← Carmeuse Lime and Stone, Inc.

Carmeuse Lime and Stone, Inc. safety activity

MSHA violations, accident reports and inspections across the current mine portfolio.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Moving machine parts.

    violationRecord 5083681
    Underground Black River Operation · 1500062

    30 CFR 57.14107(b) · Significant and substantial (S&S) · $883.00 proposed penalty

  2. Safety defects; examination, correction and records.

    violationRecord 5083680
    Underground Black River Operation · 1500062

    30 CFR 57.14100(b) · $151.00 proposed penalty

  3. Restricted clearance.

    violationRecord 5083679
    Underground Black River Operation · 1500062

    30 CFR 57.11008 · $151.00 proposed penalty

  4. Construction and maintenance of guards.

    violationRecord 5083678
    Underground Black River Operation · 1500062

    30 CFR 57.14112(a)(1) · Significant and substantial (S&S) · $398.00 proposed penalty

  5. Inspection and cover plates.

    violationRecord 5083677
    Underground Black River Operation · 1500062

    30 CFR 57.12032 · Significant and substantial (S&S) · $267.00 proposed penalty

  6. Toilet facilities.

    violationRecord 5083675
    Underground Black River Operation · 1500062

    30 CFR 57.20008(a) · $151.00 proposed penalty

  7. Operators' stations.

    violationRecord 5083674
    Underground Black River Operation · 1500062

    30 CFR 57.14103(b) · $151.00 proposed penalty

  8. Construction and maintenance of guards.

    violationRecord 5083673
    Underground Black River Operation · 1500062

    30 CFR 57.14112(b) · Significant and substantial (S&S) · $398.00 proposed penalty

  9. Safe access.

    violationRecord 5083672
    Underground Black River Operation · 1500062

    30 CFR 57.11001 · $226.00 proposed penalty

  10. Exits for surface buildings and structures.

    violationRecord 5083671
    Underground Black River Operation · 1500062

    30 CFR 57.4530 · $151.00 proposed penalty

  11. Testing grounding systems.

    violationRecord 5083864
    Underground Black River Operation · 1500062

    30 CFR 57.12028 · $151.00 proposed penalty

  12. Moving machine parts.

    violationRecord 5083863
    Underground Black River Operation · 1500062

    30 CFR 57.14107(a) · $151.00 proposed penalty

  13. Testing grounding systems.

    violationRecord 5083862
    Underground Black River Operation · 1500062

    30 CFR 57.12028 · $151.00 proposed penalty

  14. Housekeeping.

    violationRecord 5083860
    Underground Black River Operation · 1500062

    30 CFR 57.20003(a) · $151.00 proposed penalty

  15. Battery-charging stations.

    violationRecord 5083670
    Underground Black River Operation · 1500062

    30 CFR 57.4502(c) · $151.00 proposed penalty

  16. Electrical conductors.

    violationRecord 5083669
    Underground Black River Operation · 1500062

    30 CFR 57.12004 · $151.00 proposed penalty

  17. Operators' stations.

    violationRecord 5083668
    Underground Black River Operation · 1500062

    30 CFR 57.14103(b) · $151.00 proposed penalty

  18. Regular Safety and Health Inspection

    inspectionRecord F01A3CE
    Maysville Mine · 1507101

    115.5 on-site hours reported

  19. Housekeeping.

    violationRecord 5083859
    Underground Black River Operation · 1500062

    30 CFR 57.20003(a) · $151.00 proposed penalty

  20. Testing grounding systems.

    violationRecord 5083858
    Underground Black River Operation · 1500062

    30 CFR 57.12028 · $151.00 proposed penalty

  21. Housekeeping.

    violationRecord 5083857
    Underground Black River Operation · 1500062

    30 CFR 57.20003(a) · $151.00 proposed penalty

  22. Magazine requirements.

    violationRecord 5083667
    Underground Black River Operation · 1500062

    30 CFR 57.6132(b) · $151.00 proposed penalty

  23. Stationary grinding machines.

    violationRecord 5083662
    Underground Black River Operation · 1500062

    30 CFR 57.14115(b) · $151.00 proposed penalty

  24. Safety defects; examination, correction and records.

    violationRecord 5083661
    Underground Black River Operation · 1500062

    30 CFR 57.14100(b) · $151.00 proposed penalty

  25. Regular Safety and Health Inspection

    inspectionRecord F036E4A
    Underground Black River Operation · 1500062

    104.8 on-site hours reported

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.