Accumulation of combustible materials.
DEEP MINE 41 · 440722330 CFR 75.400 · $151.00 proposed penalty
Accumulation of combustible materials.
DEEP MINE 44 · 440730830 CFR 75.400 · Significant and substantial (S&S) · $1,320.00 proposed penalty
Travelways at surface installations.
Mammoth Coal Processing Pl & Riv Tipple · 460331730 CFR 77.205(b) · $151.00 proposed penalty
Dust accumulations in surface installations.
Mammoth Coal Processing Pl & Riv Tipple · 460331730 CFR 77.202 · $151.00 proposed penalty
Accumulation of combustible materials.
Jerry Fork Eagle · 460878730 CFR 75.400 · $366.00 proposed penalty
Mine ventilation plan; submission and approval.
Jerry Fork Eagle · 460878730 CFR 75.370(a)(1) · $432.00 proposed penalty
Condition and examination of firefighting equipment.
Glen Alum Tunnel Mine · 460937530 CFR 75.1100-3 · $165.00 proposed penalty
Permissible electric face equipment; maintenance.
Glen Alum Tunnel Mine · 460937530 CFR 75.503 · $151.00 proposed penalty
Electric equipment; examination, testing and maintenance.
Glen Alum Tunnel Mine · 460937530 CFR 75.512 · $151.00 proposed penalty
Mine ventilation plan; submission and approval.
Glen Alum Tunnel Mine · 460937530 CFR 75.370(a)(1) · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
Glen Alum Tunnel Mine · 460937530 CFR 75.202(a) · Significant and substantial (S&S) · $1,219.00 proposed penalty
Permanent splicing of trailing cables.
Glen Alum Tunnel Mine · 460937530 CFR 75.604(b) · Significant and substantial (S&S) · $1,219.00 proposed penalty
Cable fittings; suitability.
Glen Alum Tunnel Mine · 460937530 CFR 75.515 · $165.00 proposed penalty
Air quality detectors and measurement devices.
ROAD FORK #52 MINE · 460952230 CFR 75.320(a) · $4,383.00 proposed penalty
Escapeways; bituminous and lignite mines.
ROAD FORK #52 MINE · 460952230 CFR 75.380(d)(7)(vi) · $1,126.00 proposed penalty
Roof control plan.
ROAD FORK #52 MINE · 460952230 CFR 75.220(a)(1) · Significant and substantial (S&S) · $3,448.00 proposed penalty
Condition and examination of firefighting equipment.
ROAD FORK #52 MINE · 460952230 CFR 75.1100-3 · $432.00 proposed penalty
Mine ventilation plan; submission and approval.
ROAD FORK #52 MINE · 460952230 CFR 75.370(a)(1) · $755.00 proposed penalty
Temporary notations, revisions, and supplements.
ROAD FORK #52 MINE · 460952230 CFR 75.1202 · $209.00 proposed penalty
Mine ventilation plan; submission and approval.
BLACK EAGLE · 460955030 CFR 75.370(a)(1) · $193.00 proposed penalty
Electrical connections or splices; suitability.
KINGSTON SEWELL · 460963130 CFR 75.514 · $151.00 proposed penalty
Methane monitors.
KINGSTON SEWELL · 460963130 CFR 75.342(a)(4) · $151.00 proposed penalty
Spot Inspections
Jerry Fork Eagle · 4608787103(i) · 7.3 on-site hours reported
Atmospheric monitoring systems.
DEEP MINE 41 · 440722330 CFR 75.351(k) · $209.00 proposed penalty
Violation — cited standard not reported
Kingston Processing · 4604343$151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.