Coal production
0reported short tons
ALL STATUSES / CONTROLLER PORTFOLIO
Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.
MINE PORTFOLIO
2025-01-01 – 2026-10-18. All statuses records; production reporting is not required.
Material, method and type filters apply to this table. The portfolio’s status applies to the entire page. GEM fields describe their own release, not the selected MSHA year.
| Mine | Location / type | Coal · short tons | Hours worked | Violations | Accident records | On-site inspection hours |
|---|---|---|---|---|---|---|
| Bingham Canyon Mine4200149 · Active6/8 quarters reported | Salt Lake, UTSurface · MSHA: Copper Ore NEC | 0 | 3,389,047 | 246 | 46 | 1,136.0 |
| Boron Operations0400743 · Active6/8 quarters reported | Kern, CASurface · MSHA: Boron Minerals | 0 | 2,253,991 | 140 | 14 | 626.3 |
| Copperton Concentrator4201996 · Active6/8 quarters reported | Salt Lake, UTFacility · MSHA: Copper Ore NEC | 0 | 928,674 | 214 | 5 | 698.8 |
| Kennecott Keystone Underground4201392 · Active6/8 quarters reported | Salt Lake, UTUnderground · MSHA: Copper Ore NEC | 0 | 184,020 | 105 | 10 | 514.3 |
| Owens Lake Mine0402834 · Intermittent6/8 quarters reported | Inyo, CASurface · MSHA: Trona | 0 | 14,298 | 0 | 0 | 11.0 |
| BORON OPERATIONS UNDERGROUND MIN0405366 · Abandoned | Kern, CAUnderground · MSHA: Boron Minerals | — | — | 0 | 0 | — |
| Boron Refinery0403886 · Abandoned | Kern, CAFacility · MSHA: Boron Minerals | — | — | 0 | 0 | — |
| California Clay Pit0405170 · Abandoned | Inyo, CASurface · MSHA: Common Clays NEC | — | — | 0 | 0 | — |
| Excelsior Mine4502531 · Abandoned | Whatcom, WAUnderground · MSHA: Silver Ore | — | — | 0 | 0 | — |
| FLAMBEAU MINE4702920 · Abandoned | Rusk, WISurface · MSHA: Copper Ore NEC | — | — | 0 | 0 | — |
| GERSTLEY MINE0404953 · Abandoned | Inyo, CAUnderground · MSHA: Boron Minerals | — | — | 0 | 0 | — |
| GERSTLEY MINE0405300 · Abandoned | Inyo, CAFacility · MSHA: Boron Minerals | — | — | 0 | 0 | — |
| Humboldt Mill2003420 · Abandoned | Marquette, MISurface · MSHA: Iron Ore | — | — | 0 | 0 | — |
| Kennecott Barneys Canyon Mining4202040 · Abandoned | Salt Lake, UTSurface · MSHA: Gold Ore | — | — | 0 | 0 | — |
| Ledyard Plant0600018 · Abandoned | New London, CTSurface · MSHA: Crushed, Broken Sandstone | — | — | 0 | 0 | — |
| Oceanside Plant0402304 · Abandoned | San Diego, CASurface · MSHA: Crushed, Broken Sandstone | — | — | 0 | 0 | — |
| Quartz Hill Project5001230 · Abandoned | Aleutians East, AKSurface · MSHA: Molybdenum Ore | — | — | 0 | 0 | — |
| REDHILL MINE0404395 · Abandoned | Calaveras, CASurface · MSHA: Talc | — | — | 0 | 0 | — |
| RIDGEWAY MINE3800626 · Abandoned | Fairfield, SCSurface · MSHA: Gold Ore | — | — | 0 | 0 | — |
| Three Rivers Plant4102418 · Abandoned | Live Oak, TXSurface · MSHA: Construction Sand and Gravel | — | — | 0 | 0 | — |
| TOYON MILL0404490 · Abandoned | Calaveras, CAFacility · MSHA: Talc | — | — | 0 | 0 | — |
| Utah Concentrator North4200717 · Abandoned | Salt Lake, UTFacility · MSHA: Copper Ore NEC | — | — | 0 | 0 | — |
Production and hours sum available quarterly reports. — means unavailable; zero safety records means none in the selected imported period. Ownership reflects the current MSHA record.
LOCATION
8 of 22 mines with usable MSHA coordinates. Select a marker to open a mine.
2025 Q1 – 2026 Q4
Database snapshot · 2026-10-18. All 22 mines listed under this controller were checked; 5 have reports in the available quarters. Totals use current ownership.
reported short tons
reported employee hours
production ÷ hours worked
Missing values appear as —. Totals use available reports. Tons per hour requires production and hours for the same quarters and a nonzero hours total. * Striped bars mark partial mine coverage or an incomplete quarter. See the table for coverage.
| Quarter | Coal (short tons) | Hours worked | Tons / hour | Avg. employees | Coverage |
|---|---|---|---|---|---|
| 2025 Q1 | 0 | 1,267,115 | 0.00 | 2,349 | 5/5 mines reporting |
| 2025 Q2 | 0 | 1,030,261 | 0.00 | 2,097 | 5/5 mines reporting |
| 2025 Q3 | 0 | 1,085,434 | 0.00 | 2,083 | 5/5 mines reporting |
| 2025 Q4 | 0 | 1,093,133 | 0.00 | 2,053 | 5/5 mines reporting |
| 2026 Q1 | 0 | 1,146,397 | 0.00 | 2,185 | 5/5 mines reporting |
| 2026 Q2 | 0 | 1,147,690 | 0.00 | 2,198 | 5/5 mines reporting |
| 2026 Q3 | — | — | — | — | No report |
| 2026 Q4 | — | — | — | — | No report |
2025-01-01 – 2026-10-18
111 significant & substantial (S&S)
1 records classified as fatality
665 of 705 violations with amounts
86 inspections · 86 with hours
Counts are published records, including contractor records. * The quarter was incomplete at the snapshot date; recent counts may rise as reports arrive. — means no reported amount or hours. Portfolio totals use current membership.
