Coal production
7,011,636reported short tons
ACTIVE / OPERATOR PORTFOLIO
Membership and operating status are from the latest MSHA Mines snapshot. Open a mine for its ownership history.
MINE PORTFOLIO
2025-01-01 – 2026-10-13. Active records; production reporting is not required.
Material, method and type filters apply to this table. The portfolio’s status applies to the entire page. GEM fields describe their own release, not the selected MSHA year.
| Mine | Location / type | Coal · short tons | Hours worked | Violations | Accident records | On-site inspection hours |
|---|---|---|---|---|---|---|
| Navajo Mine2900097 · Active6/8 quarters reported | San Juan, NMSurface · MSHA: Coal (Bituminous) | 7,011,636 | 1,004,061 | 23 | 4 | 473.3 |
Production and hours sum available quarterly reports. — means unavailable; zero safety records means none in the selected imported period. Ownership reflects the current MSHA record.
LOCATION
1 of 1 mine with usable MSHA coordinates. Select a marker to open a mine.
2025 Q1 – 2026 Q4
Database snapshot · 2026-10-13. All 1 mines listed under this operator were checked; 1 have reports in the available quarters. Totals use current ownership.
reported short tons
reported employee hours
production ÷ hours worked
Missing values appear as —. Totals use available reports. Tons per hour requires production and hours for the same quarters and a nonzero hours total. * Striped bars mark partial mine coverage or an incomplete quarter. See the table for coverage.
| Quarter | Coal (short tons) | Hours worked | Tons / hour | Avg. employees | Coverage |
|---|---|---|---|---|---|
| 2025 Q1 | 662,085 | 155,188 | 4.27 | 343 | 1/1 mines reporting |
| 2025 Q2 | 1,051,593 | 165,630 | 6.35 | 337 | 1/1 mines reporting |
| 2025 Q3 | 1,347,047 | 167,636 | 8.04 | 347 | 1/1 mines reporting |
| 2025 Q4 | 1,481,336 | 171,211 | 8.65 | 350 | 1/1 mines reporting |
| 2026 Q1 | 1,371,432 | 173,528 | 7.90 | 348 | 1/1 mines reporting |
| 2026 Q2 | 1,098,143 | 170,868 | 6.43 | 348 | 1/1 mines reporting |
| 2026 Q3 | — | — | — | — | No report |
| 2026 Q4 | — | — | — | — | No report |
2025-01-01 – 2026-10-13
1 significant & substantial (S&S)
0 records classified as fatality
21 of 23 violations with amounts
11 inspections · 11 with hours
Counts are published records, including contractor records. * The quarter was incomplete at the snapshot date; recent counts may rise as reports arrive. — means no reported amount or hours. Portfolio totals use current membership.
| Quarter | Violations | S&S | Proposed USD | Accident records | Fatality records | Inspections | On-site hours |
|---|---|---|---|---|---|---|---|
| 2025-Q1 | 5 | 0 | 895.00 | 1 | 0 | 1 | 3.0 |
| 2025-Q2 | 0 | 0 | — | 0 | 0 | 2 | 147.0 |
| 2025-Q3 | 9 | 0 | 2,088.00 | 0 | 0 | 1 | 4.0 |
| 2025-Q4 | 4 | 0 | 2,606.00 | 0 | 0 | 1 | 155.0 |
| 2026-Q1 | 0 | 0 | — | 1 | 0 | 0 | — |
| 2026-Q2 | 4 | 1 | 5,188.00 | 2 | 0 | 2 | 155.3 |
| 2026-Q3 | 0 | 0 | — | 0 | 0 | 3 | 9.0 |
| 2026-Q4 * | 1 | 0 | — | 0 | 0 | 1 | 0.0 |
All violations issued in the selected period. Counts combine subsections.
103 (g) Written Notification Hazard Complaint Inspectio · 0.0 on-site hours
77.502
103 (g) Written Notification Hazard Complaint Inspectio · 0.0 on-site hours
Verbal Hazard Complaint Inspections · 4.0 on-site hours
103 (g) Written Notification Hazard Complaint Inspectio · 5.0 on-site hours
HANDTOOLS (NONPOWERED) · NO DYS AWY FRM WRK,NO RSTR ACT
While cleaning out a 24-inch water valve that was filled with weeds and poly pipe shavings, employee used a with a 3-foot alignment pry bar. Employee struck EE's left ear with the narrow-pointed section of the bar. Employee received 3 stiches to repair cartilage in ear.
77.205(c) · $151.00 proposed
77.210(c) · S&S · $4,749.00 proposed
MACHINERY · DAYS AWAY FROM WORK ONLY
A hoisted dragline drag blower motor was being lowered down while suspended, the load shifted and made contact with the employee.
Non-Fatal Accident Investigation · 19.5 on-site hours
Description not reported
77.509(c) · $288.00 proposed
Regular Safety and Health Inspection · 135.8 on-site hours
SLIP OR FALL OF PERSON · DAYS AWAY FROM WORK ONLY
Employee was cleaning snow off conveyor belt walkway, after task was completed, employee removed EE's lock from Substation and proceeded to walk away from substation and slipped on an icy area twisted/fractured EE's ankle, weather conditions snowed the previous day, so the 9th was a mixture of snow and mud.
