ACTIVE / CONTROLLER PORTFOLIO

ACNR Holdings, Inc

Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.

MSHA CONTROLLER ID0157801

MINE PORTFOLIO

6 of 6 mines and facilities

2025-01-01 – 2026-10-31. Active records; production reporting is not required.

MineLocation / typeCoal · short tonsHours workedViolationsAccident recordsOn-site inspection hours
Conner Run Dam and Fly Ash Impoundment4609072 · Active6/8 quarters reportedMarshall, WVFacility · MSHA: Coal (Bituminous)04,3394184.5
Harrison County Mine4601318 · Active6/8 quarters reportedWetzel, WVUnderground · MSHA: Coal (Bituminous)8,378,6271,641,378554784,614.8
Marion County Mine4601433 · Active6/8 quarters reportedMarion, WVUnderground · MSHA: Coal (Bituminous)10,664,5121,926,4039981536,784.8
MARSHALL COUNTY MINE4601437 · Active6/8 quarters reportedMarshall, WVUnderground · MSHA: Coal (Bituminous)16,866,4243,140,3331,6833548,208.8
Marshall County River Loadout4601438 · Active6/8 quarters reportedMarshall, WVFacility · MSHA: Coal (Bituminous)069,5892133.5
OHIO COUNTY MINE4601436 · Active6/8 quarters reportedMarshall, WVUnderground · MSHA: Coal (Bituminous)8,975,8021,739,3925681015,159.0

LOCATION

Portfolio map

6 of 6 mines with usable MSHA coordinates. Select a marker to open a mine.

Mine coordinates

2025-01-01 – 2026-10-31Applies to production, safety and portfolio metrics. Silica samples have separate filters.

Violations

3,809

571 significant & substantial (S&S)

  1. 2025 Q1445
  2. 2025 Q2431
  3. 2025 Q3594
  4. 2025 Q4393
  5. 2026 Q1345
  6. 2026 Q2590
  7. 2026 Q3786
  8. 2026 Q4 *225

Accident records

688

1 records classified as fatality

  1. 2025 Q183
  2. 2025 Q281
  3. 2025 Q3115
  4. 2025 Q481
  5. 2026 Q180
  6. 2026 Q297
  7. 2026 Q3132
  8. 2026 Q4 *19

Proposed penalties · USD

2,435,071.00

3,331 of 3,809 violations with amounts

  1. 2025 Q1252,258
  2. 2025 Q2242,509
  3. 2025 Q3455,343
  4. 2025 Q4222,274
  5. 2026 Q1285,799
  6. 2026 Q2555,069
  7. 2026 Q3421,819
  8. 2026 Q4 *—

On-site inspection hours

24,885.25

1,027 inspections · 1,027 with hours

  1. 2025 Q13,279.25
  2. 2025 Q23,510.25
  3. 2025 Q33,790.25
  4. 2025 Q43,144.25
  5. 2026 Q13,100.00
  6. 2026 Q23,380.75
  7. 2026 Q33,775.50
  8. 2026 Q4 *905.00
Quarterly safety data
QuarterViolationsS&SProposed USDAccident recordsFatality recordsInspectionsOn-site hours
2025-Q144555252,258.008301373,279.3
2025-Q243156242,509.008101363,510.3
2025-Q3594104455,343.0011501673,790.3
2025-Q439346222,274.008101213,144.3
2026-Q134544285,799.008001233,100.0
2026-Q259089555,069.009711253,380.8
2026-Q3786143421,819.0013201723,775.5
2026-Q4 *22534—19046905.0

Most cited CFR sections

All violations issued in the selected period. Counts combine subsections.

Safety activity

Open activity page ↗
  1. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 9933374
    OHIO COUNTY MINE · 4601436

    30 CFR 75.1731(c) · $151.00 proposed penalty

  2. Training of new miners; minimum courses of instruction; hours of instruction.

    violationRecord 9585007
    MARSHALL COUNTY MINE · 4601437

    30 CFR 48.5(b)(4) · $168.00 proposed penalty

  3. Mine emergency evacuation and firefighting program of instruction.

    violationRecord 9585006
    MARSHALL COUNTY MINE · 4601437

    30 CFR 75.1502 · $504.00 proposed penalty

  4. Mechanical equipment guards.

    violationRecord 9584997
    MARSHALL COUNTY MINE · 4601437

    30 CFR 77.400(a) · $165.00 proposed penalty

  5. Fall of roof or back

    accidentRecord 220250830013
    MARSHALL COUNTY MINE · 4601437

    Accident only

    Accident narrative

    An up planned roof fall occurred on 3/15/2025 at 14-13 crosscut on the haulage. The fall was 56' long by 16' wide 9-10' high. 14-13 was dangered off on both sides and will be cleaned up.

