HM Pacific Northwest, Inc. safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Regular Safety and Health Inspection
Enumclaw Pit & Plant · 45006099.0 on-site hours reported
Splices and repairs of power cables.
Enumclaw Pit & Plant · 450060930 CFR 56.12013 · $1,431.00 proposed penalty
Moving machine parts.
Enumclaw Pit & Plant · 450060930 CFR 56.14107(a) · $642.00 proposed penalty
Protection of persons at switchgear.
Enumclaw Pit & Plant · 450060930 CFR 56.12020 · $1,431.00 proposed penalty
Construction and maintenance of guards.
Enumclaw Pit & Plant · 450060930 CFR 56.14112(b) · $1,431.00 proposed penalty
Moving machine parts.
Enumclaw Pit & Plant · 450060930 CFR 56.14107(a) · $1,431.00 proposed penalty
Impoundment Spot Inspection
Lewisville Pit · 45032933.0 on-site hours reported
Regular Safety and Health Inspection
North Bend · 45035478.3 on-site hours reported
Safety defects; examination, correction and records.
North Bend · 450354730 CFR 56.14100(b) · $549.00 proposed penalty
Regular Safety and Health Inspection
Cadman Longview (Gold Bar) Pit · 450359114.8 on-site hours reported
Housekeeping.
Cadman Longview (Gold Bar) Pit · 450359130 CFR 56.20003(a) · $398.00 proposed penalty
Electrical conductors.
Cadman Longview (Gold Bar) Pit · 450359130 CFR 56.12004 · $398.00 proposed penalty
Regular Safety and Health Inspection
Thunder Mountain Quarry · 45011275.5 on-site hours reported
Berms or guardrails.
Thunder Mountain Quarry · 450112730 CFR 56.9300(b) · Significant and substantial (S&S) · $226.00 proposed penalty
Powered haulage
Sumner Pit And Plant · 4500705No dys awy frm wrk,no rstr act
Accident narrative
Operator was hauling mud in a 980H loader when EE hit a bump in the haul road and received a possible pinched nerve in EE's neck. EE is seeing a physical therapist for pain relief. No time lost, no light duty restrictions, still working job of injury.
Identification of power switches.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.12018 · $193.00 proposed penalty
Identification of power switches.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.12018 · $193.00 proposed penalty
Housekeeping.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.20003(a) · Significant and substantial (S&S) · $959.00 proposed penalty
Correction of hazardous conditions.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.3200 · Significant and substantial (S&S) · $3,184.00 proposed penalty
Regular Safety and Health Inspection
Sumner Pit And Plant · 45007056.5 on-site hours reported
Examination of working places.
Sumner Pit And Plant · 450070530 CFR 56.18002(b) · $151.00 proposed penalty
Controls and switches.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.12002 · $642.00 proposed penalty
Scaffolds and working platforms.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.11027 · $193.00 proposed penalty
Horns and backup alarms.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.14132(a) · $642.00 proposed penalty
Construction and maintenance of guards.
Heidelberg Materials High Rock Quarry · 450199930 CFR 56.14112(a)(1) · $288.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.