MSHA DATABASEMSHA records · 17 contributing sources · snapshot Oct 28, 2026

MINE DETAILS

AUS #1

NonProducingUndergroundCoal (Bituminous)
MSHA MINE ID1519847
LOCATIONPike, KY
PUBLIC RECORD3,259 linked rows

LOCATION

Mine location

1 of 1 mine with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-28Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

216

34 significant & substantial (S&S)

  1. 2025 Q139
  2. 2025 Q218
  3. 2025 Q318
  4. 2025 Q425
  5. 2026 Q131
  6. 2026 Q281
  7. 2026 Q33
  8. 2026 Q4 *1

Accident records

0

0 records classified as fatality

  1. 2025 Q10
  2. 2025 Q20
  3. 2025 Q30
  4. 2025 Q40
  5. 2026 Q10
  6. 2026 Q20
  7. 2026 Q30
  8. 2026 Q4 *0

Proposed penalties · USD

67,743.00

211 of 216 violations with amounts

  1. 2025 Q17,881
  2. 2025 Q25,359
  3. 2025 Q32,810
  4. 2025 Q44,224
  5. 2026 Q15,850
  6. 2026 Q241,300
  7. 2026 Q3319
  8. 2026 Q4 *—

On-site inspection hours

1,225.75

13 inspections · 13 with hours

  1. 2025 Q1128.00
  2. 2025 Q2219.50
  3. 2025 Q3205.50
  4. 2025 Q4183.25
  5. 2026 Q1199.50
  6. 2026 Q2263.00
  7. 2026 Q320.50
  8. 2026 Q4 *6.50
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q139107,881.00001128.0
2025-Q21845,359.00002219.5
2025-Q31822,810.00001205.5
2025-Q42544,224.00001183.3
2026-Q13145,850.00002199.5
2026-Q2811041,300.00002263.0
2026-Q330319.0000220.5
2026-Q4 *10—0026.5

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

Open activity page ↗
  1. Regular Safety and Health Inspection

    inspectionRecord F0102C2

    3.5 on-site hours reported

  2. Mine ventilation plan; submission and approval.

    violationRecord 9273033

    30 CFR 75.370(a)(1)

  3. 103 (g) Written Notification Hazard Complaint Inspectio

    inspectionRecord F007238

    3.0 on-site hours reported

  4. Spot Inspection

    inspectionRecord F007753

    1.0 on-site hours reported

  5. Mine ventilation plan; submission and approval.

    violationRecord 8309333

    30 CFR 75.370(a)(1)

  6. Mine ventilation plan; submission and approval.

    violationRecord 8309332

    30 CFR 75.370(a)(1) · $168.00 proposed penalty

  7. Quarterly sampling; mechanized mining units.

    violationRecord 9215516

    30 CFR 70.208(a)(2) · $151.00 proposed penalty

  8. Regular Safety and Health Inspection

    inspectionRecord F00774B

    19.5 on-site hours reported

  9. Spot Inspection

    inspectionRecord F005003

    1.3 on-site hours reported

  10. Other safeguards.

    violationRecord 9270811

    30 CFR 75.1403 · Significant and substantial (S&S) · $151.00 proposed penalty

  11. Other safeguards.

    violationRecord 9270810

    30 CFR 75.1403 · $151.00 proposed penalty

  12. Accumulation of combustible materials.

    violationRecord 8252416

    30 CFR 75.400 · $151.00 proposed penalty

  13. Maintenance of incombustible content of rock dust.

    violationRecord 9270809

    30 CFR 75.403 · $549.00 proposed penalty

  14. Mine ventilation plan; submission and approval.

    violationRecord 9270807

    30 CFR 75.370(a)(1) · $151.00 proposed penalty

  15. Roof control plan.

    violationRecord 9270806

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  16. Preshift examination at fixed intervals.

    violationRecord 9270805

    30 CFR 75.360(a)(1) · Significant and substantial (S&S) · $10,005.00 proposed penalty

  17. Boreholes in advance of mining.

    violationRecord 9270804

    30 CFR 75.388(g) · Significant and substantial (S&S) · $9,004.00 proposed penalty

  18. Mechanical equipment guards.

    violationRecord 9270803

    30 CFR 77.400(a) · Significant and substantial (S&S) · $165.00 proposed penalty

  19. Grounding metallic frames, casings, and other enclosures of electric equipment.

    violationRecord 9270802

    30 CFR 77.701 · $151.00 proposed penalty

  20. Cable fittings; suitability.

    violationRecord 9270801

    30 CFR 77.505 · $151.00 proposed penalty

  21. Roof control plan.

    violationRecord 9272911

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  22. Roof control plan.