  6. Spot Inspections

    inspectionRecord F005C53
    OHIO COUNTY MINE · 4601436

    103(i) · 9.0 on-site hours reported

  7. Short circuit protection; ratings and settings of circuit breakers.

    violationRecord 9584661
    Harrison County Mine · 4601318

    30 CFR 75.601-1 · $245.00 proposed penalty

  8. Mine ventilation plan; submission and approval.

    violationRecord 9586926
    OHIO COUNTY MINE · 4601436

    30 CFR 75.370(a)(1) · $336.00 proposed penalty

  9. Accumulation of combustible materials.

    violationRecord 9586925
    OHIO COUNTY MINE · 4601436

    30 CFR 75.400 · $549.00 proposed penalty

  10. Mine ventilation plan; submission and approval.

    violationRecord 9936081
    OHIO COUNTY MINE · 4601436

    30 CFR 75.370(a)(1) · $226.00 proposed penalty

  11. Atmospheric monitoring systems.

    violationRecord 9933303
    MARSHALL COUNTY MINE · 4601437

    30 CFR 75.351(e)(1)(iv) · $151.00 proposed penalty

  12. Mechanical equipment guards.

    violationRecord 9933302
    MARSHALL COUNTY MINE · 4601437

    30 CFR 75.1722(a) · $165.00 proposed penalty

  13. Ventilation controls.

    violationRecord 9585005
    MARSHALL COUNTY MINE · 4601437

    30 CFR 75.333(c)(3) · $151.00 proposed penalty

  14. Inspection of fire suppression devices.

    violationRecord 9585004
    MARSHALL COUNTY MINE · 4601437

    30 CFR 75.1107-16(b) · $151.00 proposed penalty

  15. Handling of materials

    accidentRecord 220250790010
    Harrison County Mine · 4601318

    Days away from work only

    Accident narrative

    Injured employee was carrying a cinder block and stepped on a loose piece of coal/rock on the mine floor and rolled an ankle. Finished the shift but later noticed it was swollen. Sought treatment the following day and began missing work. No rules or regulations were violated, and employee has training and experience.

  16. Mine ventilation plan; submission and approval.

    violationRecord 9587105
    Marion County Mine · 4601433

    30 CFR 75.370(f)(3) · $165.00 proposed penalty

  17. Ventilation controls.

    violationRecord 9586924
    OHIO COUNTY MINE · 4601436

    30 CFR 75.333(c)(3) · $151.00 proposed penalty

  18. Mechanical equipment guards.

    violationRecord 9584996
    MARSHALL COUNTY MINE · 4601437

    30 CFR 77.400(a) · $165.00 proposed penalty

  19. Mechanical equipment guards.

    violationRecord 9584995
    MARSHALL COUNTY MINE · 4601437

    30 CFR 77.400(a) · $165.00 proposed penalty

  20. Accumulations of combustible materials.

    violationRecord 9584994
    MARSHALL COUNTY MINE · 4601437

    30 CFR 77.1104 · $151.00 proposed penalty

  21. Mechanical equipment guards.

    violationRecord 9584993
    MARSHALL COUNTY MINE · 4601437

    30 CFR 77.400(a) · $165.00 proposed penalty

  22. Accumulations of combustible materials.

    violationRecord 9584992
    MARSHALL COUNTY MINE · 4601437

    30 CFR 77.1104 · $151.00 proposed penalty

  23. Slip or fall of person

    accidentRecord 220250870003
    MARSHALL COUNTY MINE · 4601437

    Days away from work only

    Accident narrative

    Employee was passing thru a man door, when EE's foot caught the frame, and EE fell injuring EE's shoulder. PPE was not a factor, mining system was not a factor, compliance with rules and regulations was not a factor. Employee did not start missing time until 3/17/25.

  24. Spot Inspections

    inspectionRecord F0079F1
    Harrison County Mine · 4601318

    103(i) · 6.8 on-site hours reported

  25. Spot Inspections

    inspectionRecord F0097B7
    MARSHALL COUNTY MINE · 4601437

    103(i) · 6.0 on-site hours reported

Safety sources and definitions

MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-31.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.

CFR headings link to the current Title 30 index; they are not historical legal determinations.

Latest EIA month: 2026-08Source checked 2026-10-31 · publication lag differs from MSHA.

