Best Lime Manufacturing safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Electrical conductors.
Best Lime Manufacturing · 230254930 CFR 56.12004
Electrical conductors.
Best Lime Manufacturing · 230254930 CFR 56.12004
Spot Inspection
Best Lime Manufacturing · 23025493.5 on-site hours reported
Spot Inspection
Best Lime Manufacturing · 23025490.8 on-site hours reported
Inspection and cover plates.
Best Lime Manufacturing · 230254930 CFR 56.12032 · $165.00 proposed penalty
Written safety program.
Best Lime Manufacturing · 230254930 CFR 56.23002(a) · $151.00 proposed penalty
Construction and maintenance of ladders.
Best Lime Manufacturing · 230254930 CFR 56.11003 · Significant and substantial (S&S) · $1,219.00 proposed penalty
Electrical conductors.
Best Lime Manufacturing · 230254930 CFR 56.12004 · $642.00 proposed penalty
Horns and backup alarms.
Best Lime Manufacturing · 230254930 CFR 56.14132(a) · $549.00 proposed penalty
Housekeeping.
Best Lime Manufacturing · 230254930 CFR 56.20003(a) · Significant and substantial (S&S) · $818.00 proposed penalty
Regular Safety and Health Inspection
Best Lime Manufacturing · 230254934.3 on-site hours reported
Moving machine parts.
Best Lime Manufacturing · 230254930 CFR 56.14107(a) · $549.00 proposed penalty
Testing grounding systems.
Best Lime Manufacturing · 230254930 CFR 56.12028 · $549.00 proposed penalty
General requirements.
Best Lime Manufacturing · 230254930 CFR 56.4200(b)(1) · $245.00 proposed penalty
Horns and backup alarms.
Best Lime Manufacturing · 230254930 CFR 56.14132(a) · $549.00 proposed penalty
Safety defects; examination, correction and records.
Best Lime Manufacturing · 230254930 CFR 56.14100(b) · $2,133.00 proposed penalty
Safety defects; examination, correction and records.
Best Lime Manufacturing · 230254930 CFR 56.14100(a) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Electric substations and liquid storage facilities.
Best Lime Manufacturing · 230254930 CFR 56.4130(b) · $151.00 proposed penalty
Electrical conductors.
Best Lime Manufacturing · 230254930 CFR 56.12004 · $151.00 proposed penalty
Protection of gas cylinder valves.
Best Lime Manufacturing · 230254930 CFR 56.16006 · $151.00 proposed penalty
Electrical conductors.
Best Lime Manufacturing · 230254930 CFR 56.12004 · $151.00 proposed penalty
Regular Safety and Health Inspection
Best Lime Manufacturing · 23025498.3 on-site hours reported
Moving machine parts.
Best Lime Manufacturing · 230254930 CFR 56.14107(a) · $432.00 proposed penalty
Housekeeping.
Best Lime Manufacturing · 230254930 CFR 56.20003(a) · $193.00 proposed penalty
Safety defects; examination, correction and records.
Best Lime Manufacturing · 230254930 CFR 56.14100(b) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.