MSHA DATABASEMSHA records · 17 contributing sources · snapshot Oct 17, 2026

MINE DETAILS

Dry Fork Mine

ActiveSurfaceCoal (Bituminous)
MSHA MINE ID4801429
LOCATIONCampbell, WY
PUBLIC RECORD6,109 linked rows

LOCATION

Mine location

1 of 1 mine with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-17Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

7

1 significant & substantial (S&S)

  1. 2025 Q11
  2. 2025 Q20
  3. 2025 Q30
  4. 2025 Q44
  5. 2026 Q10
  6. 2026 Q20
  7. 2026 Q32
  8. 2026 Q4 *0

Accident records

3

0 records classified as fatality

  1. 2025 Q10
  2. 2025 Q20
  3. 2025 Q30
  4. 2025 Q40
  5. 2026 Q10
  6. 2026 Q22
  7. 2026 Q31
  8. 2026 Q4 *0

Proposed penalties · USD

3,460.00

5 of 7 violations with amounts

  1. 2025 Q1151
  2. 2025 Q2—
  3. 2025 Q3—
  4. 2025 Q43,309
  5. 2026 Q1—
  6. 2026 Q2—
  7. 2026 Q3—
  8. 2026 Q4 *—

On-site inspection hours

184.50

4 inspections · 4 with hours

  1. 2025 Q139.00
  2. 2025 Q248.25
  3. 2025 Q3—
  4. 2025 Q466.00
  5. 2026 Q1—
  6. 2026 Q2—
  7. 2026 Q331.25
  8. 2026 Q4 *—
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q110151.0000139.0
2025-Q200—00148.3
2025-Q300—000—
2025-Q4413,309.0000166.0
2026-Q100—000—
2026-Q200—200—
2026-Q320—10131.3
2026-Q4 *00—000—

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. violation9732641

    77.1104

  2. violation5034570

    77.502-2

  3. inspectionF003108

    Regular Safety and Health Inspection · 31.3 on-site hours

  4. accident220262430035

    HANDLING OF MATERIALS · DAYS AWAY FROM WORK ONLY

    Accident narrative

    Maintenance Technician servicing dozer. They stepped on the bottom step with their right foot and felt a pop in their knee.

  5. accident220261730021

    FIRE · ACCIDENT ONLY

    Accident narrative

    We received notice that there was a grass fire in the field West of the mine. Campbell County Fire Department responded and extinguished the fire. It was found to be caused by a birds nest that had been built on a power pole and had caught on fire.

  6. accident220261170013

    FIRE · ACCIDENT ONLY

    Accident narrative

    Truck driver noticed some smoke coming from behind the truck dump. Plant Technician and supervisor responded and did not see a fire but noticed a hot spot in the roof area of the building behind the truck dump. The decision was made to notify the local fire department. An area of hot coal was identified by the fire department, and they washed out the area.

