Warrior Met Coal Mining, LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Protection from falls of roof, face and ribs.
No 4 Mine · 010124730 CFR 75.202(a) · $504.00 proposed penalty
Air quality.
No 7 Mine · 010140130 CFR 75.321(a)(1) · $313.00 proposed penalty
Protection from falls of roof, face and ribs.
No 7 Mine · 010140130 CFR 75.202(a) · Significant and substantial (S&S) · $2,936.00 proposed penalty
Spot Inspections
No 4 Mine · 0101247103(i) · 6.3 on-site hours reported
Spot Inspections
No 7 Mine · 0101401103(i) · 3.5 on-site hours reported
Weekly examination.
No 7 Mine · 010140130 CFR 75.364(g) · $313.00 proposed penalty
Protection from falls of roof, face and ribs.
No 7 Mine · 010140130 CFR 75.202(a) · $592.00 proposed penalty
Verbal Hazard Complaint Inspections
No 7 Mine · 01014011.0 on-site hours reported
Roof control plan.
No 4 Mine · 010124730 CFR 75.220(a)(1) · $465.00 proposed penalty
Escapeways; bituminous and lignite mines.
No 4 Mine · 010124730 CFR 75.380(d)(7)(iv) · Significant and substantial (S&S) · $9,757.00 proposed penalty
Travelways at surface installations.
No 7 Mine · 010140130 CFR 77.205(b) · Significant and substantial (S&S) · $1,219.00 proposed penalty
Insulating mats at power switches.
No 7 Mine · 010140130 CFR 77.513 · $245.00 proposed penalty
Travelways at surface installations.
No 7 Mine · 010140130 CFR 77.205(b) · $245.00 proposed penalty
Insulating mats at power switches.
No 7 Mine · 010140130 CFR 77.513 · $245.00 proposed penalty
Insulating mats at power switches.
No 7 Mine · 010140130 CFR 77.513 · $245.00 proposed penalty
Cable fittings; suitability.
No 7 Mine · 010140130 CFR 77.505 · $245.00 proposed penalty
Electric equipment; examination, testing, and maintenance.
No 7 Mine · 010140130 CFR 77.502 · $245.00 proposed penalty
Travelways at surface installations.
No 7 Mine · 010140130 CFR 77.205(e) · $245.00 proposed penalty
Surface installations; general.
No 7 Mine · 010140130 CFR 77.200 · $549.00 proposed penalty
Travelways at surface installations.
No 7 Mine · 010140130 CFR 77.205(e) · Significant and substantial (S&S) · $4,047.00 proposed penalty
Electric equipment; examination, testing, and maintenance.
No 7 Mine · 010140130 CFR 77.502 · $818.00 proposed penalty
Mechanical equipment guards.
No 7 Mine · 010140130 CFR 77.400(d) · $366.00 proposed penalty
Mechanical equipment guards.
No 7 Mine · 010140130 CFR 77.400(d) · $366.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
No 7 Mine · 010140130 CFR 77.1606(c) · $245.00 proposed penalty
Travelways at surface installations.
No 7 Mine · 010140130 CFR 77.205(e) · $818.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.