    violationRecord 9272910

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  23. Mine ventilation plan; submission and approval.

    violationRecord 9270800

    30 CFR 75.370(a)(1) · $1,818.00 proposed penalty

  24. Electric equipment; examination, testing, and maintenance.

    violationRecord 9270799

    30 CFR 77.502 · $151.00 proposed penalty

  25. Roof control plan.

    violationRecord 8283849

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-28.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-08Source checked 2026-10-29 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS—0 rows · 0 receiving plants
HEAT CONTENT · BTU/LB—Weighted by reported tons
SULFUR / ASH · % BY WEIGHT— / —Separate averages over measured receipts
DELIVERED COST · USD/TON—No price coverage

No receipts matched this mine in the selected period. EIA-923 does not cover all mine sales, exports or metallurgical coal shipments.

Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_08_2026_22OCT2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

Latest priced year: 2024Source checked 2026-10-29. Prices apply only to their calendar year.

FOB PRICE BENCHMARK · USD/TON—Published county average
ESTIMATED SALES · SHORT TONS—Allocated from published county sales
ESTIMATED COAL REVENUE · USD—Covered mines only · not reported revenue
ANNUAL PRODUCTION COVERED—0 of 0 producing annual mine records
Mine / countyAnnual production · tonsCounty FOB · USD/tonEst. sales · tonsEst. coal revenue · USDBasis / availability
AUS #11519847 · Location unavailable————No matching annual production record
Method, assumptions and source records
  1. This is an annual county-sales allocation, not reported mine or company revenue. Currency is nominal USD in the source year; quantities are short tons.
  2. Mine share = same-year annual mine production / eligible same-county production. Estimated sales = published county sales × share. Estimated coal revenue = estimated sales × published county average FOB price.
  3. The model assumes eligible mines share county sales in proportion to production and receive the county-average price. Matching mine counts is a check, not proof of identical respondents. Mine quality, contracts and sales timing can differ substantially. No statistical confidence interval is implied.
  4. FOB excludes transport and insurance. EIA-923 delivered costs do not enter this model. No grade premium, state/national fallback, quarterly apportionment or carry-forward to a later year is applied.
  5. Eligibility follows the source's production threshold and excludes preparation-only and refuse operations. Withheld values, inconsistent county counts and missing/ambiguous locations produce no estimate.
  6. County sales are published in thousands of tons and prices to cents. Calculations retain precision, but the inputs are rounded and the allocation is approximate.
  7. Portfolio attribution uses current MSHA ownership, not ownership during the sales year. Covered-mine sums exclude unavailable estimates and must not be read as whole-company revenue. Coverage denominators use the annual EIA mine-production release.

Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.

EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index

Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.

OWNERSHIP

Operator and controller history

Current operator and controller relationships come from MSHA Mines. Historical start and end dates come from MSHA Controller and Operator History.

CURRENT HIERARCHYJerry Todd Tackett → EBM Mining Operations, LLC → AUS #1
HISTORY RECORDS1024 relationships
INTERVAL CHECK3 REVIEWcontroller/operator overlap
—

Jerry Todd TackettcontrolsLighthouse Mining, Inc.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Jerry TackettcontrolsTackett Mining, Inc.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Michael Runyon et alcontrolsTENNCO INC.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Jack Stump et alcontrolsTENNCO INC.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Daris StumpcontrolsTENNCO INC.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Jack Stump Et AlcontrolsTENNCO INC.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Jackie (Mitch) Fannin Et AlcontrolsTENNCO INC.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

RDR Coal Holdings LLCcontrolsPODIUM MINING LLCoperatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Janet R BryantcontrolsTrump Energy Corp.operatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
—

Billy Kyle SmithcontrolsBEECH TREE MINING LLCoperatesAUS #1

msha-controller-operator-history · controller/operator co-tenure derived on mine 1519847
Other historical summaries · source-specific periods

RECORD SUMMARY

Production, safety and enforcement

These summaries use the periods stated on each card, independently of the reporting period above.

01 / SAFETYneutral

Accidents and injuries

1 historical accident/injury rows; 0 coded fatalities and 0 lost days across the published record.

ACCIDENT + INJURY RECORD0 since 2021
accidentsmine-production-quarterly
02 / COMPLIANCEwatch

Violations and penalties

755 violation rows across the full record; 145 carry an S&S flag and $258,431 appears in current assessed amounts.

