Coal production
133,613,189reported short tons
ACTIVE / CONTROLLER PORTFOLIO
Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.
MINE PORTFOLIO
2025-01-01 – 2026-10-18. Active records; production reporting is not required.
Material, method and type filters apply to this table. The portfolio’s status applies to the entire page. GEM fields describe their own release, not the selected MSHA year.
| Mine | Location / type | Coal · short tons | Hours worked | Violations | Accident records | On-site inspection hours |
|---|---|---|---|---|---|---|
| Bailey Mine3607230 · Active6/8 quarters reported | Greene, PAUnderground · MSHA: Coal (Bituminous) | 17,629,602 | 2,611,012 | 1,229 | 106 | 10,923.5 |
| BECKLEY POCAHONTAS MINE4605252 · Active6/8 quarters reported | Raleigh, WVUnderground · MSHA: Coal (Bituminous) | 1,788,402 | 1,258,929 | 741 | 20 | 5,914.5 |
| Beckley Pocahontas Plant4609216 · Active6/8 quarters reported | Raleigh, WVFacility · MSHA: Coal (Bituminous) | 0 | 99,192 | 10 | 1 | 226.5 |
| Black Thunder4800977 · Active6/8 quarters reported | Campbell, WYSurface · MSHA: Coal (Bituminous) | 70,462,955 | 2,525,675 | 176 | 23 | 917.3 |
| Cardinal Preparation Plant4609046 · Active6/8 quarters reported | Logan, WVFacility · MSHA: Coal (Bituminous) | 0 | 80,434 | 29 | 1 | 260.5 |
| Coal Creek Mine4801215 · Active6/8 quarters reported | Campbell, WYSurface · MSHA: Coal (Bituminous) | 2,572,759 | 107,835 | 26 | 0 | 237.8 |
| ENLOW FORK MINE3607416 · Active6/8 quarters reported | Washington, PAUnderground · MSHA: Coal (Bituminous) | 15,038,810 | 1,799,445 | 460 | 41 | 8,544.3 |
| HARVEY MINE3610045 · Active6/8 quarters reported | Greene, PAUnderground · MSHA: Coal (Bituminous) | 8,307,083 | 1,107,372 | 285 | 27 | 5,320.0 |
| Itmann No 54609569 · Active6/8 quarters reported | Wyoming, WVUnderground · MSHA: Coal (Bituminous) | 650,612 | 419,529 | 551 | 14 | 2,538.5 |
| Itmann No.5 Plant4609598 · Active6/8 quarters reported | Wyoming, WVFacility · MSHA: Coal (Bituminous) | 0 | 78,644 | 15 | 1 | 111.0 |
| LEER MINE4609192 · Active6/8 quarters reported | Taylor, WVUnderground · MSHA: Coal (Bituminous) | 6,991,302 | 1,840,279 | 424 | 32 | 4,435.5 |
| Leer Prep Plant4609191 · Active6/8 quarters reported | Taylor, WVFacility · MSHA: Coal (Bituminous) | 0 | 158,911 | 14 | 2 | 232.8 |
| Leer South Mine4604168 · Active6/8 quarters reported | Barbour, WVUnderground · MSHA: Coal (Bituminous) | 2,428,464 | 1,340,582 | 508 | 27 | 6,576.0 |
| Leer South Preparation Plant4608777 · Active6/8 quarters reported | Barbour, WVFacility · MSHA: Coal (Bituminous) | 0 | 156,565 | 15 | 0 | 193.5 |
| Mountaineer II Mine4609029 · Active6/8 quarters reported | Logan, WVUnderground · MSHA: Coal (Bituminous) | 1,811,088 | 1,173,667 | 950 | 19 | 5,541.8 |
| West Elk Mine0503672 · Active6/8 quarters reported | Gunnison, COUnderground · MSHA: Coal (Bituminous) | 5,932,112 | 858,989 | 482 | 19 | 4,555.5 |
Production and hours sum available quarterly reports. — means unavailable; zero safety records means none in the selected imported period. Ownership reflects the current MSHA record.
LOCATION
16 of 16 mines with usable MSHA coordinates. Select a marker to open a mine.