| Quarter | Violations | S&S | Proposed USD | Accident records | Fatality records | Inspections | On-site hours |
|---|---|---|---|---|---|---|---|
| 2025-Q1 | 97 | 12 | 105,309.00 | 13 | 0 | 11 | 594.8 |
| 2025-Q2 | 78 | 13 | 69,361.00 | 9 | 0 | 13 | 315.3 |
| 2025-Q3 | 118 | 27 | 224,568.00 | 21 | 0 | 17 | 463.3 |
| 2025-Q4 | 194 | 26 | 178,676.00 | 13 | 0 | 10 | 523.5 |
| 2026-Q1 | 21 | 2 | 22,590.00 | 8 | 1 | 7 | 172.0 |
| 2026-Q2 | 127 | 13 | 181,674.00 | 3 | 0 | 11 | 552.5 |
| 2026-Q3 | 45 | 13 | 23,910.00 | 8 | 0 | 13 | 274.5 |
| 2026-Q4 * | 25 | 5 | — | 0 | 0 | 4 | 90.5 |
All violations issued in the selected period. Counts combine subsections.
56.12032 · $245.00 proposed
56.14112(b) · $1,219.00 proposed
103 (g) Written Notification Hazard Complaint Inspectio · 6.8 on-site hours
Regular Safety and Health Inspection · 116.0 on-site hours
56.14107(a) · $818.00 proposed
56.12004 · $818.00 proposed
56.20003(a) · S&S · $1,219.00 proposed
56.16009 · S&S · $1,968.00 proposed
Spot Inspection · 1.5 on-site hours
56.14100(b) · $267.00 proposed
56.14112(b) · $818.00 proposed
STRIKING OR BUMPING · DAYS RESTRICTED ACTIVITY ONLY
While trying to board the haul truck operator hit the right knee on the second rail on the ladder. EMT assessed IP and noted a purple mark on the front of their knee cap. IP was walking with a limp and said it was painful to press on the gas of haul truck. EMT sent IP to RMMC with supervisor.
103 (g) Written Notification Hazard Complaint Inspectio · 4.5 on-site hours
SLIP OR FALL OF PERSON · DAYS RESTRICTED ACTIVITY ONLY
Worker was walking to a hole they were about to measure when they tripped and rolled their ankle on uneven ground. Worker was assessed by EMT at 10:21am. EMT provided worker with an ice pack and advised them to go Medical Clinic for further evaluation. Supervisor took worker to MC.
HANDLING OF MATERIALS · DAYS RESTRICTED ACTIVITY ONLY
Operator walked from grader to talk to oncoming shift grader operator. Talked for a minute then proceeded to walk to board the Burnell bus when operator turned left to board bus, they felt a pop and some pain in left knee. Operator failed to report incident to leader after event happened. Went into RMMC after shift for further evaluation.
Impoundment Spot Inspection · 15.5 on-site hours
HANDLING OF MATERIALS · NO DYS AWY FRM WRK,NO RSTR ACT
Lifter on the drill that suspends the pipe down hole slipped and smashed the driller helper's finger between the pipe holder (or clamp) and the lifter.
HANDTOOLS (NONPOWERED) · NO DYS AWY FRM WRK,NO RSTR ACT
Drill crew was tripping in Tremie pipe and a driller assistant was attempting to remove the lifter with a pipe wrench when the pipe slipped downward causing the injured employee to get a finger pinched between the pipe wrench and the foot clamp. The injured employee sustained a laceration and possible fracture to employees right ring fingertip.
HANDLING OF MATERIALS · NO DYS AWY FRM WRK,NO RSTR ACT
Drill helper was helping to remove a sub adapter from the roughneck by holding the elevated sub adapter prior to release. Once it was released, the weight of the adapter caused the sub to drop slightly causing the drill helper to pinch their middle finger between the threads of the sub adapter and drill rod; causing a laceration and fracture of the finger tip.
Verbal Hazard Complaint Inspections · 17.0 on-site hours
POWERED HAULAGE · NO DYS AWY FRM WRK,NO RSTR ACT
Employee and a geo-tech were pull-testing bolts. A bolt plate was placed beneath one of the legs of the pull tester so the leg would not get trapped in the mesh. Tension was pulled and the bolt passed. The employee unscrewed the nut securing the pull testing machine to the bolt. When removing the nut, the bolt plate became loose and fell 3-4 ft hitting the employee in the lip.
POWERED HAULAGE · DAYS RESTRICTED ACTIVITY ONLY
IP stated while they were operating the haul truck, they hit a bump and got pulled by the wheel of the haul truck when they hit the bump. Felt a pain in their shoulder which worsened as they were required to pull hard on the steering wheel to get the truck to move. IP was assessed by EMT and was referred to RMMC.
MACHINERY · NO DYS AWY FRM WRK,NO RSTR ACT
The worker received a foreign body in the left eye following grinding. Visited medical clinic. Remove Foreign Body Cornea (with slit lamp): saline irrigation and anesthetized by 2 gtt(s) of Proparicaine. Foreign body removed with a needle. The eye was irrigated with saline after the procedure. Release full duties, may perform regular work. Released from care.
57.12028 · $2,133.00 proposed
57.14100(b) · $959.00 proposed
MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-18.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.
CFR headings link to the current Title 30 index; they are not historical legal determinations.