ICG BECKLEY LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Maintenance of diesel-powered equipment.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.1914(e) · $288.00 proposed penalty
Electric equipment and circuits; overload and short circuit protection.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.518 · $432.00 proposed penalty
Mine ventilation plan; submission and approval.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.370(a)(1) · $432.00 proposed penalty
Fall of roof or back
BECKLEY POCAHONTAS MINE · 4605252No dys awy frm wrk,no rstr act
Accident narrative
While bent over putting oil in bolter a piece of roof rock fell and hit them on their arm/shoulder. Because they were bent over in the walkway of the machine, the rock fell perpendicular and broke across the machine. The initial rock measured approximately 77" long, 36" wide, and 2 �" thick. Mining height in this area is 13'.
Spot Inspections
BECKLEY POCAHONTAS MINE · 4605252103(i) · 14.3 on-site hours reported
Methane monitors.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.342(a)(4) · $549.00 proposed penalty
Roof control plan.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.220(a)(1) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Roof control plan.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.220(a)(1) · $9,004.00 proposed penalty
Protection from falls of roof, face and ribs.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.202(a) · $1,679.00 proposed penalty
Inspection of fire suppression devices.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.1107-16(b) · $151.00 proposed penalty
Accumulation of combustible materials.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.400 · $267.00 proposed penalty
Electric equipment; examination, testing and maintenance.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.512 · $465.00 proposed penalty
Frequency of examinations.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.512-2 · $1,037.00 proposed penalty
Proximity detection systems.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.1732(a) · $2,133.00 proposed penalty
Electric equipment; examination, testing and maintenance.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.512 · $465.00 proposed penalty
Electric equipment; examination, testing and maintenance.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.512 · $193.00 proposed penalty
Electric equipment; examination, testing and maintenance.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.512 · $193.00 proposed penalty
Roof control plan.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.220(a)(1) · $818.00 proposed penalty
Temporary, portable containers.
Beckley Pocahontas Plant · 460921630 CFR 47.44(b) · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
Beckley Pocahontas Plant · 460921630 CFR 77.1606(c) · $151.00 proposed penalty
Regular Safety and Health Inspection
BECKLEY POCAHONTAS MINE · 4605252732.5 on-site hours reported
Protection from falls of roof, face and ribs.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.202(a) · Significant and substantial (S&S) · $1,679.00 proposed penalty
Accumulation of combustible materials.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.400 · $267.00 proposed penalty
Spot Inspection
BECKLEY POCAHONTAS MINE · 460525218.5 on-site hours reported
Protection from falls of roof, face and ribs.
BECKLEY POCAHONTAS MINE · 460525230 CFR 75.202(a) · $1,679.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.