2025 Q1 – 2026 Q4
Database snapshot · 2026-10-18. All 16 mines listed under this controller were checked; 16 have reports in the available quarters. Totals use current ownership.
reported short tons
reported employee hours
production ÷ hours worked
Missing values appear as —. Totals use available reports. Tons per hour requires production and hours for the same quarters and a nonzero hours total. * Striped bars mark partial mine coverage or an incomplete quarter. See the table for coverage.
| Quarter | Coal (short tons) | Hours worked | Tons / hour | Avg. employees | Coverage |
|---|---|---|---|---|---|
| 2025 Q1 | 22,423,429 | 2,778,532 | 8.07 | 4,883 | 16/16 mines reporting |
| 2025 Q2 | 22,869,293 | 2,723,879 | 8.40 | 4,900 | 16/16 mines reporting |
| 2025 Q3 | 22,755,103 | 2,602,169 | 8.74 | 4,631 | 16/16 mines reporting |
| 2025 Q4 | 22,210,759 | 2,452,688 | 9.06 | 4,507 | 16/16 mines reporting |
| 2026 Q1 | 22,003,325 | 2,559,209 | 8.60 | 4,473 | 16/16 mines reporting |
| 2026 Q2 | 21,351,280 | 2,500,583 | 8.54 | 4,413 | 16/16 mines reporting |
| 2026 Q3 | — | — | — | — | No report |
| 2026 Q4 | — | — | — | — | No report |
2025-01-01 – 2026-10-18
685 significant & substantial (S&S)
2 records classified as fatality
5,398 of 5,915 violations with amounts
1,656 inspections · 1,656 with hours
Counts are published records, including contractor records. * The quarter was incomplete at the snapshot date; recent counts may rise as reports arrive. — means no reported amount or hours. Portfolio totals use current membership.
| Quarter | Violations | S&S | Proposed USD | Accident records | Fatality records | Inspections | On-site hours |
|---|---|---|---|---|---|---|---|
| 2025-Q1 | 856 | 90 | 832,281.00 | 33 | 0 | 196 | 9,672.0 |
| 2025-Q2 | 830 | 87 | 739,652.00 | 47 | 0 | 231 | 8,375.8 |
| 2025-Q3 | 854 | 68 | 428,583.00 | 44 | 0 | 234 | 8,180.3 |
| 2025-Q4 | 650 | 44 | 283,982.00 | 46 | 0 | 200 | 7,049.5 |
| 2026-Q1 | 879 | 119 | 669,526.00 | 51 | 0 | 226 | 7,310.8 |
| 2026-Q2 | 902 | 146 | 561,950.00 | 59 | 1 | 261 | 7,937.0 |
| 2026-Q3 | 809 | 115 | 352,187.00 | 53 | 1 | 260 | 7,268.5 |
| 2026-Q4 * | 135 | 16 | — | 0 | 0 | 48 | 735.0 |
All violations issued in the selected period. Counts combine subsections.
103(i) Spot Inspections · 0.0 on-site hours
103(i) Spot Inspections · 0.0 on-site hours
75.1505(b)
75.1718
75.400
75.340(a)(1)(i)
75.400
75.403
75.362(g)(2)
75.360(b)(4)
75.1505(b)
103(i) Spot Inspections · 6.0 on-site hours
103(i) Spot Inspections · 7.0 on-site hours
Health Technical Investigation · 1.0 on-site hours
103(i) Spot Inspections · 5.5 on-site hours
Non-Injury Accident Investigation · 8.0 on-site hours
103(i) Spot Inspections · 0.0 on-site hours
103(i) Spot Inspections · 7.5 on-site hours
Electrical Technical Investigation · 16.5 on-site hours
77.1110
75.1403 · S&S
75.333(c)(3)
75.400
75.333(c)(3)
75.400
MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-18.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.
CFR headings link to the current Title 30 index; they are not historical legal determinations.
EIA-923 · COAL RECEIPTS
Receipts reported by power plants and terminals, matched by MSHA mine ID.
| Quarter | Short tons | Heat · Btu/lb | Sulfur % | Ash % | Delivered USD/ton | |
|---|---|---|---|---|---|---|
| 2025-Q3 * | 11,101,477 | 9,762 | 0.74 | 5.85 | 46.06 | |
| 2025-Q4 | 16,344,064 | 9,665 | 0.66 | 5.63 | 45.53 | |
| 2026-Q1 | 14,139,148 | 9,703 | 0.69 | 5.69 | 45.89 | |
| 2026-Q2 | 12,816,068 | 9,839 | 0.73 | 5.76 | 48.55 | |
| 2026-Q3 * | 5,240,391 | 9,577 | 0.61 | 5.37 | 44.92 |
| Month / source | Mine | Receiving plant / supplier | Short tons | Delivered USD/ton | Heat · Btu/lb | Sulfur % | Ash % | Purchase | Transport |
|---|---|---|---|---|---|---|---|---|---|
| 2026-05EIA row 7917 · preliminary | BAILEY MINE3607230 | Monroe (MI)1733 · MI · CONSOL | 41,839 | 86.90 | 13,005 | 2.15 | 7.90 | ContractBIT | Rail / Great Lakes |
| 2026-05EIA row 7918 · preliminary | BAILEY MINE3607230 | Monroe (MI)1733 · MI · CONSOL | 77,604 | 77.31 | 13,095 | 2.14 | 7.80 | ContractBIT | Rail |