  7. violation5038876

    77.1607(j) · S&S · $2,503.00 proposed

  8. violation5038875

    77.502-2 · $151.00 proposed

  9. inspectionF03AAFD

    Regular Safety and Health Inspection · 66.0 on-site hours

  10. violation9732355

    77.502 · $504.00 proposed

  11. violation9732354

    77.502 · $151.00 proposed

  12. inspection6472609

    Regular Safety and Health Inspection · 48.3 on-site hours

  13. violation9731506

    77.1104 · $151.00 proposed

  14. inspectionF009FDF

    Regular Safety and Health Inspection · 39.0 on-site hours

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-17.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-07Source checked 2026-10-17 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS4,885,40535 rows · 3 receiving plants
HEAT CONTENT · BTU/LB8,099Weighted by reported tons
SULFUR / ASH · % BY WEIGHT0.34 / 4.92Separate averages over measured receipts
DELIVERED COST · USD/TON20.47100.0% of reported tons have usable costs
Quarterly receipts and quality
QuarterShort tonsHeat · Btu/lbSulfur %Ash %Delivered USD/ton
2025-Q3 *875,9108,0840.454.9619.93
2025-Q41,370,5638,0680.314.7219.82
2026-Q11,141,5868,1130.314.7821.35
2026-Q21,083,3688,1120.315.3320.70
2026-Q3 *413,9788,1650.374.8520.76
Month / sourceReceiving plant / supplierShort tonsDelivered USD/tonHeat · Btu/lbSulfur %Ash %PurchaseTransport
2026-07EIA row 11967 · preliminaryDave Johnston4158 · WY · WESTERN FUELS31,67221.418,1090.365.50ContractSUBRail
2026-07EIA row 12184 · preliminaryLaramie River Station6204 · WY · WESTERN FUELS212,56326.478,1660.374.80ContractSUBRail / Truck
2026-07EIA row 13110 · preliminaryDry Fork Station56609 · WY · WESTERN FUELS169,74313.498,1740.374.80ContractSUBRail / Truck
2026-06EIA row 10070 · preliminaryDave Johnston4158 · WY · WESTERN FUELS79,74020.038,0910.325.20ContractSUBRail
2026-06EIA row 10275 · preliminaryLaramie River Station6204 · WY · WESTERN FUELS179,59126.548,1260.324.80ContractSUBRail / Truck
2026-06EIA row 11158 · preliminaryDry Fork Station56609 · WY · WESTERN FUELS123,76417.458,1090.324.90ContractSUBRail / Truck
2026-05EIA row 8228 · preliminaryDave Johnston4158 · WY · WESTERN FUELS78,70819.418,0890.335.30ContractSUBRail
2026-05EIA row 8411 · preliminaryLaramie River Station6204 · WY · WESTERN FUELS114,60926.598,1420.309.10ContractSUBRail / Truck
2026-05EIA row 9249 · preliminaryDry Fork Station56609 · WY · WESTERN FUELS123,69216.268,1390.304.60ContractSUBRail / Truck
2026-04EIA row 6413 · preliminaryDave Johnston4158 · WY · WESTERN FUELS111,62119.068,0720.315.20ContractSUBRail
2026-04EIA row 6611 · preliminaryLaramie River Station6204 · WY · WESTERN FUELS98,51626.628,1000.314.70ContractSUBRail / Truck
2026-04EIA row 7458 · preliminaryDry Fork Station56609 · WY · WESTERN FUELS173,12714.808,1150.314.70ContractSUBRail / Truck
2026-03EIA row 4605 · preliminaryDave Johnston4158 · WY · WESTERN FUELS64,14019.108,0920.315.40ContractSUBRail
2026-03EIA row 4788 · preliminaryLaramie River Station6204 · WY · WESTERN FUELS163,46226.538,1080.304.80ContractSUBRail / Truck
2026-03EIA row 5647 · preliminaryDry Fork Station56609 · WY · WESTERN FUELS153,95414.958,0790.344.90ContractSUBRail / Truck
2026-02EIA row 2647 · preliminaryDave Johnston4158 · WY · WESTERN FUELS15,61519.187,9600.426.40ContractSUBRail
2026-02EIA row 2862 · preliminaryLaramie River Station6204 · WY · WESTERN FUELS211,97426.518,1180.314.70ContractSUBRail / Truck
2026-02EIA row 3768 · preliminaryDry Fork Station56609 · WY · WESTERN FUELS155,32115.258,1100.314.80ContractSUBRail / Truck
2026-01EIA row 881 · preliminaryLaramie River Station6204 · WY · WESTERN FUELS227,71426.998,1350.304.60ContractSUBRail / Truck
2026-01EIA row 1822 · preliminaryDry Fork Station56609 · WY · WESTERN FUELS149,40613.888,1430.294.60ContractSUBRail / Truck
2025-12EIA row 34708 · finalDave Johnston4158 · WY · WESTERN FUELS95,74618.908,0430.305.20ContractSUBRail
2025-12EIA row 34904 · finalLaramie River Station6204 · WY · WESTERN FUELS228,91927.008,0900.294.50ContractSUBRail / Truck
2025-12EIA row 36529 · finalDry Fork Station56609 · WY · WESTERN FUELS146,40411.798,0730.334.80ContractSUBRail / Truck
2025-11EIA row 31725 · finalDave Johnston4158 · WY · WESTERN FUELS79,96918.048,0180.324.10ContractSUBRail
2025-11EIA row 31917 · finalLaramie River Station6204 · WY · WESTERN FUELS196,76727.008,0930.314.70ContractSUBRail / Truck
Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_07_2026_21SEP2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

Latest priced year: 2024Source checked 2026-10-17. Prices apply only to their calendar year.

