  1. Verbal Hazard Complaint Inspections

    inspectionRecord F04228A
    3805 Cone Crushing Plant 209 pit · 1002228

    12.3 on-site hours reported

  2. Exposure monitoring.

    violationRecord 5210219
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.5002 · Significant and substantial (S&S) · $288.00 proposed penalty

  3. Exposure limits for airborne contaminants.

    violationRecord 5210218
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.5001(a)/56.5005 · Significant and substantial (S&S) · $267.00 proposed penalty

  4. Exposure limits for airborne contaminants.

    violationRecord 5210217
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.5001(a)/56.5005 · Significant and substantial (S&S) · $267.00 proposed penalty

  5. Regular Safety and Health Inspection

    inspectionRecord F03BA76
    3805 Cone Crushing Plant 209 pit · 1002228

    14.5 on-site hours reported

  6. Inspection.

    violationRecord 5210208
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.4201(a)(2) · $151.00 proposed penalty

  7. Protection of power conductors from mobile equipment.

    violationRecord 5210207
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.12005 · $151.00 proposed penalty

  8. Moving machine parts.

    violationRecord 5210206
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.14107(a) · $151.00 proposed penalty

  9. Housekeeping.

    violationRecord 5210205
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.20003(a) · $151.00 proposed penalty

  10. Moving machine parts.

    violationRecord 5210204
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.14107(a) · $151.00 proposed penalty

  11. Inspection and cover plates.

    violationRecord 5210203
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.12032 · $151.00 proposed penalty

  12. Moving machine parts.

    violationRecord 5210202
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.14107(a) · $151.00 proposed penalty

  13. Roll-over protective structures (ROPS) and seat belts.

    violationRecord 5210201
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.14130(g) · Significant and substantial (S&S) · $592.00 proposed penalty

  14. Regular Safety and Health Inspection

    inspectionRecord F00D267
    3805 Cone Crushing Plant 209 pit · 1002228

    8.0 on-site hours reported

  15. Inspection.

    violationRecord 9907478
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.4201(a)(2) · $151.00 proposed penalty

  16. Notification of commencement of operations and closing of mines.

    violationRecord 9907477
    3805 Cone Crushing Plant 209 pit · 1002228

    30 CFR 56.1000 · $151.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.