Wolverine Fuels LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Accumulation of combustible materials.
SUFCO · 420008930 CFR 75.400 · $1,431.00 proposed penalty
Preshift examination at fixed intervals.
SUFCO · 420008930 CFR 75.360(g) · $209.00 proposed penalty
Machinery and equipment; operation and maintenance.
Fossil Rock Mine · 420121130 CFR 75.1725(a) · $151.00 proposed penalty
Identification of circuit breakers.
Fossil Rock Mine · 420121130 CFR 75.904 · $151.00 proposed penalty
Machinery and equipment; operation and maintenance.
SKYLINE MINE #3 · 420156630 CFR 75.1725(a) · $165.00 proposed penalty
Powered haulage
SKYLINE MINE #3 · 4201566No dys awy frm wrk,no rstr act
Accident narrative
While Climbing off the machine, Employee Placed EE's right hand on the engine cover Resulting in EE's fingers contacting the cooling fan.
Atmospheric monitoring systems.
SUFCO · 420008930 CFR 75.351(h) · $642.00 proposed penalty
Mine ventilation plan; submission and approval.
SUFCO · 420008930 CFR 75.370(a)(1) · $504.00 proposed penalty
Underground storage, lubricating oil and grease.
SKYLINE MINE #3 · 420156630 CFR 75.1104 · $226.00 proposed penalty
Escapeways; bituminous and lignite mines.
SKYLINE MINE #3 · 420156630 CFR 75.380(d)(7)(i) · Significant and substantial (S&S) · $1,679.00 proposed penalty
Permissible electric face equipment; maintenance.
Emery Valley Mine · 420007930 CFR 75.503 · $245.00 proposed penalty
Accumulation of combustible materials.
SUFCO · 420008930 CFR 75.400 · $1,431.00 proposed penalty
Accumulation of combustible materials.
SUFCO · 420008930 CFR 75.400 · $1,431.00 proposed penalty
Ventilation controls.
SUFCO · 420008930 CFR 75.333(h) · $313.00 proposed penalty
Machinery and equipment; operation and maintenance.
SKYLINE MINE #3 · 420156630 CFR 75.1725(a) · $267.00 proposed penalty
Non-Injury Accident Investigation
SUFCO · 420008928.3 on-site hours reported
Protection from falls of roof, face and ribs.
SUFCO · 420008930 CFR 75.202(a) · Significant and substantial (S&S) · $2,133.00 proposed penalty
Violation — cited standard not reported
SUFCO · 4200089Handling of materials
SKYLINE MINE #3 · 4201566Days away from work only
Accident narrative
While pulling old conveyor belt off and pulling new one on the a frame pulled loose landing on employee's foot, this caused two metatarsal fractures.
103 (g) Written Notification Hazard Complaint Inspectio
SKYLINE MINE #3 · 42015666.0 on-site hours reported
Underground storage, lubricating oil and grease.
Emery Valley Mine · 420007930 CFR 75.1104 · $193.00 proposed penalty
Mine ventilation plan; submission and approval.
SKYLINE MINE #3 · 420156630 CFR 75.370(a)(1) · $398.00 proposed penalty
Permissible electric face equipment; maintenance.
Emery Valley Mine · 420007930 CFR 75.503 · $245.00 proposed penalty
Mine ventilation plan; submission and approval.
Emery Valley Mine · 420007930 CFR 75.370(a)(1)
Emergency Response Plan; refuge alternatives.
SUFCO · 420008930 CFR 75.1507(a)(11)(i) · $1,818.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.