FOB PRICE BENCHMARK · USD/TON13.96Published county average
ESTIMATED SALES · SHORT TONS3,962,553Allocated from published county sales
ESTIMATED COAL REVENUE · USD55,317,235Covered mines only · not reported revenue
ANNUAL PRODUCTION COVERED100.0%1 of 1 producing annual mine records
Mine / countyAnnual production · tonsCounty FOB · USD/tonEst. sales · tonsEst. coal revenue · USDBasis / availability
Dry Fork Mine4801429 · Campbell, Wyoming3,962,85313.963,962,55355,317,235County allocation estimate2.33% of eligible county production11 eligible mines / 11 sales respondents
Method, assumptions and source records
  1. This is an annual county-sales allocation, not reported mine or company revenue. Currency is nominal USD in the source year; quantities are short tons.
  2. Mine share = same-year annual mine production / eligible same-county production. Estimated sales = published county sales × share. Estimated coal revenue = estimated sales × published county average FOB price.
  3. The model assumes eligible mines share county sales in proportion to production and receive the county-average price. Matching mine counts is a check, not proof of identical respondents. Mine quality, contracts and sales timing can differ substantially. No statistical confidence interval is implied.
  4. FOB excludes transport and insurance. EIA-923 delivered costs do not enter this model. No grade premium, state/national fallback, quarterly apportionment or carry-forward to a later year is applied.
  5. Eligibility follows the source's production threshold and excludes preparation-only and refuse operations. Withheld values, inconsistent county counts and missing/ambiguous locations produce no estimate.
  6. County sales are published in thousands of tons and prices to cents. Calculations retain precision, but the inputs are rounded and the allocation is approximate.
  7. Portfolio attribution uses current MSHA ownership, not ownership during the sales year. Covered-mine sums exclude unavailable estimates and must not be read as whole-company revenue. Coverage denominators use the annual EIA mine-production release.

Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.

EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index

Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.

OWNERSHIP

Operator and controller history

Current ownership comes from MSHA Mines. Historical start and end dates come from MSHA Controller and Operator History.

CURRENT HIERARCHYWestern Fuels Association Inc → Western Fuels-Wyoming Inc → Dry Fork Mine
HISTORY RECORDS13 relationships
INTERVAL CHECKPASScontroller/operator overlap
—

Western Fuels Association InccontrolsWestern Fuels-Wyoming IncoperatesDry Fork Mine

msha-controller-operator-history · controller/operator co-tenure derived on mine 4801429
Other historical summaries · source-specific periods

RECORD SUMMARY

Production, safety and enforcement

These summaries use the periods stated on each card, independently of the reporting period above.

01 / SAFETYwatch

Accidents and injuries

59 historical accident/injury rows; 0 coded fatalities and 906 lost days across the published record.

ACCIDENT + INJURY RECORD5 since 2021
accidentsmine-production-quarterly
02 / COMPLIANCEwatch

Violations and penalties

112 violation rows across the full record; 11 carry an S&S flag and $58,500 appears in current assessed amounts.

ENFORCEMENT ACTIVITY16 since 2021
inspectionsviolationsassessed-violationsorders-107a
03 / HEALTHwatch

Occupational health samples

457 coal dust; 15 coal quartz; 192 noise. 0 personal-sample rows have a published C/E ratio above 1; 6 noise rows have an action-level or PEL dose above 100%. These are separate measures, not a silica exceedance count. Silica results and sample status are shown separately.

OCCUPATIONAL EXPOSURE664 samples
coal-dust-samplesquartz-samplesnoise-samples
04 / PRODUCTIONcontext

Quarterly production and employment

32K employee hours and 64 summed average employees across reported subunits in the latest published quarter.

2002-Q41M tons
mine-production-quarterlymine-production-yearly
05 / LEGALwatch

Contests, conferences and decisions

35 contested-violation rows, 35 civil-penalty docket/decision rows, and 3 conference records linked by issuance number.

POST-ISSUANCE LIFECYCLE73 linked rows
conferencescontested-violationscivil-penalty-dockets-decisions
06 / CONTRACTORScontext

Contractors

Contractors are linked through this mine’s violation or accident records. Their production and hours cover all their operations, so they are not included in this mine’s totals.

ENTITY-LEVEL CONTEXT22 linked entities
contractor-production-quarterlycontractor-production-yearlyaccidentsviolations
07 / INSPECTIONScontext

Inspections

103 inspection events and 4K published inspection hours across the historical record.

