ACTIVE / CONTROLLER PORTFOLIO

Texas United Corp

Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.

MSHA CONTROLLER IDM00582

MINE PORTFOLIO

3 of 3 mines and facilities

2025-01-01 – 2026-10-18. Active records; production reporting is not required.

MineLocation / typeCoal · short tonsHours workedViolationsAccident recordsOn-site inspection hours
CARLSBAD LAKE PLANT2901042 · Active6/8 quarters reportedEddy, NMSurface · MSHA: Salt, Brine Evaporated040,04433142.5
CARLSBAD PLANT2901043 · Active6/8 quarters reportedEddy, NMSurface · MSHA: Salt, Brine Evaporated0162,18239889.8
HOCKLEY MINE4102478 · Active6/8 quarters reportedHarris, TXUnderground · MSHA: Salt0187,489295218.8

LOCATION

Portfolio map

3 of 3 mines with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-18Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

101

14 significant & substantial (S&S)

  1. 2025 Q125
  2. 2025 Q23
  3. 2025 Q324
  4. 2025 Q45
  5. 2026 Q131
  6. 2026 Q23
  7. 2026 Q310
  8. 2026 Q4 *0

Accident records

14

1 records classified as fatality

  1. 2025 Q13
  2. 2025 Q24
  3. 2025 Q31
  4. 2025 Q42
  5. 2026 Q12
  6. 2026 Q20
  7. 2026 Q32
  8. 2026 Q4 *0

Proposed penalties · USD

58,869.00

97 of 101 violations with amounts

  1. 2025 Q17,407
  2. 2025 Q2453
  3. 2025 Q313,572
  4. 2025 Q41,150
  5. 2026 Q120,420
  6. 2026 Q211,868
  7. 2026 Q33,999
  8. 2026 Q4 *—

On-site inspection hours

351.00

20 inspections · 20 with hours

  1. 2025 Q163.50
  2. 2025 Q234.25
  3. 2025 Q369.25
  4. 2025 Q459.00
  5. 2026 Q147.75
  6. 2026 Q224.75
  7. 2026 Q352.50
  8. 2026 Q4 *—
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q12547,407.0030463.5
2025-Q230453.0040134.3
2025-Q324513,572.0010369.3
2025-Q4511,150.0021359.0
2026-Q131320,420.0020447.8
2026-Q23111,868.0000124.8
2026-Q31003,999.0020452.5
2026-Q4 *00—000—

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

  1. violation5008813
    CARLSBAD LAKE PLANT · 2901042

    56.4102 · $398.00 proposed

  2. violation5008812
    CARLSBAD LAKE PLANT · 2901042

    56.12004 · $267.00 proposed

  3. violation5007447
    CARLSBAD LAKE PLANT · 2901042

    56.23003(b) · $151.00 proposed

  4. violation5007446
    CARLSBAD LAKE PLANT · 2901042

    56.12032 · $267.00 proposed

  5. violation5007445
    CARLSBAD LAKE PLANT · 2901042

    56.16006 · $267.00 proposed

  6. violation5007444
    CARLSBAD LAKE PLANT · 2901042

    56.4102 · $398.00 proposed

  7. violation5007443
    CARLSBAD LAKE PLANT · 2901042

    56.13011 · $398.00 proposed

  8. violation5007442
    CARLSBAD LAKE PLANT · 2901042

    56.16004 · $267.00 proposed

  9. violation5007441
    CARLSBAD LAKE PLANT · 2901042

    56.12032 · S&S · $1,320.00 proposed

  10. violation9795777
    CARLSBAD PLANT · 2901043

    56.23003(b) · $151.00 proposed

  11. violation9795776
    CARLSBAD PLANT · 2901043

    56.14112(a)(1) · S&S · $2,312.00 proposed

  12. violation9795775
    CARLSBAD PLANT · 2901043

    56.20003(a) · S&S · $1,550.00 proposed

  13. violation5003492
    CARLSBAD PLANT · 2901043

    56.15005 · $151.00 proposed

  14. violation5003491
    CARLSBAD PLANT · 2901043

    56.20003(a) · $151.00 proposed

  15. violation5005258
    HOCKLEY MINE · 4102478

    57.11012 · $151.00 proposed

  16. violation5005257
    HOCKLEY MINE · 4102478

    56.14107(a) · $151.00 proposed

  17. violation5005256
    HOCKLEY MINE · 4102478

    47.41(a) · $151.00 proposed

  18. violation5005255
    HOCKLEY MINE · 4102478

    48.7(a) · $168.00 proposed

  19. inspectionF017450
    HOCKLEY MINE · 4102478

    Regular Safety and Health Inspection · 33.3 on-site hours

  20. violation5005254
    HOCKLEY MINE · 4102478

    56.14100(c) · $151.00 proposed

  21. accident220251640007
    HOCKLEY MINE · 4102478

    HANDTOOLS (NONPOWERED) · DAYS AWAY FROM WORK ONLY

    Accident narrative

    Hand Scaling on JLG rock fell and struck employee.

  22. violation9799200
    HOCKLEY MINE · 4102478

    56.4201(a)(2) · $151.00 proposed

  23. violation9799199
    HOCKLEY MINE · 4102478

    47.41(a) · $151.00 proposed

  24. violation9799198
    HOCKLEY MINE · 4102478

    57.4203 · $151.00 proposed

  25. inspection6937698
    HOCKLEY MINE · 4102478

    Regular Safety and Health Inspection · 34.3 on-site hours

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-18.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

SELECTED PORTFOLIO

2 linked operators.

Relationships reflect the selected mine status and current MSHA controller/operator fields.