REPORTED RECEIPTS · SHORT TONS20,254,055411 rows · 27 receiving plants
HEAT CONTENT · BTU/LB12,805Weighted by reported tons
SULFUR / ASH · % BY WEIGHT3.45 / 9.05Separate averages over measured receipts
DELIVERED COST · USD/TON59.9351.8% of reported tons have usable costs
Quarterly receipts and quality
QuarterShort tonsHeat · Btu/lbSulfur %Ash %Delivered USD/ton
2025-Q3 *1,678,83712,7493.579.1958.37
2025-Q45,761,74712,8103.448.9860.49
2026-Q14,565,87312,8373.438.8758.40
2026-Q24,657,38812,7583.319.2059.29
2026-Q3 *3,590,21012,8413.599.1362.29
Month / sourceMineReceiving plant / supplierShort tonsDelivered USD/tonHeat · Btu/lbSulfur %Ash %PurchaseTransport
2026-08EIA row 13431 · preliminaryLOVERIDGE #224601433Brandon Shores602 · MD · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES67,465—Not published13,2452.958.40ContractBITRail
2026-08EIA row 13498 · preliminaryMCELROY MINE4601437Clifty Creek983 · IN · ACNR COAL SALES, Inc.55,31360.0212,8023.208.30ContractBITRiver
2026-08EIA row 13579 · preliminaryMCELROY MINE4601437Ghent1356 · KY · ACNR COAL SALES, Inc.24,35847.5412,7933.108.30ContractBITRiver
2026-08EIA row 13584 · preliminaryMCELROY MINE4601437Ghent1356 · KY · ACNR COAL SALES, Inc.37,52161.6812,7762.788.40ContractBITRiver
2026-08EIA row 13588 · preliminaryMCELROY MINE4601437Ghent1356 · KY · ACNR COAL SALES, Inc.38,05555.4512,7843.178.50ContractBITRiver
2026-08EIA row 13665 · preliminaryLOVERIDGE #224601433Monroe (MI)1733 · MI · AMERICAN NATURAL SUPPLY, LLC.19,25574.3413,2512.708.20ContractBITRail / Great Lakes
2026-08EIA row 13666 · preliminaryLOVERIDGE #224601433Monroe (MI)1733 · MI · AMERICAN NATURAL SUPPLY, LLC.15,30282.9613,3262.697.80ContractBITRail / Great Lakes
2026-08EIA row 13753 · preliminaryLOVERIDGE #224601433Roxboro2712 · NC · ACNR COAL SALES, Inc.24,88897.6113,2333.048.60ContractBITRail
2026-08EIA row 13757 · preliminaryLOVERIDGE #224601433Roxboro2712 · NC · ACNR COAL SALES, Inc.12,445103.9213,0453.029.90ContractBITRail
2026-08EIA row 13791 · preliminarySHOEMAKER MINE4601436Cardinal2828 · OH · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES37,239—Not published12,7244.178.20ContractBITRiver
2026-08EIA row 13792 · preliminaryMCELROY MINE4601437Cardinal2828 · OH · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES42,998—Not published12,7592.848.20ContractBITRiver
2026-08EIA row 13795 · preliminaryMCELROY MINE4601437Cardinal2828 · OH · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES15,994—Not published12,8082.888.30ContractBITRiver
2026-08EIA row 13797 · preliminarySHOEMAKER MINE4601436Cardinal2828 · OH · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES10,815—Not published12,7054.108.20ContractBITRiver
2026-08EIA row 13800 · preliminaryMCELROY MINE4601437Cardinal2828 · OH · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES12,505—Not published12,8972.888.20ContractBITRiver
2026-08EIA row 13801 · preliminarySHOEMAKER MINE4601436Cardinal2828 · OH · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES51,845—Not published12,7373.528.30ContractBITRiver
2026-08EIA row 13806 · preliminaryMCELROY MINE4601437Miami Fort2832 · OH · BLACKHAWK COAL SALES, LLC9,807—Not published12,7922.918.30SpotBITRiver
2026-08EIA row 13808 · preliminaryMCELROY MINE4601437Miami Fort2832 · OH · BLACKHAWK COAL SALES, LLC1,526—Not published13,5213.447.90SpotBITRiver
2026-08EIA row 13809 · preliminaryMCELROY MINE4601437Miami Fort2832 · OH · BLACKHAWK COAL SALES, LLC4,956—Not published13,1153.348.30SpotBITRiver
2026-08EIA row 13810 · preliminaryMCELROY MINE4601437Miami Fort2832 · OH · AMERICAN ENERGY65,050—Not published12,7792.778.40SpotBITRiver
2026-08EIA row 13811 · preliminaryMCELROY MINE4601437Miami Fort2832 · OH · AMERICAN ENERGY56,117—Not published12,7542.828.60SpotBITRiver
2026-08EIA row 13816 · preliminaryMCELROY MINE4601437Kyger Creek2876 · OH · ACNR COAL SALES, Inc.70,23453.5612,7224.228.20ContractBITRiver
2026-08EIA row 13950 · preliminaryMCELROY MINE4601437John E Amos3935 · WV · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES16,55457.4612,6852.748.94ContractBITRiver
2026-08EIA row 13951 · preliminarySHOEMAKER MINE4601436John E Amos3935 · WV · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES13,41258.1812,6105.228.34ContractBITRiver
2026-08EIA row 13953 · preliminaryMCELROY MINE4601437John E Amos3935 · WV · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES6,00353.1412,7302.718.98ContractBITRiver
2026-08EIA row 13954 · preliminarySHOEMAKER MINE4601436John E Amos3935 · WV · AMERICAN CONSOLIDATED NATURAL RESOURCES COAL SALES2,05760.3312,5805.248.29ContractBITRiver
Coverage, sources and calculations
  • Reported coal receipts at EIA-923 power plants/terminals; this is not a census of mine shipments, exports or metallurgical sales.
  • Matches use only the published MSHA ID, normalized to seven digits. Unidentified mine origins remain in the source table but are not assigned to a mine.
  • Portfolio attribution uses current MSHA ownership, not ownership at the shipment date. Receipts and production can differ because of timing, stocks and coverage.
  • Quality means are weighted by positive reported tons with that measurement. Delivered cost uses only rows with published cost, positive heat and positive tons; missing/withheld costs are never zero-filled.
  • USD/ton = (cents/MMBtu ÷ 100) × MMBtu/ton. This is plant delivered cost, not mine sales price or revenue.
  • Receipt month is as published, including records supplied by annual respondents. Recent months are preliminary and subject to revision. Missing rows do not prove zero shipments.

Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions

  • 2026 · preliminary · EIA923_Schedules_2_3_4_5_M_08_2026_22OCT2026.xlsx · Page 5 Fuel Receipts and Costs
  • 2025 · final · EIA923_Schedules_2_3_4_5_M_12_2025_Final.xlsx · Page 5 Fuel Receipts and Costs

Latest priced year: 2024Source checked 2026-10-31. Prices apply only to their calendar year.

FOB PRICE BENCHMARK · USD/TON—Weighted by estimated sales of covered mines
ESTIMATED SALES · SHORT TONS—Allocated from published county sales
ESTIMATED COAL REVENUE · USD—Covered mines only · not reported revenue
ANNUAL PRODUCTION COVERED0.0%0 of 4 producing annual mine records
Mine / countyAnnual production · tonsCounty FOB · USD/tonEst. sales · tonsEst. coal revenue · USDBasis / availability
Harrison County Mine4601318 · Wetzel, West Virginia5,579,207———County sales or price not published1 eligible mines / 1 sales respondents
Marion County Mine4601433 · Marion, West Virginia5,645,400———County sales or price not published2 eligible mines / 2 sales respondents
Ohio County Mine4601436 · Marshall, West Virginia5,558,609———County sales or price not published2 eligible mines / 2 sales respondents
Marshall County Mine4601437 · Marshall, West Virginia9,000,360———County sales or price not published2 eligible mines / 2 sales respondents
Marshall County River Loadout4601438 · Marshall, West Virginia0———Preparation plant2 eligible mines / 2 sales respondents
Conner Run Dam and Fly Ash Impoundment4609072 · Location unavailable————No matching annual production record
Method, assumptions and source records
  1. This is an annual county-sales allocation, not reported mine or company revenue. Currency is nominal USD in the source year; quantities are short tons.
  2. Mine share = same-year annual mine production / eligible same-county production. Estimated sales = published county sales × share. Estimated coal revenue = estimated sales × published county average FOB price.
  3. The model assumes eligible mines share county sales in proportion to production and receive the county-average price. Matching mine counts is a check, not proof of identical respondents. Mine quality, contracts and sales timing can differ substantially. No statistical confidence interval is implied.
  4. FOB excludes transport and insurance. EIA-923 delivered costs do not enter this model. No grade premium, state/national fallback, quarterly apportionment or carry-forward to a later year is applied.
  5. Eligibility follows the source's production threshold and excludes preparation-only and refuse operations. Withheld values, inconsistent county counts and missing/ambiguous locations produce no estimate.
  6. County sales are published in thousands of tons and prices to cents. Calculations retain precision, but the inputs are rounded and the allocation is approximate.
  7. Portfolio attribution uses current MSHA ownership, not ownership during the sales year. Covered-mine sums exclude unavailable estimates and must not be read as whole-company revenue. Coverage denominators use the annual EIA mine-production release.

Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.

EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index

Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.

SELECTED PORTFOLIO

4 linked operators.

Relationships reflect the selected mine status and current MSHA controller/operator fields.