OVERSIGHT COVERAGE12 since 2021
inspectionsviolations

HEALTH SAMPLING

Silica and quartz

Matching records00 coal · 0 personal · 0 area
Sample status0 not voided0 voided · 0 status not reported
Mean coal quartz concentration— µg/m³0 eligible measurements · 0 missing concentration
2026 · No reported dates in this selection
Date / sampleDataset / analyteOccupation / areaMeasurementSample statusPublished action
No silica records match these filters. Missing samples do not establish safe conditions.
Sources and interpretation
  • Coal means use numeric concentrations from samples marked not voided, excluding control/invalid sample types and dates after the snapshot. Missing values remain null; reported zeroes remain zero.
  • Quarterly means describe available samples, not mine-wide or worker-average exposure. Quarters with no eligible measurements remain empty; the current quarter is partial.
  • Personal C/E is MSHA's published concentration-to-limit ratio. A value above 1 is not by itself a citation or a determination under the 2024 silica rule. Personal and area files do not publish a void-status field.
  • Area records include bulk-dust analyses and are kept separate from personal exposure results. Their concentration units are not specified in the source dictionary.
  • Missing samples do not establish safe conditions. Coal quartz percentage and concentration are separate measures. No compliance threshold is inferred for coal samples.

Coal quartz field definitions ↗Metal/nonmetal personal field definitions ↗Metal/nonmetal area field definitions ↗

EIA + TITLE 30

EIA production and cited regulations

EIA annual figures are reported separately from MSHA. Regulation links use the current eCFR snapshot.

RECENT PUBLIC RECORDS

Recent violations and samples

Latest records retained for inspection; aggregates above use the full source history.

VIOLATIONS12 latest shown
973264177.1104Citation
503457077.502-2Citation
503887677.1607(j)S&S
503887577.502-2Citation
973235577.502Citation
973235477.502Citation
973150677.1104Citation
973188877.1713(c)Citation
OTHER HEALTH SAMPLES8 latest shown

Coal dust, noise and other contaminants. Silica records above ↑

Coal dustCLEANUP MAN
.123 mg/m³Not voided
Coal dustHIGHLIFT OPERATOR/FRONT END LOADER
.019 mg/m³Not voided
Coal dustCOAL TRUCK DRIVER
.056 mg/m³Not voided
Coal dustBULLDOZER OPERATOR
.051 mg/m³Not voided
Coal dustBULLDOZER OPERATOR
.028 mg/m³Not voided
Coal dustHIGHWALL DRILL OPERATOR
.01 mg/m³Not voided
NoiseWATER TRUCK OPERATOR
PEL dose: 9%Action-level dose: 46%
NoiseCOAL TRUCK DRIVER
PEL dose: 38%Action-level dose: 66%

SOURCE COVERAGE

Reporting dates and coverage

17 datasets contain linked records. Missing datasets are listed below.

DATASETROWSWINDOWSTATUS
Accident, Injuries, and Illnessessafety · contractors59Mar 30, 2000—Aug 16, 2026mine-keyed
Addresses of Recordidentity · logistics1Jun 18, 1990—Jun 18, 1990mine-keyed
Assessed Violationscompliance · legal106Nov 29, 2000—Oct 12, 2025mine-keyed
Civil Penalty Dockets and Decisionscompliance · legal35Nov 14, 2005—Sep 24, 2014mine-keyed
Coal Dust Sampleshealth · safety457Apr 18, 2000—Sep 23, 2026mine-keyed
Conferencescompliance · legal3Dec 14, 2004—Feb 4, 2008mine-keyed
Contested Violationscompliance · legal35Jul 14, 2004—Oct 12, 2025mine-keyed
Contractor Employment and Production — Quarterlycontractors · production · safety3,967Not published—Not publishedentity-linked
Contractor Employment and Production — Yearlycontractors · production · safety920Not published—Not publishedentity-linked
Controller and Operator Historyidentity · compliance1Apr 1, 1989—Apr 1, 1989mine-keyed
Mine Employment and Production — Quarterlyproduction · safety · compliance24Not published—Not publishedmine-keyed
Mine Employment and Production — Yearlyproduction · safety · compliance78Not published—Not publishedmine-keyed
Inspectionssafety · compliance103Apr 4, 2000—Sep 14, 2026mine-keyed
Minesidentity · production · logistics1Not published—Not publishedmine-keyed
Metal and Nonmetal Area Sampleshealth · safety—No published rowsabsent / not applicable
Metal and Nonmetal Personal Health Sampleshealth · safety—No published rowsabsent / not applicable
Noise Sampleshealth · safety · equipment192Apr 20, 2000—Sep 23, 2026mine-keyed
Quartz Samples — Coalhealth · safety15Jan 22, 2001—Sep 10, 2024mine-keyed
Violationscompliance · safety · legal112Nov 29, 2000—Sep 23, 2026mine-keyed
107(a) Orders Issuedsafety · compliance—No published rowsabsent / not applicable

NOTES

Limitations

  • Contractor production is entity-level and is never represented as mine-attributable.
  • Missing rows can mean no event, publication delay, identity mismatch, or inapplicability.