Safety activity
Combustible waste.
Mojave Plant & Quarry · 040003630 CFR 56.4104(b) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Mojave Plant & Quarry · 040003630 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Mojave Plant & Quarry · 040003630 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Mojave Plant & Quarry · 040003630 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Mojave Plant & Quarry · 040003630 CFR 50.30(a) · $151.00 proposed penalty
Examination of working places.
Mojave Plant & Quarry · 040003630 CFR 56.18002(b) · $151.00 proposed penalty
Newly hired experienced miner training.
Mojave Plant & Quarry · 040003630 CFR 46.6 · $168.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Mojave Plant & Quarry · 040003630 CFR 50.30(a) · $151.00 proposed penalty
Electrical conductors.
Mojave Plant & Quarry · 040003630 CFR 56.12004 · $151.00 proposed penalty
Testing grounding systems.
Mojave Plant & Quarry · 040003630 CFR 56.12028 · $177.00 proposed penalty
Construction and maintenance of guards.
Mojave Plant & Quarry · 040003630 CFR 56.14112(b) · Significant and substantial (S&S) · $1,818.00 proposed penalty
Electrical conductors.
Mojave Plant & Quarry · 040003630 CFR 56.12004 · $398.00 proposed penalty
Safety belts and lines.
Mojave Plant & Quarry · 040003630 CFR 56.15005 · Significant and substantial (S&S) · $226.00 proposed penalty
Moving machine parts.
Mojave Plant & Quarry · 040003630 CFR 56.14107(a) · Significant and substantial (S&S) · $883.00 proposed penalty
Construction and maintenance of guards.
Mojave Plant & Quarry · 040003630 CFR 56.14112(a)(1) · $151.00 proposed penalty
Insulation and fittings for power wires and cables.
Mojave Plant & Quarry · 040003630 CFR 56.12008 · $151.00 proposed penalty
Housekeeping.
Mojave Plant & Quarry · 040003630 CFR 56.20003(a) · $151.00 proposed penalty
Construction and maintenance of guards.
Mojave Plant & Quarry · 040003630 CFR 56.14112(b) · $209.00 proposed penalty
Regular Safety and Health Inspection
Mojave Plant & Quarry · 040003674.3 on-site hours reported
Guarding around lights.
Mojave Plant & Quarry · 040003630 CFR 56.12034 · $151.00 proposed penalty
Moving machine parts.
Mojave Plant & Quarry · 040003630 CFR 56.14107(a) · $151.00 proposed penalty
Other
Mojave Plant & Quarry · 0400036Injuries due to natural causes
Accident narrative
A contract truck driver was delivering Ione clay to the plant. After dumping almost all of the material from the end dump trailer. The driver climbed inside the trailer to remove some material that was stuck to the bottom of the trailer. The driver was found unconscious and unresponsive inside the trailer.
Spot Inspection
Mojave Plant & Quarry · 04000360.5 on-site hours reported
Non-Chargeable Accident Investigation
Mojave Plant & Quarry · 040003621.0 on-site hours reported
Illumination of surface working areas.
Mojave Plant & Quarry · 040003630 CFR 56.17001 · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.