Vulcan Construction Materials, LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Safety defects; examination, correction and records.
Quinton Twp Pit · 280101430 CFR 56.14100(d) · $151.00 proposed penalty
Handling of materials
VILLA RICA QUARRY · 0900736Days restricted activity only
Accident narrative
Employee was cutting metal when EE tried moving a piece EE felt pain in EE's arm.
Other
Frederick Quarry · 1800729Injuries due to natural causes
Accident narrative
Customer (Dennis Trucking) was found unresponsive and transported by ambulance where EE later died.
Non-Chargeable Accident Investigation
Frederick Quarry · 18007297.0 on-site hours reported
Regular Safety and Health Inspection
Quinton Twp Pit · 28010149.3 on-site hours reported
Regular Safety and Health Inspection
LIBERTY QUARRY · 380000329.0 on-site hours reported
Regular Safety and Health Inspection
Dixie Lee Quarry · 400142724.0 on-site hours reported
Spot Inspection
Rogersville Quarry · 40027223.5 on-site hours reported
Violation — cited standard not reported
Frederick Quarry · 1800729Slip or fall of person
Wolman · 0700112Days away from work only
Accident narrative
The employee was replacing a ground fault cable for a dredge, as EE was walking down a berm EE slipped and fell to the ground.
Regular Safety and Health Inspection
Barin Quarry · 090007222.5 on-site hours reported
Regular Safety and Health Inspection
STOKESDALE QUARRY · 31000885.3 on-site hours reported
Regular Safety and Health Inspection
Helotes Quarry · 410297616.0 on-site hours reported
Horns and backup alarms.
Barin Quarry · 090007230 CFR 56.14132(a) · $151.00 proposed penalty
Combustible waste.
Barin Quarry · 090007230 CFR 56.4104(b) · $151.00 proposed penalty
Electrical conductors.
Barin Quarry · 090007230 CFR 56.12004 · $151.00 proposed penalty
General requirements.
Barin Quarry · 090007230 CFR 56.4200(b)(2) · $151.00 proposed penalty
Safety defects; examination, correction and records.
Barin Quarry · 090007230 CFR 56.14100(c) · $151.00 proposed penalty
Handling of materials
Puddledock Sand & Gravel · 4402424Days away from work only
Accident narrative
EE was shoveling material off of C-15 when they felt a pain in lower back. Did not seek medical treatment until 7/15/2025.
Regular Safety and Health Inspection
Manassas · 440015926.5 on-site hours reported
Moving machine parts.
Readyville Quarry · 400013330 CFR 56.14107(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
Hermitage Quarry · 400010313.0 on-site hours reported
Regular Safety and Health Inspection
Readyville Quarry · 40001339.0 on-site hours reported
Handling of materials
Glen Gardner Quarry · 2800009Days away from work only
Accident narrative
Employee was working with another employee trying to remove a pin holding the hydraulic cylinder on a rock hammer. The employee requested to seek medical attention on August 6, 2025
Special Emphasis Programs
HELENA QUARRY · 01005262.0 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.