Flying Eagle safety activity
MSHA violations, accident reports and inspections.
Safety activity
Escapeways; bituminous and lignite mines.
30 CFR 75.380(d)(7)(vii)(A) · $177.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $7,084.00 proposed penalty
Regular Safety and Health Inspection
160.8 on-site hours reported
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(a) · $3,184.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(a) · $3,184.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(a) · $642.00 proposed penalty
Accumulations of combustible materials.
30 CFR 77.1104 · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $151.00 proposed penalty
Power wires; support.
30 CFR 75.516 · $177.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(a) · $288.00 proposed penalty
Violation — cited standard not reported
$714.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $959.00 proposed penalty
Examination and maintenance of firefighting equipment.
30 CFR 77.1110 · $398.00 proposed penalty
Automatic fire warning devices; actions and response.
30 CFR 75.1103-5(h) · $336.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $1,219.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $642.00 proposed penalty
Permanent splicing of trailing cables.
30 CFR 75.604(b) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $642.00 proposed penalty
Drill dust control at underground areas of underground mines.
30 CFR 72.630(b) · $504.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $883.00 proposed penalty
Permanent splicing of trailing cables.
30 CFR 75.604(b) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $3,736.00 proposed penalty
Permanent splicing of trailing cables.
30 CFR 75.604(b) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $818.00 proposed penalty
Self-rescue devices; inspection, testing, maintenance, repair, and recordkeeping.
30 CFR 75.1714-3(b) · $504.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.