  1. Roof control plan.

    violationRecord 5024802

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  2. Roof control plan.

    violationRecord 5024801

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  3. Spot Inspections

    inspectionRecord 6322582

    103(i) · 6.5 on-site hours reported

  4. Drill dust control at underground areas of underground mines.

    violationRecord 5024800

    30 CFR 72.630(b) · $193.00 proposed penalty

  5. Methane monitors.

    violationRecord 5024799

    30 CFR 75.342(a)(4) · $151.00 proposed penalty

  6. Power wires and cables; insulation and protection.

    violationRecord 9841595

    30 CFR 75.517 · $177.00 proposed penalty

  7. Spot Inspections

    inspectionRecord 6322581

    103(i) · 8.0 on-site hours reported

  8. Grounding metallic frames, casings, and other enclosures of electric equipment.

    violationRecord 9841594

    30 CFR 75.701 · $177.00 proposed penalty

  9. Spot Inspections

    inspectionRecord 6322580

    103(i) · 7.0 on-site hours reported

  10. Electric equipment; examination, testing and maintenance.

    violationRecord 5024798

    30 CFR 75.512 · $465.00 proposed penalty

  11. Permanent splicing of trailing cables.

    violationRecord 5024797

    30 CFR 75.604(b) · $177.00 proposed penalty

  12. Additional self-contained self-rescuers (SCSRs).

    violationRecord 5024796

    30 CFR 75.1714-4(b) · $592.00 proposed penalty

  13. Mine ventilation plan; submission and approval.

    violationRecord 9841593

    30 CFR 75.370(a)(1) · $267.00 proposed penalty

  14. Roof control plan.

    violationRecord 9841592

    30 CFR 75.220(a)(1) · $193.00 proposed penalty

  15. Mine ventilation plan; submission and approval.

    violationRecord 9841591

    30 CFR 75.370(a)(1) · $267.00 proposed penalty

  16. Grounding metallic frames, casings, and other enclosures of electric equipment.

    violationRecord 9841590

    30 CFR 75.701 · $151.00 proposed penalty

  17. Spot Inspections

    inspectionRecord 6322579

    103(i) · 7.5 on-site hours reported

  18. Emergency tethers.

    violationRecord 5024795

    30 CFR 75.1714-6 · $226.00 proposed penalty

  19. Accumulation of combustible materials.

    violationRecord 9841589

    30 CFR 75.400 · $165.00 proposed penalty

  20. Other safeguards.

    violationRecord 9841588

    30 CFR 75.1403 · $1,219.00 proposed penalty

  21. Escapeways; bituminous and lignite mines.

    violationRecord 9841587

    30 CFR 75.380(d)(7)(vi) · $209.00 proposed penalty

  22. Health Technical Investigation

    inspectionRecord F009581

    21.8 on-site hours reported

  23. Maintenance of incombustible content of rock dust.

    violationRecord 9841586

    30 CFR 75.403 · $151.00 proposed penalty

  24. Spot Inspections

    inspectionRecord 6322578

    103(i) · 11.5 on-site hours reported

  25. Roof control plan.

    violationRecord 5024794

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.