Spot Inspections
103(i) · 6.0 on-site hours reported
Handling of materials
No dys awy frm wrk,no rstr act
Accident narrative
Employee slipped and fell with a crib block in their hand resulting in smashing their left ring finger between the crib block and front of the section feeder.
Verbal Hazard Complaint Inspections
4.0 on-site hours reported
Spot Inspections
103(i) · 7.0 on-site hours reported
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · $1,320.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(a) · $151.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $226.00 proposed penalty
Spot Inspections
103(i) · 5.0 on-site hours reported
Roof control plan.
30 CFR 75.220(a)(1) · $151.00 proposed penalty
Health Technical Investigation
9.0 on-site hours reported
Spot Inspections
103(i) · 6.0 on-site hours reported
Fall of face/rib/pillar/side/highwall
No dys awy frm wrk,no rstr act
Accident narrative
A rock fell striking the miner in the upper back causing them to stumble and fall striking their face and mouth on the continuous mining machine resulting in dental damaged that required cosmetic repair and sutures on the inside of the lip.
Permanent splicing of trailing cables.
30 CFR 75.604(b) · $465.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $288.00 proposed penalty
Maintenance of incombustible content of rock dust.
30 CFR 75.403 · $398.00 proposed penalty
Spot Inspections
103(i) · 6.0 on-site hours reported
Verbal Hazard Complaint Inspections
9.0 on-site hours reported
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $549.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · Significant and substantial (S&S) · $755.00 proposed penalty
Additional self-contained self-rescuers (SCSRs).
30 CFR 75.1714-4(b) · $151.00 proposed penalty
Verbal Hazard Complaint Inspections
15.8 on-site hours reported
Permanent splicing of trailing cables.
30 CFR 75.604(b) · $366.00 proposed penalty
Permanent splicing of trailing cables.
30 CFR 75.604(b) · $465.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $2,133.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 75.1725(a) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.