Doe Run Company safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Temporary, portable containers.
Sweetwater Mine/Mill · 230045830 CFR 47.44(b) · $226.00 proposed penalty
Correction of hazardous conditions.
Sweetwater Mine/Mill · 230045830 CFR 57.3200 · $504.00 proposed penalty
Disorders (repeated trauma)
Fletcher Mine and Mill · 2300409Occupatnal illness not deg 1-6
Accident narrative
CARPAL TUNNEL RIGHT WRIST
Regular Safety and Health Inspection
Sweetwater Mine/Mill · 230045891.3 on-site hours reported
Inspection.
Sweetwater Mine/Mill · 230045830 CFR 57.4201(a)(2) · $226.00 proposed penalty
Inspection.
Sweetwater Mine/Mill · 230045830 CFR 57.4201(a)(2) · $226.00 proposed penalty
Non-Injury Accident Investigation
Brushy Creek Mine/Mill · 23004992.5 on-site hours reported
Identification of power switches.
Brushy Creek Mine/Mill · 230049930 CFR 57.12018 · $398.00 proposed penalty
Parking procedures for unattended equipment.
Brushy Creek Mine/Mill · 230049930 CFR 57.14207 · $151.00 proposed penalty
Protection of gas cylinder valves.
Brushy Creek Mine/Mill · 230049930 CFR 57.16006 · $151.00 proposed penalty
Impoundment Spot Inspection
Viburnum #29 Mine · 23004958.8 on-site hours reported
Berms or guardrails.
Viburnum #29 Mine · 230049530 CFR 57.9300(d) · Significant and substantial (S&S) · $366.00 proposed penalty
Escapeways and refuges.
Brushy Creek Mine/Mill · 230049930 CFR 57.11050(a) · $151.00 proposed penalty
Operators' stations.
Brushy Creek Mine/Mill · 230049930 CFR 57.14103(b) · Significant and substantial (S&S) · $592.00 proposed penalty
Escapeways and refuges.
Brushy Creek Mine/Mill · 230049930 CFR 57.11050(a) · $398.00 proposed penalty
First aid materials.
Brushy Creek Mine/Mill · 230049930 CFR 57.15001 · $177.00 proposed penalty
Prohibited areas for food and beverages.
Brushy Creek Mine/Mill · 230049930 CFR 57.20014
Exposure monitoring.
Brushy Creek Mine/Mill · 230049930 CFR 57.5002 · $177.00 proposed penalty
Combustible waste.
Brushy Creek Mine/Mill · 230049930 CFR 57.4104(a) · $151.00 proposed penalty
Protection for openings around travelways.
Brushy Creek Mine/Mill · 230049930 CFR 57.11012 · $177.00 proposed penalty
Housekeeping.
Brushy Creek Mine/Mill · 230049930 CFR 57.20003(a) · $151.00 proposed penalty
Housekeeping.
Brushy Creek Mine/Mill · 230049930 CFR 57.20003(a) · Significant and substantial (S&S) · $883.00 proposed penalty
High-pressure hose connections.
Brushy Creek Mine/Mill · 230049930 CFR 57.13021 · $151.00 proposed penalty
Impoundment Spot Inspection
Buick Mine/Mill · 23004572.5 on-site hours reported
Splices and repairs of power cables.
Brushy Creek Mine/Mill · 230049930 CFR 57.12013(b) · $398.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.