  1. Power wires and cables; insulation and protection.

    violationRecord 9548277

    30 CFR 75.517 · Significant and substantial (S&S) · $1,679.00 proposed penalty

  2. Roof control plan.

    violationRecord 9548276

    30 CFR 75.220(a)(1) · $336.00 proposed penalty

  3. Drill dust control at underground areas of underground mines.

    violationRecord 9548275

    30 CFR 72.630(b) · Significant and substantial (S&S) · $2,133.00 proposed penalty

  4. Electric equipment; examination, testing and maintenance.

    violationRecord 9197722

    30 CFR 75.512 · $151.00 proposed penalty

  5. Spot Inspections

    inspectionRecord 7037675

    103(i) · 6.0 on-site hours reported

  6. Preshift examination at fixed intervals.

    violationRecord 9780911

    30 CFR 75.360(f) · $209.00 proposed penalty

  7. Roof control plan.

    violationRecord 9548274

    30 CFR 75.220(a)(1) · $313.00 proposed penalty

  8. Face ventilation control devices.

    violationRecord 9548273

    30 CFR 75.330(b)(1) · Significant and substantial (S&S) · $1,431.00 proposed penalty

  9. Accumulation of combustible materials.

    violationRecord 9780910

    30 CFR 75.400 · $504.00 proposed penalty

  10. Accumulation of combustible materials.

    violationRecord 9548272

    30 CFR 75.400 · $504.00 proposed penalty

  11. Violation — cited standard not reported

    violationRecord 9780909

    $982.00 proposed penalty

  12. Permanent splicing of trailing cables.

    violationRecord 9548271

    30 CFR 75.604(b) · Significant and substantial (S&S) · $3,736.00 proposed penalty

  13. Spot Inspections

    inspectionRecord 7037674

    103(i) · 4.0 on-site hours reported

  14. Health Technical Investigation

    inspectionRecord 7010687

    26.5 on-site hours reported

  15. Maintenance of incombustible content of rock dust.

    violationRecord 9548270

    30 CFR 75.403 · $336.00 proposed penalty

  16. Electric equipment; examination, testing, and maintenance.

    violationRecord 9197721

    30 CFR 77.502 · Significant and substantial (S&S) · $1,679.00 proposed penalty

  17. Spot Inspections

    inspectionRecord 7011097

    103(i) · 6.0 on-site hours reported

  18. Proximity detection systems.

    violationRecord 9780908

    30 CFR 75.1732(b)(1) · Significant and substantial (S&S) · $3,736.00 proposed penalty

  19. Roof control plan.

    violationRecord 9780907

    30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $5,144.00 proposed penalty

  20. Spot Inspections

    inspectionRecord 7011096

    103(i) · 5.0 on-site hours reported

  21. Health Technical Investigation

    inspectionRecord 7011095

    3.0 on-site hours reported

  22. Mine ventilation plan; submission and approval.

    violationRecord 9780906

    30 CFR 75.370(a)(1) · $209.00 proposed penalty

  23. Permanent splicing of trailing cables.

    violationRecord 9548269

    30 CFR 75.604(b) · Significant and substantial (S&S) · $1,679.00 proposed penalty

  24. Methane monitors.

    violationRecord 9548268

    30 CFR 75.342(a)(4) · $151.00 proposed penalty

  25. Permissible electric face equipment; maintenance.

    violationRecord 9780905

    30 CFR 75.503 · $151.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.