77.1101(c) · $245.00 proposed
77.1110 · $288.00 proposed
77.1110 · $1,431.00 proposed
77.1110 · $642.00 proposed
Regular Safety and Health Inspection · 155.0 on-site hours
77.1101(c) · $151.00 proposed
77.1605(b) · $193.00 proposed
77.410(c) · $151.00 proposed
77.1713(a) · $336.00 proposed
Verbal Hazard Complaint Inspections · 4.0 on-site hours
77.1110 · $432.00 proposed
MSHA Violations (issue date), Accidents (accident date), and Inspections (begin date). Snapshot 2026-10-13.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.
CFR headings link to the current Title 30 index; they are not historical legal determinations.
EIA-923 · COAL RECEIPTS
Receipts reported by power plants and terminals, matched by MSHA mine ID.
| Quarter | Short tons | Heat · Btu/lb | Sulfur % | Ash % | Delivered USD/ton | |
|---|---|---|---|---|---|---|
| 2025-Q3 * | 968,639 | 9,190 | 0.82 | 20.30 | 66.06 | |
| 2025-Q4 | 1,392,390 | 8,931 | 0.87 | 21.13 | 64.99 | |
| 2026-Q1 | 1,203,660 | 9,020 | 0.89 | 20.85 | 66.72 | |
| 2026-Q2 | 1,055,856 | 9,029 | 0.91 | 21.40 | 59.80 | |
| 2026-Q3 * | 443,144 | 9,032 | 0.81 | 21.50 | 66.93 |
| Month / source | Mine | Receiving plant / supplier | Short tons | Delivered USD/ton | Heat · Btu/lb | Sulfur % | Ash % | Purchase | Transport |
|---|---|---|---|---|---|---|---|---|---|
| 2026-07EIA row 11702 · preliminary | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 443,144 | 66.93 | 9,032 | 0.81 | 21.50 | ContractBIT | Truck |
| 2026-06EIA row 9804 · preliminary | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 520,973 | 65.44 | 9,034 | 0.90 | 21.40 | ContractBIT | Truck |
| 2026-05EIA row 7974 · preliminary | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 329,519 | 46.80 | 9,028 | 0.90 | 21.40 | ContractBIT | Truck |
| 2026-04EIA row 6149 · preliminary | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 205,364 | 66.37 | 9,017 | 0.93 | 21.40 | ContractBIT | Truck |
| 2026-03EIA row 4339 · preliminary | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 347,913 | 67.03 | 9,152 | 0.93 | 20.40 | ContractBIT | Truck |
| 2026-02EIA row 2381 · preliminary | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 339,398 | 66.69 | 8,984 | 0.90 | 21.10 | ContractBIT | Truck |
| 2026-01EIA row 392 · preliminary | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 516,349 | 66.54 | 8,955 | 0.85 | 21.00 | ContractBIT | Truck |
| 2025-12EIA row 34281 · final | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 499,978 | 65.68 | 8,950 | 0.88 | 21.10 | ContractBIT | Truck |
| 2025-11EIA row 31291 · final | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 449,618 | 65.11 | 8,985 | 0.83 | 20.90 | ContractBIT | Truck |
| 2025-10EIA row 28340 · final | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 442,794 | 64.09 | 8,855 | 0.89 | 21.40 | ContractBIT | Truck |
| 2025-09EIA row 25267 · final | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 469,695 | 66.24 | 9,190 | 0.82 | 20.30 | ContractBIT | Truck |
| 2025-08EIA row 22117 · final | NAVAJO MINE2900097 | Four Corners2442 · NM · BHP BILLITON MARKETING | 498,944 | 65.89 | 9,190 | 0.82 | 20.30 | ContractBIT | Truck |
Delivered cost includes transport and is not mine revenue. Missing prices remain blank. * Fewer than three months are published in the selected quarter. Receipts reflect the months EIA has published; an unfinished quarter is not comparable with a full quarter. Portfolio matches use current ownership.
Imported releases start 2008-01. This window includes 12 published months. EIA releases · Survey instructions
EIA ANNUAL COAL REPORT · 2024
Annual county prices and a production-based allocation of county coal sales.
The estimate assumes each eligible mine receives its county-average price and shares county sales in proportion to production. Actual sales and prices can differ substantially. Unavailable estimates are excluded; this is not a total for the whole portfolio. Annual price data uses a separate window from the MSHA charts.
| Mine / county | Annual production · tons | County FOB · USD/ton | Est. sales · tons | Est. coal revenue · USD | Basis / availability |
|---|---|---|---|---|---|
| Navajo Mine2900097 · San Juan, New Mexico | 4,759,297 | — | — | — | County sales or price not published1 eligible mines / 1 sales respondents |
Sales-reporting threshold: 50,000 short tons per mine in 2024. Withheld sales or prices stay unavailable.
EIA Table 30 · county sales and FOB prices · EIA annual mine production · Release index
Annual report released November 19, 2025. Method: county-sales-allocation-v1. JSON and CSV preserve source row numbers and file checksums.