Regular Safety and Health Inspection
MMC Materials, Inc. · 220047813.5 on-site hours reported
Regular Safety and Health Inspection
MMC Materials, Inc. · 22004784.3 on-site hours reported
Safety defects; examination, correction and records.
Hard Rock Sand and Gravel · 160155330 CFR 56.14100(b) · Significant and substantial (S&S) · $1,037.00 proposed penalty
Regular Safety and Health Inspection
Hard Rock Sand and Gravel · 16015537.3 on-site hours reported
Safety defects; examination, correction and records.
Hard Rock Sand and Gravel · 160155330 CFR 56.14100(b) · $209.00 proposed penalty
Combustible waste.
Hard Rock Sand and Gravel · 160155330 CFR 56.4104(b) · $209.00 proposed penalty
Berms or guardrails.
Hard Rock Sand and Gravel · 160155330 CFR 56.9300(b) · Significant and substantial (S&S) · $3,448.00 proposed penalty
Regular Safety and Health Inspection
MMC Materials, Inc. · 22004783.0 on-site hours reported
103 (g) Written Notification Hazard Complaint Inspectio
Hard Rock Sand and Gravel · 16015533.3 on-site hours reported
Regular Safety and Health Inspection
Hard Rock Sand and Gravel · 16015537.0 on-site hours reported
Securing gas cylinders.
Hard Rock Sand and Gravel · 160155330 CFR 56.16005 · $209.00 proposed penalty
Requirement for container labels.
Hard Rock Sand and Gravel · 160155330 CFR 47.41(a) · $209.00 proposed penalty
Moving machine parts.
Hard Rock Sand and Gravel · 160155330 CFR 56.14107(a) · Significant and substantial (S&S) · $1,037.00 proposed penalty
Housekeeping.
Hard Rock Sand and Gravel · 160155330 CFR 56.20003(a) · Significant and substantial (S&S) · $1,037.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Hard Rock Sand and Gravel · 160155330 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Hard Rock Sand and Gravel · 160155330 CFR 50.30(a) · $151.00 proposed penalty
Correction of dangerous conditions.
Hard Rock Sand and Gravel · 160155330 CFR 56.12030 · Significant and substantial (S&S) · $3,448.00 proposed penalty
Regular Safety and Health Inspection
Hard Rock Sand and Gravel · 160155312.0 on-site hours reported
Site-specific hazard awareness training.
Hard Rock Sand and Gravel · 160155330 CFR 46.11(a) · Significant and substantial (S&S) · $3,832.00 proposed penalty
Protective equipment or clothing for welding, cutting, or working with molten metal.
Hard Rock Sand and Gravel · 160155330 CFR 56.15007 · Significant and substantial (S&S) · $165.00 proposed penalty
Regular Safety and Health Inspection
MMC Materials, Inc. · 22004783.0 on-site hours reported
103 (g) Written Notification Hazard Complaint Inspectio
Hard Rock Sand and Gravel · 16015531.5 on-site hours reported
Work on power circuits.
Hard Rock Sand and Gravel · 160155330 CFR 56.12017 · Significant and substantial (S&S) · $1,219.00 proposed penalty
Regular Safety and Health Inspection
MMC Materials, Inc. · 22004784.0 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.