| 2026-05EIA row 7921 · preliminary | BLACK THUNDER4800977 | Monroe (MI)1733 · MI · ARCH COAL SALES | 173,503 | 38.85 | 8,980 | 0.31 | 5.00 | ContractSUB | Rail |
| 2026-05EIA row 7923 · preliminary | BLACK THUNDER4800977 | Monroe (MI)1733 · MI · ARCH COAL SALES | 108,663 | 38.77 | 8,930 | 0.34 | 5.40 | ContractSUB | Rail |
| 2026-05EIA row 7929 · preliminary | BLACK THUNDER4800977 | Clay Boswell1893 · MN · BLACK THUNDER - ARCH | 189,185 | 45.63 | 8,965 | 0.32 | 5.10 | ContractSUB | Rail |
| 2026-05EIA row 7951 · preliminary | BLACK THUNDER4800977 | Labadie2103 · MO · THUNDER BASIN | 220,060 | 29.48 | 9,000 | 0.25 | 4.60 | ContractSUB | Rail |
| 2026-05EIA row 8003 · preliminary | BAILEY MINE3607230 | Roxboro2712 · NC · CONSOL | 85,524 | 97.98 | 13,001 | 2.21 | 7.70 | ContractBIT | Rail |
| 2026-05EIA row 8012 · preliminary | BAILEY MINE3607230 | Marshall (NC)2727 · NC · CONSOL | 64,550 | 110.80 | 13,017 | 2.13 | 7.90 | ContractBIT | Rail |
| 2026-05EIA row 8016 · preliminary | BAILEY MINE3607230 | Marshall (NC)2727 · NC · CONSOL | 25,539 | 96.71 | 13,051 | 2.00 | 7.70 | ContractBIT | Rail |
| 2026-05EIA row 8117 · preliminary | BAILEY MINE3607230 | Wateree3297 · SC · CORE NATURAL RESOURCES, INC | 12,889 | 95.41 | 13,045 | 2.24 | 7.50 | ContractBIT | Rail |
| 2026-05EIA row 8135 · preliminary | BAILEY MINE3607230 | Kingston3407 · TN · CONSOL | 40,701 | 88.57 | 13,036 | 2.25 | 7.90 | ContractBIT | Rail |
| 2026-05EIA row 8136 · preliminary | BLACK THUNDER4800977 | Kingston3407 · TN · ARCH COAL SALES | 14,640 | 51.91 | 8,969 | 0.29 | 5.50 | ContractSUB | Rail |
| 2026-05EIA row 8209 · preliminary | BAILEY MINE3607230 | Mt Storm3954 · WV · CONSOL | 93,107 | 79.63 | 13,093 | 2.07 | 7.50 | ContractBIT | Rail |
| 2026-05EIA row 8215 · preliminary | BLACK THUNDER4800977 | South Oak Creek4041 · WI · CORE SALES LLC | 13,380 | 42.95 | 8,990 | 0.28 | 4.80 | ContractSUB | Rail |
| 2026-05EIA row 8218 · preliminary | BLACK THUNDER4800977 | Edgewater4050 · WI · ARCH COAL SALES | 16,338 | 46.27 | 8,784 | 0.43 | 5.70 | ContractSUB | Rail |
| 2026-05EIA row 8219 · preliminary | BLACK THUNDER4800977 | Edgewater4050 · WI · ARCH COAL SALES | 16,377 | 46.72 | 9,089 | 0.26 | 4.70 | ContractSUB | Rail |
| 2026-05EIA row 8227 · preliminary | COAL CREEK MINE4801215 | Dave Johnston4158 · WY · THUNDER BASIN | 78,844 | 20.03 | 8,373 | 0.36 | 6.40 | ContractSUB | Rail |
| 2026-05EIA row 8241 · preliminary | BLACK THUNDER4800977 | James H Miller Jr6002 · AL · ARCH/CORE SALES INC | 399,986 | 43.37 | 8,855 | 0.41 | 5.60 | ContractSUB | Rail |
| 2026-05EIA row 8244 · preliminary | BLACK THUNDER4800977 | James H Miller Jr6002 · AL · ARCH/CORE SALES INC | 32,007 | 42.65 | 8,733 | 0.43 | 5.50 | ContractSUB | Rail |
| 2026-05EIA row 8252 · preliminary | BLACK THUNDER4800977 | Newton6017 · IL · BLACK THUNDER - ARCH | 95,258 | —Not published | 9,000 | 0.25 | 4.50 | ContractSUB | Rail |
| 2026-05EIA row 8302 · preliminary | BLACK THUNDER4800977 | Iatan6065 · MO · CORE SALES LLC | 49,278 | 36.71 | 8,889 | 0.32 | 5.50 | SpotSUB | Rail |
| 2026-05EIA row 8308 · preliminary | BLACK THUNDER4800977 | Jeffrey Energy Center6068 · KS · CORE NATURAL RESOURCES, INC | 29,773 | 30.22 | 8,978 | 0.31 | 4.90 | SpotSUB | Rail |
| 2026-05EIA row 8310 · preliminary | BLACK THUNDER4800977 | Jeffrey Energy Center6068 · KS · CORE NATURAL RESOURCES, INC | 29,919 | 31.45 | 8,949 | 0.35 | 5.10 | SpotSUB | Rail |
| 2026-05EIA row 8311 · preliminary | BLACK THUNDER4800977 | Jeffrey Energy Center6068 · KS · CORE NATURAL RESOURCES, INC | 29,940 | 29.89 | 8,766 | 0.39 | 6.20 | SpotSUB | Rail |
| 2026-05EIA row 8313 · preliminary | BLACK THUNDER4800977 | Jeffrey Energy Center6068 · KS · CORE NATURAL RESOURCES, INC | 14,907 | 30.98 | 8,795 | 0.42 | 5.80 | SpotSUB | Rail |
Delivered cost includes transport and is not mine revenue. Missing prices remain blank. * Fewer than three months are published in the selected quarter. Receipts reflect the months EIA has published; an unfinished quarter is not comparable with a full quarter. Portfolio matches use current ownership.
Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions
EIA ANNUAL COAL REPORT · 2024
Annual county prices and a production-based allocation of county coal sales.
The estimate assumes each eligible mine receives its county-average price and shares county sales in proportion to production. Actual sales and prices can differ substantially. Unavailable estimates are excluded; this is not a total for the whole portfolio. Annual price data uses a separate window from the MSHA charts.
| Mine / county | Annual production · tons | County FOB · USD/ton | Est. sales · tons | Est. coal revenue · USD | Basis / availability |
|---|---|---|---|---|---|
| Black Thunder4800977 · Campbell, Wyoming | 44,480,976 | 13.96 | 44,477,605 | 620,907,365 | County allocation estimate26.16% of eligible county production11 eligible mines / 11 sales respondents |
| Beckley Pocahontas Mine4605252 · Raleigh, West Virginia | 1,180,158 | 145.53 | 1,207,752 | 175,764,145 | County allocation estimate16.70% of eligible county production12 eligible mines / 12 sales respondents |
| Mountaineer Ii Mine4609029 · Logan, West Virginia | 1,102,478 | 123.83 | 1,086,200 | 134,504,110 | County allocation estimate11.31% of eligible county production24 eligible mines / 24 sales respondents |
| Itmann No 54609569 · Wyoming, West Virginia | 397,470 | 151.85 | 404,975 | 61,495,405 | County allocation estimate6.01% of eligible county production18 eligible mines / 18 sales respondents |
| Coal Creek Mine4801215 · Campbell, Wyoming | 1,552,309 | 13.96 | 1,552,191 | 21,668,591 | County allocation estimate0.91% of eligible county production11 eligible mines / 11 sales respondents |
| West Elk Mine0503672 · Gunnison, Colorado | 3,705,019 | — | — | — | County sales or price not published1 eligible mines / 1 sales respondents |
| Bailey Mine3607230 · Greene, Pennsylvania | 10,761,880 | — | — | — | County sales or price not published3 eligible mines / 3 sales respondents |
| Enlow Fork Mine3607416 · Washington, Pennsylvania | 9,181,023 | — | — | — | County sales or price not published1 eligible mines / 1 sales respondents |
| Harvey Mine3610045 · Greene, Pennsylvania | 5,743,707 | — | — | — | County sales or price not published3 eligible mines / 3 sales respondents |
| Leer South Mine4604168 · Barbour, West Virginia | 2,556,403 | — | — | — | County sales or price not published2 eligible mines / 2 sales respondents |
| Leer South Preparation Plant4608777 · Barbour, West Virginia | 0 | — | — | — | Preparation plant2 eligible mines / 2 sales respondents |
| Cardinal Preparation Plant4609046 · Logan, West Virginia | 0 | 123.83 | — | — | Preparation plant24 eligible mines / 24 sales respondents |
| Leer Prep Plant4609191 · Taylor, West Virginia | 0 | — | — | — | Preparation plant1 eligible mines / 1 sales respondents |
| Leer Mine4609192 · Taylor, West Virginia | 3,650,142 | — | — | — | County sales or price not published1 eligible mines / 1 sales respondents |
| Beckley Pocahontas Plant4609216 · Raleigh, West Virginia | 0 | 145.53 | — | — | Preparation plant12 eligible mines / 12 sales respondents |
| Itmann No.5 Plant4609598 · Wyoming, West Virginia | 0 | 151.85 | — | — | Preparation plant18 eligible mines / 18 sales respondents |
Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.
EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index
Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.
SELECTED PORTFOLIO
Relationships reflect the selected mine status and current MSHA controller/operator fields.