ENFORCEMENT ACTIVITY490 since 2021
inspectionsviolationsassessed-violationsorders-107a
03 / HEALTHwatch

Occupational health samples

497 coal dust; 72 coal quartz; 29 noise. 0 personal-sample rows have a published C/E ratio above 1; 3 noise rows have an action-level or PEL dose above 100%. These are separate measures, not a silica exceedance count. Silica results and sample status are shown separately.

OCCUPATIONAL EXPOSURE598 samples
coal-dust-samplesquartz-samplesnoise-samples
04 / PRODUCTIONcontext

Quarterly production and employment

5K employee hours and 13 summed average employees across reported subunits in the latest published quarter.

2026-Q28K tons
mine-production-quarterlymine-production-yearly
05 / LEGALwatch

Contests, conferences and decisions

85 contested-violation rows, 85 civil-penalty docket/decision rows, and 2 conference records linked by issuance number.

POST-ISSUANCE LIFECYCLE172 linked rows
conferencescontested-violationscivil-penalty-dockets-decisions
06 / CONTRACTORScontext

Contractors

Contractors are linked through this mine’s violation or accident records. Their production and hours cover all their operations, so they are not included in this mine’s totals.

ENTITY-LEVEL CONTEXT5 linked entities
contractor-production-quarterlycontractor-production-yearlyaccidentsviolations
07 / INSPECTIONScontext

Inspections

52 inspection events and 6K published inspection hours across the historical record.

OVERSIGHT COVERAGE36 since 2021
inspectionsviolations

HEALTH SAMPLING

Silica and quartz

Matching records1212 coal · 0 personal · 0 area
Sample status5 not voided7 voided · 0 status not reported
Mean coal quartz concentration48.6 µg/m³5 eligible measurements · 0 missing concentration
2026 · Jan 13, 2026–Jun 16, 2026
Date / sampleDataset / analyteOccupation / areaMeasurementSample statusPublished action
58499631 / lab 2026025321Coal quartzQuartzOCCUPATION CODE NOT FOUNDSAMPLE TYPE NOT FOUND3 µg/m³2% quartzVoidedSUSPENDED QUARTZ SAMPLENot reported
58566188 / lab 2026015202Coal quartzQuartzROOF BOLTER (SINGLE HEAD)SAMPLE TYPE NOT FOUND37 µg/m³11.9% quartzVoidedSUSPENDED QUARTZ SAMPLENot reported
58565966 / lab 2026015198Coal quartzQuartzCUTTING MACHINE OPERATORDESIGNATED OCCUPATION15 µg/m³7% quartzNot voidedNot reported
58566198 / lab 2026015200Coal quartzQuartzSCOOP CAR OPERATORSAMPLE TYPE NOT FOUND4 µg/m³2.6% quartzVoidedSUSPENDED QUARTZ SAMPLENot reported
58565961 / lab 2026015204Coal quartzQuartzROOF BOLTER (SINGLE HEAD)NON DESIGNATED OCCUPATION9 µg/m³6.6% quartzNot voidedNot reported
58509786 / lab 2026006600Coal quartzQuartzUTILITY MANSAMPLE TYPE NOT FOUND8 µg/m³3% quartzVoidedSUSPENDED QUARTZ SAMPLENot reported
58509669 / lab 2026006601Coal quartzQuartzOCCUPATION CODE NOT FOUNDDESIGNATED AREA5 µg/m³1% quartzNot voidedNot reported
58561447 / lab 2026001698Coal quartzQuartzCUTTING MACHINE OPERATORDESIGNATED OCCUPATION14 µg/m³2.4% quartzNot voidedNot reported
58561536 / lab 2026001699Coal quartzQuartzROOF BOLTER (SINGLE HEAD)NON DESIGNATED OCCUPATION200 µg/m³9.1% quartzNot voidedNot reported
58561434 / lab 2026001696Coal quartzQuartzCOAL DRILL OPERATORSAMPLE TYPE NOT FOUND3 µg/m³2.5% quartzVoidedSUSPENDED QUARTZ SAMPLENot reported
58561441 / lab 2026001694Coal quartzQuartzSCOOP CAR OPERATORSAMPLE TYPE NOT FOUND17 µg/m³2.5% quartzVoidedSUSPENDED QUARTZ SAMPLENot reported
58561288 / lab 2026001700Coal quartzQuartzROOF BOLTER (SINGLE HEAD)SAMPLE TYPE NOT FOUND68 µg/m³12.9% quartzVoidedSUSPENDED QUARTZ SAMPLENot reported
Sources and interpretation
  • Coal means use numeric concentrations from samples marked not voided, excluding control/invalid sample types and dates after the snapshot. Missing values remain null; reported zeroes remain zero.
  • Quarterly means describe available samples, not mine-wide or worker-average exposure. Quarters with no eligible measurements remain empty; the current quarter is partial.
  • Personal C/E is MSHA's published concentration-to-limit ratio. A value above 1 is not by itself a citation or a determination under the 2024 silica rule. Personal and area files do not publish a void-status field.
  • Area records include bulk-dust analyses and are kept separate from personal exposure results. Their concentration units are not specified in the source dictionary.
  • Missing samples do not establish safe conditions. Coal quartz percentage and concentration are separate measures. No compliance threshold is inferred for coal samples.

