Peabody Midwest Mining, LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Special Emphasis Programs
Preparation Plant · 11025461.5 on-site hours reported
Spot Inspections
Francisco Underground Pit · 1202295103(i) · 6.8 on-site hours reported
Surface installations; general.
Francisco Underground Pit · 120229530 CFR 77.200 · $151.00 proposed penalty
Regular Safety and Health Inspection
Francisco Underground Pit · 1202295523.3 on-site hours reported
Examination and maintenance of firefighting equipment.
Francisco Mine · 120214730 CFR 77.1110 · $151.00 proposed penalty
Spot Inspections
Francisco Underground Pit · 1202295103(i) · 7.5 on-site hours reported
Mine ventilation plan; submission and approval.
Francisco Underground Pit · 120229530 CFR 75.370(a)(1) · $432.00 proposed penalty
103 (g) Written Notification Hazard Complaint Inspectio
Francisco Underground Pit · 12022954.8 on-site hours reported
Spot Inspections
Francisco Underground Pit · 1202295103(i) · 4.5 on-site hours reported
Temporary notations, revisions, and supplements.
Francisco Underground Pit · 120229530 CFR 75.1202 · $398.00 proposed penalty
Spot Inspections
Francisco Underground Pit · 1202295103(i) · 4.0 on-site hours reported
Roof control plan.
Francisco Underground Pit · 120229530 CFR 75.220(a)(1) · $313.00 proposed penalty
Protection from falls of roof, face and ribs.
Francisco Underground Pit · 120229530 CFR 75.202(a) · $226.00 proposed penalty
Protection from falls of roof, face and ribs.
Francisco Underground Pit · 120229530 CFR 75.202(a) · $226.00 proposed penalty
Regular Safety and Health Inspection
Preparation Plant · 110254627.5 on-site hours reported
Spot Inspections
Francisco Underground Pit · 1202295103(i) · 5.5 on-site hours reported
Mechanical equipment guards.
Francisco Underground Pit · 120229530 CFR 75.1722(b) · Significant and substantial (S&S) · $1,679.00 proposed penalty
Health Technical Investigation
Francisco Underground Pit · 12022954.0 on-site hours reported
Nonpermissible diesel-powered equipment; electrical system design and performance requirements.
Francisco Underground Pit · 120229530 CFR 75.1910(o) · $151.00 proposed penalty
Spot Inspections
Francisco Underground Pit · 1202295103(i) · 6.3 on-site hours reported
Mine ventilation plan; submission and approval.
Francisco Underground Pit · 120229530 CFR 75.370(a)(1) · $504.00 proposed penalty
Electric equipment; examination, testing and maintenance.
Francisco Underground Pit · 120229530 CFR 75.512 · Significant and substantial (S&S) · $1,679.00 proposed penalty
Roof control plan.
Francisco Underground Pit · 120229530 CFR 75.220(a)(1) · $151.00 proposed penalty
Criteria—Haulage; general.
Francisco Underground Pit · 120229530 CFR 75.1403-10(i) · $226.00 proposed penalty
Accumulation of combustible materials.
Francisco Underground Pit · 120229530 CFR 75.400 · $2,503.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.