Warrior Met Coal BC, LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Accumulation of combustible materials.
Blue Creek Mine No. 1 · 010344830 CFR 75.400 · $193.00 proposed penalty
Power wires and cables; insulation and protection.
Blue Creek Mine No. 1 · 010344830 CFR 75.517 · Significant and substantial (S&S) · $642.00 proposed penalty
Protection from falls of roof, face and ribs.
Blue Creek Mine No. 1 · 010344830 CFR 75.202(a) · $245.00 proposed penalty
Maintenance of incombustible content of rock dust.
Blue Creek Mine No. 1 · 010344830 CFR 75.403 · $193.00 proposed penalty
Maintenance of incombustible content of rock dust.
Blue Creek Mine No. 1 · 010344830 CFR 75.403 · $193.00 proposed penalty
Protection from falls of roof, face and ribs.
Blue Creek Mine No. 1 · 010344830 CFR 75.202(a) · $245.00 proposed penalty
Ventilation controls.
Blue Creek Mine No. 1 · 010344830 CFR 75.333(c)(3) · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
Blue Creek Mine No. 1 · 010344830 CFR 75.1731(a) · $151.00 proposed penalty
Escapeways; bituminous and lignite mines.
Blue Creek Mine No. 1 · 010344830 CFR 75.380(d)(7)(vi) · $151.00 proposed penalty
Mechanical equipment guards.
Blue Creek Mine No. 1 · 010344830 CFR 75.1722(a) · Significant and substantial (S&S) · $959.00 proposed penalty
Escapeways; bituminous and lignite mines.
Blue Creek Mine No. 1 · 010344830 CFR 75.380(d)(7)(vii)(B) · Significant and substantial (S&S) · $7,084.00 proposed penalty
Escapeways; bituminous and lignite mines.
Blue Creek Mine No. 1 · 010344830 CFR 75.380(d)(7)(iv) · Significant and substantial (S&S) · $7,084.00 proposed penalty
Protection from falls of roof, face and ribs.
Blue Creek Mine No. 1 · 010344830 CFR 75.202(a) · $245.00 proposed penalty
Roof control plan.
Blue Creek Mine No. 1 · 010344830 CFR 75.220(a)(1) · $226.00 proposed penalty
Protection from falls of roof, face and ribs.
Blue Creek Mine No. 1 · 010344830 CFR 75.202(a) · Significant and substantial (S&S) · $1,219.00 proposed penalty
Protection from falls of roof, face and ribs.
Blue Creek Mine No. 1 · 010344830 CFR 75.202(a) · $245.00 proposed penalty
Protection from falls of roof, face and ribs.
Blue Creek Mine No. 1 · 010344830 CFR 75.202(a) · $245.00 proposed penalty
Spot Inspections
Blue Creek Mine No. 1 · 0103448103(i) · 14.3 on-site hours reported
Maintenance of incombustible content of rock dust.
Blue Creek Mine No. 1 · 010344830 CFR 75.403 · $193.00 proposed penalty
Maintenance of incombustible content of rock dust.
Blue Creek Mine No. 1 · 010344830 CFR 75.403 · $193.00 proposed penalty
Maintenance of incombustible content of rock dust.
Blue Creek Mine No. 1 · 010344830 CFR 75.403 · $193.00 proposed penalty
Emergency Response Plan; refuge alternatives.
Blue Creek Mine No. 1 · 010344830 CFR 75.1507(a)(2) · $151.00 proposed penalty
Identification of circuit breakers.
Blue Creek Mine No. 1 · 010344830 CFR 75.904 · $151.00 proposed penalty
Short circuit protection of trailing cables.
Blue Creek Mine No. 1 · 010344830 CFR 75.601 · $151.00 proposed penalty
Condition and examination of firefighting equipment.
Blue Creek Mine No. 1 · 010344830 CFR 75.1100-3 · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.