Permissible electric face equipment; maintenance.
Oak Grove Mine · 010085130 CFR 75.503 · $549.00 proposed penalty
Electric equipment; examination, testing and maintenance.
Oak Grove Mine · 010085130 CFR 75.512 · Significant and substantial (S&S) · $3,184.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $697.00 proposed penalty
Slip or fall of person
Oak Grove Mine · 0100851Days away from work only
Accident narrative
IE was walking down the slope when they slipped with their left foot. As they slipped they rolled their right ankle causing a sprain.
Short circuit protection; ratings and settings of circuit breakers.
Oak Grove Mine · 010085130 CFR 75.601-1 · Significant and substantial (S&S) · $2,503.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $755.00 proposed penalty
Permissible electric face equipment; maintenance.
Oak Grove Mine · 010085130 CFR 75.503 · Significant and substantial (S&S) · $2,936.00 proposed penalty
Grounding metallic frames, casings, and other enclosures of electric equipment.
Oak Grove Mine · 010085130 CFR 75.701 · Significant and substantial (S&S) · $2,312.00 proposed penalty
Short circuit protection; ratings and settings of circuit breakers.
Oak Grove Mine · 010085130 CFR 75.601-1 · Significant and substantial (S&S) · $2,312.00 proposed penalty
Operation of diesel-powered equipment.
Oak Grove Mine · 010085130 CFR 75.1916(e) · $313.00 proposed penalty
Ventilation controls.
Oak Grove Mine · 010085130 CFR 75.333(h) · $366.00 proposed penalty
Ventilation controls.
Oak Grove Mine · 010085130 CFR 75.333(c) · $313.00 proposed penalty
Roof control plan.
Oak Grove Mine · 010085130 CFR 75.220(a)(1) · Significant and substantial (S&S) · $2,936.00 proposed penalty
Spot Inspection
Oak Grove Preparation Plant · 01003291.0 on-site hours reported
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $2,312.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $697.00 proposed penalty
Spot Inspections
Oak Grove Mine · 0100851103(i) · 3.0 on-site hours reported
Spot Inspections
Oak Grove Mine · 0100851103(i) · 4.0 on-site hours reported
Escapeways; bituminous and lignite mines.
Oak Grove Mine · 010085130 CFR 75.380(d)(7)(iv) · Significant and substantial (S&S) · $2,312.00 proposed penalty
Spot Inspections
Oak Grove Mine · 0100851103(i) · 2.5 on-site hours reported
Spot Inspections
Oak Grove Mine · 0100851103(i) · 4.5 on-site hours reported
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $755.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $755.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $755.00 proposed penalty
Escapeways; bituminous and lignite mines.
Oak Grove Mine · 010085130 CFR 75.380(d)(7)(iv) · Significant and substantial (S&S) · $2,312.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.