Ventilation controls.
Oak Grove Mine · 010085130 CFR 75.333(h) · $336.00 proposed penalty
Mine ventilation plan; submission and approval.
Oak Grove Mine · 010085130 CFR 75.370(a)(1) · $432.00 proposed penalty
Roof control plan.
Oak Grove Mine · 010085130 CFR 75.220(a)(1) · $592.00 proposed penalty
Travelways at surface installations.
Oak Grove Mine · 010085130 CFR 77.205(e) · $313.00 proposed penalty
Mechanical equipment guards.
Oak Grove Mine · 010085130 CFR 77.400(a) · Significant and substantial (S&S) · $2,312.00 proposed penalty
Mechanical equipment guards.
Oak Grove Mine · 010085130 CFR 77.400(c) · $465.00 proposed penalty
Handling of materials
Oak Grove Mine · 0100851Days away from work only
Accident narrative
IE was working with the face crew servicing the face. As they were grabbing a tube off of other tubes it fell and smashed a thumb against the rock on the rib causing a fracture.
Machinery and equipment; operation and maintenance.
Oak Grove Mine · 010085130 CFR 77.404(a) · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
Oak Grove Mine · 010085130 CFR 75.202(a) · Significant and substantial (S&S) · $2,712.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $697.00 proposed penalty
Permissible electric face equipment; maintenance.
Oak Grove Mine · 010085130 CFR 75.503 · $592.00 proposed penalty
Spot Inspections
Oak Grove Mine · 0100851103(i) · 2.0 on-site hours reported
Spot Inspections
Oak Grove Mine · 0100851103(i) · 1.5 on-site hours reported
Emergency tethers.
Oak Grove Mine · 010085130 CFR 75.1714-6 · Significant and substantial (S&S) · $5,144.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $697.00 proposed penalty
Electric equipment; examination, testing and maintenance.
Oak Grove Mine · 010085130 CFR 75.512 · $432.00 proposed penalty
Ventilation controls.
Oak Grove Mine · 010085130 CFR 75.333(c)(3) · $313.00 proposed penalty
Preshift examination at fixed intervals.
Oak Grove Mine · 010085130 CFR 75.360(g) · $592.00 proposed penalty
Spot Inspections
Oak Grove Mine · 0100851103(i) · 6.0 on-site hours reported
Spot Inspections
Oak Grove Mine · 0100851103(i) · 2.0 on-site hours reported
Protection from falls of roof, face and ribs.
Oak Grove Mine · 010085130 CFR 75.202(a) · Significant and substantial (S&S) · $2,312.00 proposed penalty
Preshift examination at fixed intervals.
Oak Grove Mine · 010085130 CFR 75.360(g) · $267.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $549.00 proposed penalty
Accumulation of combustible materials.
Oak Grove Mine · 010085130 CFR 75.400 · $549.00 proposed penalty
Hoisting
Oak Grove Mine · 0100851Accident only
Accident narrative
The #5 Escape Capsule was taken out of service after the hydraulics failed to release. It was found that there was a failure inside the hydraulic pump and it needed rebuilt.
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.