CARDINAL safety activity
MSHA violations, accident reports and inspections.
Safety activity
Roof control plan.
30 CFR 75.220(a)(1) · $1,219.00 proposed penalty
Water sprinkler systems; fire warning devices at belt drives.
30 CFR 75.1101-10 · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $1,320.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $366.00 proposed penalty
Nonpermissible diesel-powered equipment; electrical system design and performance requirements.
30 CFR 75.1910(j) · $151.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $818.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $177.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $818.00 proposed penalty
Permanent splicing of trailing cables.
30 CFR 75.604(b) · Significant and substantial (S&S) · $1,550.00 proposed penalty
Hazardous conditions and violations of mandatory health or safety standards; posting, correcting, and recording.
30 CFR 75.363(a) · $818.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $366.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $151.00 proposed penalty
Inspection of fire suppression devices.
30 CFR 75.1107-16(b) · $267.00 proposed penalty
Machinery
Days away from work only
Accident narrative
Employee was operating a roof bolter on #3 unit, while on EE's knees with EE's lower leg behind EE a piece of slate struck EE's left foot twisting it causing a sprain/strain. The employee finished EE's shift but was taken off work for EE's sprain the next day.
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(b) · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(a) · $151.00 proposed penalty
Rock dusting.
30 CFR 75.402 · $245.00 proposed penalty
Tests of fire hydrants and fire hose; record of tests.
30 CFR 75.1103-11 · $245.00 proposed penalty
Spot Inspections
103(i) · 6.8 on-site hours reported
Accumulation of combustible materials.
30 CFR 75.400 · $398.00 proposed penalty
Spot Inspections
103(i) · 7.8 on-site hours reported
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $151.00 proposed penalty
Cable fittings; suitability.
30 CFR 75.515 · $151.00 proposed penalty
Installation of high-voltage transmission cables.
30 CFR 75.807 · $151.00 proposed penalty
Methane monitors.
30 CFR 75.342(a)(4) · Significant and substantial (S&S) · $549.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.