Coal quartz field definitions ↗Metal/nonmetal personal field definitions ↗Metal/nonmetal area field definitions ↗

EIA + TITLE 30

EIA production and cited regulations

EIA annual figures are reported separately from MSHA. Regulation links use the current eCFR snapshot.

RECENT PUBLIC RECORDS

Recent health samples

Latest records retained for inspection.

OTHER HEALTH SAMPLES8 latest shown

Coal dust, noise and other contaminants. Silica records above ↑

Coal dustROOF BOLTER (SINGLE HEAD)
.422 mg/m³Not voided
Coal dustROOF BOLTER (SINGLE HEAD)
.45 mg/m³Not voided
Coal dustROOF BOLTER (SINGLE HEAD)
.543 mg/m³Not voided
Coal dustROOF BOLTER (SINGLE HEAD)
.136 mg/m³Not voided
Coal dustOCCUPATION CODE NOT FOUND
.195 mg/m³Not voided
Coal dustROOF BOLTER (SINGLE HEAD)
.176 mg/m³Not voided
Coal dustROOF BOLTER (SINGLE HEAD)
.36 mg/m³Not voided
Coal dustROOF BOLTER (SINGLE HEAD)
.273 mg/m³Not voided

SOURCE COVERAGE

Reporting dates and coverage

17 datasets contain linked records. Missing datasets are listed below.

DATASETROWSWINDOWSTATUS
Accident, Injuries, and Illnessessafety · contractors1Nov 25, 2020—Nov 25, 2020mine-keyed
Addresses of Recordidentity · logistics1Jul 7, 2026—Jul 7, 2026mine-keyed
Assessed Violationscompliance · legal727Mar 12, 2019—Jul 27, 2026mine-keyed
Civil Penalty Dockets and Decisionscompliance · legal85Mar 25, 2020—Oct 5, 2026mine-keyed
Coal Dust Sampleshealth · safety497Mar 25, 2019—Jun 22, 2026mine-keyed
Conferencescompliance · legal2Apr 29, 2021—Apr 29, 2021mine-keyed
Contested Violationscompliance · legal85Nov 5, 2019—May 8, 2026mine-keyed
Contractor Employment and Production — Quarterlycontractors · production · safety713Not published—Not publishedentity-linked
Contractor Employment and Production — Yearlycontractors · production · safety181Not published—Not publishedentity-linked
Controller and Operator Historyidentity · compliance10Dec 4, 2018—Nov 12, 2025mine-keyed
Mine Employment and Production — Quarterlyproduction · safety · compliance33Not published—Not publishedmine-keyed
Mine Employment and Production — Yearlyproduction · safety · compliance15Not published—Not publishedmine-keyed
Inspectionssafety · compliance52Mar 11, 2019—Oct 15, 2026mine-keyed
Minesidentity · production · logistics1Not published—Not publishedmine-keyed
Metal and Nonmetal Area Sampleshealth · safety—No published rowsabsent / not applicable
Metal and Nonmetal Personal Health Sampleshealth · safety—No published rowsabsent / not applicable
Noise Sampleshealth · safety · equipment29Mar 18, 2019—Feb 18, 2026mine-keyed
Quartz Samples — Coalhealth · safety72Mar 25, 2019—Jun 16, 2026mine-keyed
Violationscompliance · safety · legal755Mar 12, 2019—Oct 15, 2026mine-keyed
107(a) Orders Issuedsafety · compliance—No published rowsabsent / not applicable

NOTES

Limitations

  • Contractor production is entity-level and is never represented as mine-attributable.
  • Missing rows can mean no event, publication delay, identity mismatch, or inapplicability.