD)
Coal dustBULLDOZER OPERATOR
.026 mg/m³Not voided
Coal dustUTILITY MAN
.296 mg/m³Not voided
Coal dustCRUSHER ATTENDANT
.017 mg/m³Not voided

SOURCE COVERAGE

Reporting dates and coverage

17 datasets contain linked records. Missing datasets are listed below.

DATASETROWSWINDOWSTATUS
Accident, Injuries, and Illnessessafety · contractors22Jan 9, 2000—May 14, 2011mine-keyed
Addresses of Recordidentity · logistics1Dec 29, 2021—Dec 29, 2021mine-keyed
Assessed Violationscompliance · legal770Sep 13, 2000—Apr 15, 2026mine-keyed
Civil Penalty Dockets and Decisionscompliance · legal27Aug 23, 2000—Mar 26, 2025mine-keyed
Coal Dust Sampleshealth · safety189Mar 21, 2000—Sep 17, 2026mine-keyed
Conferencescompliance · legal72Jan 4, 2001—Jun 18, 2026mine-keyed
Contested Violationscompliance · legal24Aug 10, 2010—May 5, 2023mine-keyed
Contractor Employment and Production — Quarterlycontractors · production · safety1,548Not published—Not publishedentity-linked
Contractor Employment and Production — Yearlycontractors · production · safety291Not published—Not publishedentity-linked
Controller and Operator Historyidentity · compliance8Mar 1, 1981—Apr 15, 2021mine-keyed
Mine Employment and Production — Quarterlyproduction · safety · compliance157Not published—Not publishedmine-keyed
Mine Employment and Production — Yearlyproduction · safety · compliance27Not published—Not publishedmine-keyed
Inspectionssafety · compliance178Mar 3, 2000—Oct 1, 2026mine-keyed
Minesidentity · production · logistics1Not published—Not publishedmine-keyed
Metal and Nonmetal Area Sampleshealth · safety—No published rowsabsent / not applicable
Metal and Nonmetal Personal Health Sampleshealth · safety—No published rowsabsent / not applicable
Noise Sampleshealth · safety · equipment90Mar 28, 2000—Oct 5, 2026mine-keyed
Quartz Samples — Coalhealth · safety3Oct 4, 2005—Apr 4, 2006mine-keyed
Violationscompliance · safety · legal785Sep 13, 2000—Oct 5, 2026mine-keyed
107(a) Orders Issuedsafety · compliance—No published rowsabsent / not applicable

NOTES

Limitations

  • Contractor production is entity-level and is never represented as mine-attributable.
  • Missing rows can mean no event, publication delay, identity mismatch, or inapplicability.