  1. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5020533
    Jerry Fork Eagle · 4608787

    30 CFR 75.1731(a) · $465.00 proposed penalty

  2. Mine ventilation plan; submission and approval.

    violationRecord 5091137
    ROAD FORK #52 MINE · 4609522

    30 CFR 75.370(a)(1) · $755.00 proposed penalty

  3. Roof control plan.

    violationRecord 5091136
    ROAD FORK #52 MINE · 4609522

    30 CFR 75.220(a)(1) · $2,936.00 proposed penalty

  4. Mine ventilation plan; submission and approval.

    violationRecord 5091135
    ROAD FORK #52 MINE · 4609522

    30 CFR 75.370(a)(1) · $697.00 proposed penalty

  5. Preshift examination at fixed intervals.

    violationRecord 5090973
    ROAD FORK #52 MINE · 4609522

    30 CFR 75.360(a)(1) · $177.00 proposed penalty

  6. Roof control plan.

    violationRecord 5020658
    BLACK EAGLE · 4609550

    30 CFR 75.220(a)(1) · $818.00 proposed penalty

  7. Mine ventilation plan; submission and approval.

    violationRecord 5020657
    BLACK EAGLE · 4609550

    30 CFR 75.370(a)(1) · $642.00 proposed penalty

  8. Roof control plan.

    violationRecord 5020656
    BLACK EAGLE · 4609550

    30 CFR 75.220(a)(1) · $818.00 proposed penalty

  9. Inspection of fire suppression devices.

    violationRecord 5090498
    Davy Branch Mine · 4609574

    30 CFR 75.1107-16(b) · $151.00 proposed penalty

  10. Spot Inspection

    inspectionRecord 7004346
    Kepler No. 1 Prep Plant · 4604637

    2.0 on-site hours reported

  11. Spot Inspections

    inspectionRecord F007E11
    Jerry Fork Eagle · 4608787

    103(i) · 8.5 on-site hours reported

  12. Mine ventilation plan; submission and approval.

    violationRecord 9880300
    DEEP MINE 41 · 4407223

    30 CFR 75.370(a)(1) · $313.00 proposed penalty

  13. Mine ventilation plan; submission and approval.

    violationRecord 9880299
    DEEP MINE 41 · 4407223

    30 CFR 75.370(a)(1) · $151.00 proposed penalty

  14. Mine ventilation plan; submission and approval.

    violationRecord 8303501
    DEEP MINE 41 · 4407223

    30 CFR 75.370(a)(1) · $336.00 proposed penalty

  15. Mine ventilation plan; submission and approval.

    violationRecord 8303500
    DEEP MINE 41 · 4407223

    30 CFR 75.370(a)(1) · $151.00 proposed penalty

  16. Drill dust control at underground areas of underground mines.

    violationRecord 8281021
    DEEP MINE 41 · 4407223

    30 CFR 72.630(b) · $151.00 proposed penalty

  17. Electric equipment; examination, testing and maintenance.

    violationRecord 8281020
    DEEP MINE 41 · 4407223

    30 CFR 75.512 · $151.00 proposed penalty

  18. Protection from falls of roof, face and ribs.

    violationRecord 8281019
    DEEP MINE 41 · 4407223

    30 CFR 75.202(a) · Significant and substantial (S&S) · $818.00 proposed penalty

  19. Power wires and cables; insulation and protection.

    violationRecord 9880993
    DEEP MINE 44 · 4407308

    30 CFR 75.517 · Significant and substantial (S&S) · $2,312.00 proposed penalty

  20. Permissible electric face equipment; maintenance.

    violationRecord 5020531
    Jerry Fork Eagle · 4608787

    30 CFR 75.503 · $432.00 proposed penalty

  21. Permissible electric face equipment; maintenance.

    violationRecord 5020530
    Jerry Fork Eagle · 4608787

    30 CFR 75.503 · $432.00 proposed penalty

  22. Permanent splicing of trailing cables.

    violationRecord 5020532
    Jerry Fork Eagle · 4608787

    30 CFR 75.604(b) · $755.00 proposed penalty

  23. Permanent splicing of trailing cables.

    violationRecord 9844180
    Rolling Thunder Mine · 4609111

    30 CFR 75.604(b) · $209.00 proposed penalty

  24. Permissible electric face equipment; maintenance.

    violationRecord 9844179
    Rolling Thunder Mine · 4609111

    30 CFR 75.503 · $432.00 proposed penalty

  25. Mine ventilation plan; submission and approval.

    violationRecord 5026072
    PANTHER EAGLE MINE · 4609212

    30 CFR 75.370(a)(1) · $432.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.